Welcome to awslagi.com – Sharing AWS, Anthropic, Google Cloud, Microsoft Azure IT Exams. It's free for all!

PMI Agile Certified Practitioner

Become a specialized agile expert with the PMI Agile Certified Practitioner.

4.8★★★★★(321 ratings)
20,675 studentsBeginner
Master the widest range of agile methodologies, including Scrum, Kanban, Lean, and XP. This course validates your ability to lead agile teams and deliver value in a fast-paced, iterative environment. Gain expertise in stakeholder engagement, adaptive planning, and continuous improvement. Become a vital asset in any modern organization by mastering the agile mindset and practices.

What you'll learn

  • Agile Mindset & Principles
  • - Value-driven delivery
  • - Adaptive planning
  • - Team performance & Empowerment
  • - Problem detection & Resolution

PMI-ACP

Lectures3
Questions168
Duration30 week
Students20,675

$20.00

Full Free Question Bank (168 Questions)

PMI Agile Certified Practitioner (PMI-ACP) Practice Questions & Verified Answers

Click any option to test your knowledge, or reveal the verified answer and detailed explanation below each question.

Jump to Section:
Question #1Part 1

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations. What should the team do to improve the accuracy of their estimates?

ADecrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
BDiscuss estimating techniques in the daily scrum meeting
CIncrease the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
DBegin tracking estimated effort metrics as an input to performance evaluation
Question #2Part 1

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals. What should the scrum master do next?

AAlert the team that sprint goals might not be met and create an alternative plan
BObtain team buy-in to perform modifications to the sprint backlog
CHave the sprint proceed as planned
DAsk the team to decide if the task should be reassigned
Question #3Part 1

During the iteration planning of a newly on boarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks need to implement the user stories?

ASelf-organize
BAssign tasks to each team member
CMeet with the customer
DIdentify the scrum master
Question #4Part 1

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B. What should the agile practitioner do?

ADefer starting the design of item B until the second iteration is being planned
BProceed with the design of item B, since it will hasten the second iteration
CEscalate the issue to the customer, and obtain their approval before starting the design of item B
DLog the issue in the risk register, and request change control board (CCB) approval.
Question #5Part 1

An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released. What should the agile team do?

ADemand frequent product reviews by the product owner
BContinuously work with the product owner to do backlog refinement and product reviews
CHave the product owner provide detailed requirement specifications to ensure the proper features are delivered
DDuring the planning session, ensure the team is committed to deliver within the specifications
Question #6Part 1

During iteration planning, it was determined that an epic should be decomposed. What was the determining factor?

ASize and priority
BMinimum marketable features
CRelease plan
DSprint mapping
Question #7Part 1

What should a scrum master do when one team member falls behind in their tasks?

AMove the task to another team member who has spare capacity in the sprint
BAsk the team for suggestions
CPrivately offer the team member encouragement to meet task commitments
DNotify the product owner
Question #8Part 1

A newly formed scrum team wants to foster an environment for transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?

AKaizen
BSpecific, measurable, assignable, realistic, and time-based (SMART) goals
CKey performance indicators (KPIs)
DMuda
Question #9Part 1

A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate. What should be the agile project leader do?

ABring up the new member's impediments at the next meeting to demonstrate team support of input
BAssure the new member that inputs on impediments are valued, and demonstrate this at the next meeting
CHave a senior leader work with the new member to avoid a negative impact on team productivity
DPrivately work with the new member to address any impediments
Question #10Part 1

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?

AAsk the lead developer to identify a solution, and then share the details with the team
BAsk a technical manager or architect to determine a solution to the problem
CWork with the product owner to add a spike to the next sprint to identify a solution
DCreate a collaborative team environment so that the team can explore a solution together
Question #11Part 1

A new team member asks what changes could accelerate a change to the project plan. What should be the proper response?

ACompetitors joined forces with the team
BThe customer changed requirements
CProject team members obtained additional certifications
DTechnology which did not interfere with the final product
Question #12Part 1

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

ARaise an impediment that resource tasks will be blocked and notify the product owner
BAsk the delivery manager for a temporary resource
CAsk the scrum master to assign that team member's tasks to the next available resource
DAssume the team member's tasks to meet iteration goals, and notify the product owner
Question #13Part 1

An agile practitioner wants to ensure that stakeholders have current information about a project's progress. What should the agile practitioner do?

ARegularly circulate an updated, detailed version of the project plan
BFrequently update the online project management office (PMO) repository site
CInvite the stakeholders to daily stand ups
DPost a project board in an area where all can view it
Question #14Part 1

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams. What strategy should be employed to re-organize the teams?

AAll the teams from both products should be simultaneously called together and allowed to completely self-manage
BTeams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
CAfter grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role
DFeatures should be prioritized and then teams should be organized around those priorities
Question #15Part 1

A client states that a product is not being built as requested. How should the agile team address this?

AConduct an internal review to validate functionality before shipping
BAudit the quality control process to ensure that the product adheres to requirements
CLengthen iterations to ensure there is sufficient time to build functionality
DHold product review sessions with the client to obtain product acceptance
Question #16Part 1

A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features. What should the product owner do?

ADetermine the required tasks for implementing the high-level features
BIdentify the detailed design for the high-level features
CPrioritize the product backlog for the upcoming release
DEstimate the user stories in the iteration backlog
Question #17Part 1

An agile practitioner wants to communicate the effect of technical debt on the project. What should the practitioner do?

APost and discuss rises in the burn down chart
BAdjust story points to account for technical debt
CLog technical debt as an impediment
DAdd refactoring tasks to all stories
Question #18Part 1

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release. What should the agile coach do?

AMeet with the agile team lead to discuss ways to improve the team velocity and get back on track
BUse this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins
CIn the upcoming retrospective, discuss ways to improve sharing project status information
DMeet with the marketing stakeholders to explain that the team will miss the planned release date
Question #19Part 1

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach. What should the agile practitioner do?

AAsk the opinion of key stakeholders and the client to ensure the correct approach is being used
BWork with the team to use this approach, and request a quality assurance iteration after every three iterations
CPropose to completely eliminate test automation, since this is a quality assurance function
DSuggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and redundancy
Question #20Part 1

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

ACollect stakeholder requirements
BConduct an iteration planning meeting
CCommunicate product backlog items to the stakeholders
DFacilitate a product development roadmap workshop
Question #21Part 1

What should an agile practitioner do to ensure that the end product meets business requirements?

AInvite the team to iteration review meetings
BObtain agreement from the product owner on business requirements
CRequest that regular reports are sent to stakeholders
DConfirm managers and stakeholders are invited to product review meetings
Question #22Part 1

Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

AThe team neglected to account for support and maintenance costs associated with other support products
BThe team discovered that previously accepted work could be greatly improved and added story points associated with that work
CThe team realized that some stories were underestimated relative to other stories and re-estimated as needed
DThe team learned that the product owner needed to increase the output in the next release
Question #23Part 1

A technical problem arises that will likely impact the stories planned for delivery in the current sprint. What should the scrum master do?

AConsider adding a story to the next sprint to seek resolution
BImmediately solve the problem on behalf of the team
CAsk the team to collaboratively work out a solution
DEngage a technical manager to assist with finding a solution
Question #24Part 1

How should an agile project leader interact with the product owner?

AConduct regular one-on-one meetings to review development features and trace them back to the product roadmap
BEnsure the they attend regular sprint meetings to provide product-feature feedback
CShare any new versions of the project plan with them, including updated statuses for tasks and project milestones
DSchedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints
Question #25Part 1

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled. What should the team have done to avoid this?

AEscalated the issue to management
BEnsured the early engagement of key stakeholders
CProvided feedback to the architecture team to change the enterprise architecture standards
DRaised an exception for non-adherence to the enterprise architecture standards for this product
Question #26Part 1

A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations. What agile practice can help the team to alleviate this?

ATest-driven development (TDD)
BClear definition of done and regular demos
CCollaborative team planning games
DConsistent team velocity
Question #27Part 1

A team member on a scrum project previously provided support to another application. Due to this with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes these issues in the risk register. What should the scrum master do next?

AMonitor the threats and risks while allowing the team member to multitask on both projects
BAssign more resources to the sprints to compensate for the absence of the team member
CEnsure that the threats and risks are communicated and addressed
DAssign fewer stories to the sprints so that the team member can still meet sprint goals
Question #28Part 1

An organization initiates a pilot project to introduce agile methodology for the successful delivery of projects. What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

AInvite people from across the organization to attend daily stand ups
BInvite people from across the organization to attend retrospectives
CInvite people from across the organization to attend the release meeting and project retrospectives
DRegularly meet with people across the organization to share the project's lessons learned and best practices
Question #29Part 1

A project team identifies a number of technical challenges with features in the next sprint. What should they do?

ARequest direction from the technical manager
BEncourage that product owner to reallocate the features to another sprint
CDetermine who is best qualified to address the challenges
DAsk the product owner to assign the tasks to the most appropriately skilled resources
Question #30Part 1

The team is refining user stories during the backlog grooming session and confused on the acceptance criteria and level of details. What should the agile practitioner do?

AComplete the test cases before creating the story in the backlog
BDefine the detailed business requirements so that the team can continue with development
CDefine the user stories with just enough details so the team can collaborate continuously
DEnsure the acceptance criteria includes testing scenarios, so the team can do through testing
Question #31Part 1

When prioritizing features to be delivered in an iteration, on what should an agile team defer work?

AHigh-risk and high-value
BHigh-risk and low-value
CLow-risk and low-value
DLow-risk and high value
Question #32Part 1

On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product. How should this be addressed?

AReview the iteration goals and have the team each describe the work to create shared understanding
BCreate a story map for the minimal viable product (MVP) functionality
CCapture this as a task in the retrospective and ensure there is more details provided at the next planning session
DHave the product owner explain the product vision and review the release plan with the team
Question #33Part 1

The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?

ADiscuss the efficiency at the next iteration retrospective
BReview the process value stream to determine potential improvements
CReview the value the customer receives from the user story to determine backlog priority
DDiscuss the performance of the solution at the next sprint review
Question #34Part 1

A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time. What type of behaviour does this describe?

ASynchronous
BCollaborative
CPassive-aggressive
DRandom
Question #35Part 1

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release. What should the team do?

AConduct frequent demos and obtain feedback from users throughout the development of the next release
BInform senior management that since the product was successfully released, the project is considered delivered and should be closed
CRequest additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity
DImplement a better definition of done to ensure that continuous integration processes are managed effectively
Question #36Part 1

A team using Kanban identifies that their cycle time has significant variation. After brainstorming, the team determines that the root cause is the stories' varying sizes and risks. What should the team do?

AReduce work in progress (WIP) limits to accommodate slack for riskier stories
BCreate a triage step on the Kanban board to pre-identify risky stories
CSet a policy to break down stories larger than a specified complexity, then adjust the WIP
DCreate a dedicated overflow swim lane on the Kanban board for stories that are too large
Question #37Part 1

Two similar stories, A and B, are estimated at 3 story points. Story C, estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C. What should the agile practitioner do?

AAssign story B more than 8 story points so to provide a better estimate
BAdd points to story B's iteration to account for the error but keep story B at 3 points
CAssign more resources to story B to bring it in line with the estimate
DRe-estimate all stories including values for A, B and C
Question #38Part 1

The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business. What should the product owner have done differently?

ADemonstrated only the completed stories and seek stakeholder feedback
BPresented the budget situation and review the cost variance
CReviewed the test results to gain confidence from the stakeholders
DPresented a demo of all the stories including the work in progress stories
Question #39Part 1

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

AAdd risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints
BAdd risk mitigation time to each requirement
CApply the 80/20 rule, reserving 20 percent of each sprint's capacity for risk mitigation
DHold all risks until they become issues, then add issue resolution tasks to the product backlog
Question #40Part 1

What should a team do when they complete all sprint goals earlier than expected?

ABegin working on an item in the backlog
BAsk the scrum master to select an item from the backlog on which to work
CAsk the product owner to select an item from the backlog on which to work
DJointly decide with the scrum master on an item from the backlog on which to work
Question #41Part 1

A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?

AEngage the team to determine the sprint velocity based on previous agile projects
BAverage the sprint velocity based on input from team members
CShare the sprint velocity obtained from the sponsor with the team
DRun multiple sprints before determining the sprint velocity with the team
Question #42Part 1

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to complete in the market place. What analysis should the team use to understand the issues?

ARisk management
BVariance and trend
CKano model
DFishbone-diagram
Question #43Part 1

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?

ATerminate the project to cut losses
BReview possible options and make an informed decision to cut losses based on delivered business value
CBring in experts to increase the probability of success
DContinue the project, release the product without the failing feature, and fix the feature in a subsequent release
Question #44Part 1

An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours which affects team performance. What should the agile coach do to mitigate this issue?

ASpeak with the functional managers and come to an agreement that will resolve the issue
BExplain to functional managers that too much control will inversely impact team morale
CMeet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue
DInform the team there will be penalties to anyone who visits that business during working hours
Question #45Part 1

After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?

APrioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI
BReplace some team embers to reduce the release costs and minimize a negative ROI
CPerform a root-cause analysis to remove waste from the delivery process and increase the ROI
DCommunicate the risk of a negative ROI to the stakeholders, and update the release plan
Question #46Part 1

During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identify the iteration's remaining scope?

AConvince the team to stop planning and keep the size small
BIdentify the technically minimal and achievable tasks
CRefer to the remaining prioritized backlog items
DSelect some of the smallest items from the backlog
Question #47Part 1

During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends the discussion. This causes a team member to withdraw from future collaboration. How could the project leader have avoided this?

ALed by example by encouraging the team to engage in consensus-driven decision making
BIterated the need for agile teams to make quick decisions, then followed up with that team member
CEmpowered a team member to facilitate decision making, then made a final decision on behalf of the team
DRefrained from participating in the team's decision-making process, except to document and communicate results
Question #48Part 1

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization. What should the project leader do?

AEncourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies
BEncourage the team to continue with the current plan, do what they can, and carry forward the work not done to the next iteration
CEnsure the team captures the technical dependencies as issues within the backlog optimization
DEnsure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization
Question #49Part 1

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date. What should the project leader do?

AFinalize the feedback in the form of a change request
BLimit the scope of the feedback to only those changes that the team can feasibly accommodate
CEncourage all feedback, then work with the customer to prioritize work for future sprints
DAllow the team to decide what feedback to incorporate
Question #50Part 1

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

AAmount of work needed to complete a single user story
BAmount of work that can be accomplished by each team member
CAmount of work that can be accomplished in an iteration
DAmount of work that can be accomplished by the entire team
Question #51Part 1

Why should a project team reduce the work in progress?

AIt indicates poor project quality
BIt represents team member's utilization
CIt represents unrealized value
DIt shows that the project is behind schedule
Question #52Part 1

During a review session, a customer representative is concerned that a story fails to satisfy the scope of work. However, the product owner declares that the scope of work is complete. What should be done with this story?

AMark it as incomplete and prioritize it for the next sprint
BMark it as complete, since the product owner has the final say
CDiscard it and create a new story for the remaining scope of work
DMark it as complete, since the team completed the scope of work
Question #53Part 1

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project. How should the agile practitioner explain to senior management the benefits of this approach?

AIt ensures a consistent level of detail is available in the project schedule
BIt prevents a wasteful build-up of requirements inventory that may never be processes
CIt provides a concrete definition of product scope, cost and duration
DIt allows the team to lock down the stories to be included in a release
Question #54Part 1

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules. How should the team lead address this?

AInform management, and suggest that additional resources may be required
BDiscuss the issue with the team in the daily stand up meetings
CMeet personally with the stressed team member to brainstorm ways to better manage their time
DBegin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting
Question #55Part 1

A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?

AProvide both project teams with the highest priority needs
BRequest the project team's questions in writing prior to the next meeting
CFacilitate a meeting with each team and the product owner to finds a solution
DProvide both teams with each project's documentation
Question #56Part 1

A seven-member agile team's composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

ANetworking
BSocial awareness
CCommunication
DLeadership
Question #57Part 1

Due to its complexity, a new team member struggles with developing a concise user story. What advice should the agile practitioner give to assist with developing the story?

AHand the story over to a more experienced team member
BBreak the story up and focus on the most valuable parts
CDiscuss the story at the retrospective
DPick another story from the product backlog
Question #58Part 1

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this. What should the agile practitioner do?

AJointly meet with the team and product owner to discuss options and determine the end date
BAnnounce that the team has exceeded the predicted velocity, and that the end date will be earlier than planned
CAsk the product owner to include additional features in the product backlog, then re-plan subsequent iterations
DAsk the team to decrease velocity to meet contractual obligations and document this decision
Question #59Part 1

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks. What should the scrum master do?

ATell the technical lead to do the testing
BFacilitate an open and focused team discussion that reinforces team agreements
CAsk the team manager to advise the technical lead that all tasks are important
DEncourage the team to take ownership of the delivery
Question #60Part 1

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project. What should the product owner do next?

AObtain approval from the change control board to discontinue the component
BAsk the team to continue developing the component
CAsk the team to discontinue developing the component
DRequest the sponsor's formal approval to discontinue the component
Question #61Part 2

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity. What should the team do?

AEstimate only functional requirements that will impact product quality
BAdd team resources
CRefer the issue tot eh product owner
DBreak non-functional requirements into those that can be delivered in the given sprint
Question #62Part 2

A development team and product owner disagrees on a user story in the product backlog. What should the agile practitioner do?

AHave the development team follow the product owner's direction
BOpenly challenge the product owner in the effort to poke holes in their approach
CFacilitate a conversation about the user story between the development team and the product owner
DServe as a nonpartisan evaluator of each option, and provide direction to the development team and product owner
Question #63Part 2

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?

AThe story should be assigned eight story points as per the majority vote
BThe story should be added to the backlog and reassessed later
CThe story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
DThe decision for the number of story points should be made by the customer
Question #64Part 2

A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge. What should the agile practitioner do?

ASelect and implement collaboration tools to augment team interactions
BProvide each geographical area with their own product owner and divide the work between the teams
CIncrease the number of requirements documents and ensure they are clearly communicated
DAfter several sprints, calculate velocity based on primary team location and use secondary team as reserve
Question #65Part 2

Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal. What should the agile team do?

ACreate a central repository for information, and provide access to team B
BUse an information board that will be visible to all passing through the workspace
CEmail all stakeholders with status updates
DProvide team B with the information on an ג€as neededג€ basis
Question #66Part 2

Chart Base on the burn down chart, what is the iteration's status?

AIt trended ahead of scheduled and completed everything on time
BIt took more time than expected and had to be lengthened
CIt trended behind schedule and did not complete everything on time
DIt took less time than expected and had to be shortened
Question #67Part 2

During planning sessions, an agile practitioner notices that some team members do not share common ideas. What should the agile practitioner do?

AAsk the team if they would like to adopt alternative techniques
BCreate a team norms document to set particular guidelines
CAsk the scrum master to resolve the issue at the stand up meeting
DCapture feedback during lessons learned at the end of the iteration
Question #68Part 2

More details for a story are required before the upcoming sprint planning meeting. What should the scrum master do?

AEmail the product owner requesting detailed story specifications and wait for a response
BGather the details from the team members before sprint planning
CSchedule a story grooming session with the product owner before sprint planning
DConduct a planning poker session with the team
Question #69Part 2

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective. What should the agile practitioner do?

AReview established ground rules with the team
BAsk team members specific questions to identify the cause
CEncourage the team to continue working to maintain the iteration's schedule
DMeet with the product owner and stakeholders to discuss the issue
Question #70Part 2

A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high. When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

ACalculated planned percent complete (PPC)
BMany small minimally marketable features (MMFs)
CStory points rather than cost estimates
DCalculated earned value (EV)
Question #71Part 2

While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck. What should the scrum team do?

AFor upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories
BHave QA team members with the appropriate skill sets spend extra to help the team succeed
CEnsure that QA team members who lack the appropriate skill up for training within the next few weeks
DAsk QA team members experienced with the new automation framework to cross-train the other QA members
Question #72Part 2

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features. What should the team member do?

AInfluence the customer
BMention the idea at the next retrospective
CShow the customer how much time and money would be saved
DPresent the idea at the next ceremony attended by stakeholders to obtain their input
Question #73Part 2

During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories. What should the team do?

ACross-train some members in the automation framework to broaden their capacity with that skill
BAsk the product owner to add team members to boost this particular skill set
CSend a member to automation framework training when funds are available
DAvoid using test automation by swarming on the testing tasks and using manual testing
Question #74Part 2

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer. How should the team resolve this?

ARefer to the values of the agile framework and the team
BReview the signed customer contract
CCheck the sprint priority list
DSubmit the problem to the product owner
Question #75Part 2

A project team realizes that an important task on the iteration backlog will take more time than originally estimated. What should the project team do?

AContinue working on the task until it is completed
BRemove the task owner from the project team
CAdd resources to reduce time to task completion
DStop working on the task and include it in the next iteration
Question #76Part 2

An executive sponsor of a new scrum team actively attends scrum ceremonies. How does this benefit the team?

AIt helps the team to focus on and meet sprint goals
BIt reminds the team about who sponsors the project
CIt provides high-level project updates to the sponsor
DIt helps to quickly resolve issues using the sponsor/s influence
Question #77Part 2

A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope. What should the scrum master do?

AMeet with the team to gain alignment with the legal department's need to stay within the contracted time and scope
BWork with the customer to narrow the scope
CShare the project's trajectory with the legal department
DMeet with the legal department to help them understand that the customer and the team are satisfied with the time and deliveries
Question #78Part 2

An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses. What can happen as a result?

AThe team will be unable to understand the iteration's status
BThe team will be unable to judge the project design's validity
CThe team cannot give accurate updates to management
DTeam collaboration cannot be measured effectively
Question #79Part 2

A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated. What should the Scrum Master do?

APoint out that the team chose to work on other requirements to speed up the project
BEnsure that the product owner reviews the contents of the information radiator
CEnsure that the next sprint planning meeting reviews the satisfaction histogram
DPoint out that it is the responsibility of the product owner to clarify requirements
Question #80Part 2

During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested. What should the agile practitioner do?

AWork with the agile team and product owner to agree on the definition of done
BAsk the sponsor to determine whether the product is completed
CPlan another review after the product has been tested
DAdd testing to the backlog, and have the product owner reprioritize
Question #81Part 2

During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint. What should the product owner do next?

ACreate a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer
BCreate a user story for this new improvement and prioritize it for the next sprint
CDocument it as a requirement creep
DAsk the team to take on additional story points to improve the UI
Question #82Part 2

A company is moving into a new space and is determining the best configuration for offices. The management team is also considering moving to an agile process. What should an agilest give?

AArrange the office space to allow co-location of development teams and centrally located information radiators
BIsolate each development team to reduce all outside distractions
CEnsure management understands the need for isolation to allow for concentration
DDefine the agile method the company will be using and implement the office configuration based upon that method
Question #83Part 2

An agile team member identifies a potential problem within the project team. How should the team's coach react?

ADocument the problem, escalate to the project manager, and develop a solution for the team
BAdd the problem to the backlog and assign resolution to a future iteration
CInstruct the team to try to solve the problem within the team
DPerform root cause analysis and report the problem to the product owner
Question #84Part 2

Stakeholders are displeased with the latest release of a product's software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction?

ACommunicated early and often, as outlined in the communications matrix
BEnsured engagement among stakeholders and the product owner
CConducted additional stakeholder reviews and demos
DWorked with the product owner to prioritize user stories
Question #85Part 2

An agile project manager notices that the product manager manages team member's day-to-day tasks in a way that distracts them from their core responsibilities. In addition, the team believes that their questions on product backlog prioritization are not being answered on time. What should the agile practitioner do?

ADiscuss and address this in the iteration retrospective
BLet the product owner know it is the project manager's responsibility to drive a ream's tasks
CDiscuss the roles and responsibilities of the project team with the product owner
DAsk the product owner to work extra hours to answer the team's questions
Question #86Part 2

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the scrum master do?

ADismiss the team member
BDiscuss the situation with the functional manager
CReport the functional manager to the project sponsor
DDemand that the functional manager respect the project charter
Question #87Part 2

During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework. To help the team gain confidence, what should the agile practitioner suggest?

ADevelop a spike
BCreate an Ishikawa diagram
CPerform a pre-mortem analysis
DComplete a variance and trend analysis
Question #88Part 2

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration. What must the agile practitioner do?

AAdd the new change request as a new user story in the product backlog for the upcoming iteration
BEvaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
CRecommend cancelling the current iteration and plan the change request into the next iteration
DRecommend that the product owner add this change request as a user story to the backlog for the current iteration
Question #89Part 2

During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet most pressing needs and provide value. What should the team have done to prevent this?

AReprioritized requirements prior to committing to iteration work
BEnsured that requirements remained stable during the iteration cycle
CHad stakeholders focus on items created after the product backlog was initially built
DWorked on features rather than a set of components
Question #90Part 2

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work and to rely on outside specialists is impacting team velocity. What should the agile team lead do?

ASend the member to training
BAsk the outside specialists if database administration is required from the team
CSend one member to training only after asking the team if there is an issue with the current work flow
DWait until all members of the team can attend training
Question #91Part 2

What role should a servant leader perform to reduce team distractions and improve progress toward project goals?

AManaging: To ensure compliance with the project plan
BMentoring: To share their knowledge with the team
CControlling: To ensure compliance with the scope, budget, and schedule
DAuditing: To ensure adherence to organizational compliance policies
Question #92Part 2

During a retrospective meeting, a team develops a large list of initiatives. All will have a positive impact and improve team performance. What should the agile coach do next?

APositively acknowledge the list and share it with management
BImmediately have the team implement the initiatives
CHelp the team choose one or two initiatives for immediate implementation
DAsk the team to choose and implement the most complex initiative
Question #93Part 2

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

ARemove the second half of the backlog, and communicate their decision in the next backlog grooming meeting
BReprioritize backlog items to future iterations
CWork with the team to deploy the first half of the backlog to ensure that value is realized
DMeet with project stakeholders to review backlog and determine if the scope should be adjusted
Question #94Part 2

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them. What should have been done to avoid this?

AA comprehensive user story with all non-functional requirements should have been created
BNon-functional requirements should have been added to the acceptance criteria
CNon-functional requirements should have been added to the definition of done
DA team review of the scope of work should have been conducted
Question #95Part 2

Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope. What should the team do?

AWork on requirements that the product owner may have overlooked
BRecord the scope creep in the change management log
CAdd the new requirement to the product backlog
DAsk the scrum master to secure additional time and resources
Question #96Part 2

A product owner, new to the role, is very enthusiastic about an agile project with an energetic team. What should be done first to ensure successful delivery of the product?

AHold a meeting with the team and the product owner to develop the team charter, working agreement, guiding principles, and product vision
BAsk the product owner to create the project vision and charter, and then discuss the guiding principles with the team
CHold a meeting during which the team can present the project charter, high-level project plan, and team values to the product owner
DSend the product owner to format product owner training where the product owner can learn how to create a product vision
Question #97Part 2

During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach. What should the scrum master do?

ADiscourage the team member from deviating from the plan and document the request during the retrospective
BEncourage the team member to research the issue and present the findings during the retrospective
CDiscourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases
DEncourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important
Question #98Part 2

The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

ACommit to a specific feature set for delivery
BExplain that a commitment will be provided after planning
CHave the team estimate in story points to commit to a specific set of features
DUse the team's historical velocity to calculate a range of features that can be delivered
Question #99Part 2

A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project. What should the project leader suggest?

ADevelop and document a detailed architectural design, peer review with the development team, and implement/test
BDevelop the functional requirements of the solution first before any non-functional requirement, as they provide more customer value
CDiscuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature
DDevelop and test the implementation approach and demonstrate it at the next sprint review to collect feedback
Question #100Part 2

During a retrospective, the agile practitioner discovers that a team member's process improvement idea has worsened the outcome. What should the agile practitioner do?

ACommend the team on trying the idea, then encourage discussion regarding alternatives
BAsk a manager to direct the team on fixing the process
CEncourage the team to continue executing the idea to see if it improves
DPrivately speak with the team member to convey that their idea worsened the outcome
Question #101Part 2

Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?

ANote the changes to the restructure and roles that affect team activities
BUse direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
CEmail a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project
DObtain a copy of the redefined key roles to update the stakeholder analysis
Question #102Part 2

A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution. What should the project leader do?

AAssign the spike to another resource to continue research for the long-term solution
BRe-estimate the spike, encourage experimentation and collaborate with the team
CStop experimentation and negotiate the short-term solution with the customer
DSchedule a root-cause analysis with the development team on the main issues with the spike
Question #103Part 2

An agile team notices that the same problems continue to occur during multiple iterations. Several team members have suggestions to fix the problem. What is the proper agile approach to handle this?

AHold frequent retrospectives and share the responsibility for making changes
BUnderstand that this is the nature of innovative business and strive to work harder
CCollect team member feedback and discuss them privately with the product owner
DConduct a team-building exercise to increase trust among the team members
Question #104Part 2

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered. What should the agile team do?

AEvaluate how much can be delivered based on the Scrum Master's estimation
BIdentify a set of user stories based on the team's velocity
CInitiate an estimation session
DConsult historical data for project completion
Question #105Part 2

An agile team is planning the next iteration for a product release that has accumulated technical debt. What should the team do?

AAdd code cleanup activities to the product backlog and request prioritization by the product owner
BAdd code cleanup activities to the next iteration and request clarification from the product owner
CAdd code cleanup activities to the next iteration and ask the product owner to end the current iteration
DAdd code cleanup activities to the next release backlog and request documentation from the product owner
Question #106Part 2

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to measure performance?

ALead time, throughput, and due date performance
BWork in progress limits, Kanban board, and time boxes
CWork item types, sprint cadences, and defect classes
DBurndown charts, scatter diagrams, and throughput
Question #107Part 2

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans. What should the agile practitioner do?

AProvide all information requested by the stakeholder
BSet expectations regarding the appropriate level of details requested during this stage
CInform the stakeholder that no detailed documents are provided using agile practices
DAsk the team to supply the information to the stakeholder
Question #108Part 2

A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals. What should the scrum master mention at the next retrospective?

ASolutions to project problems that were built into the last sprint
BProblems that arose
CSolutions that saved the organizations the most time and money
DProblems that were solved
Question #109Part 2

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?

ASchedule regular meetings with the scrum team to write, groom, and size user stories
BFocus on stores based on the highest number of story points to first address those items with the highest value
CSeek regular input from project stakeholders, and reflect this input in the backlog's priorities
DSchedule in-person, monthly meetings with key stakeholders to review the project's progress
Question #110Part 2

A team identifies the number of threats and lists them in the order in which they were identified. After analyzing a cause-and effect diagram, the ownership of the threats and their treatment is assigned, and a number of risk cards are placed on the Kanban board. What approach should be used to manage these threats?

ACreate a risk register detailing the threats, their causes, and their treatment strategies, and complete ownership to provide together risk control and a stakeholder
BFocus on the threats during the daily stand up and ensure they are visible to the entire team and other interested parties
CPrioritize the risks based on their criticality and timing, and track actions to closure
DEnsure that the prioritization of threats is complete, and that ownership actions are assigned and visible to everyone
Question #111Part 2

During product development, changes in technology and regulations require the team to reassess product architecture. How should this technical debt be captured?

AInclude it in the product backlog and use a new indicator to annotate that is technical debt
BInclude it in the product backlog as a low-priority issue
CSince it is not a part of agile methodologies, it should not be tracked
DHave team members maintain personal lists of issues and consolidate the lists during review
Question #112Part 2

The agile team disagrees with the business stakeholders on completing some epics. What could help eliminate misunderstandings?

AAgree on requirements with all stakeholders
BBegin planning every four iterations
CConsider previous sprint demo feedback when planning the next sprint
DInclude the reasons for the project in the contract
Question #113Part 2

A customer and a product delivery team meet to discuss a product's attributes, goals, expectations, hypothesis, and high-level needs. What is a benefit of this meeting?

AThe team will learn how its contribution will create product value
BIt will enable team acceptance of client priorities
CIt will enable the team to see the entire project in one glance
DIt will enable the team to ask any questions to the customer upfront
Question #114Part 2

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents. How should the agile practitioner address this concern?

AEducate the QA manager that in agile, quality is integrated from the beginning to end of the project
BWrite backlog items that include QA as part of the description
CAsk for the current QA documents and incorporate them into the technical debt backlog
DAsk the product owner to write tests and QA controls into the acceptance criteria
Question #115Part 2

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments. What should the agile coach do?

AWork with the sponsor to develop team expectations
BProvide the customer with a list of deliverables and obtain agreement
CEncourage the team to more frequently interact with all stakeholders
DWork on finishing upfront product design rather than comprehensive documentation
Question #116Part 2

During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks, which has lowered motivation. What should the agile practitioner do?

AOrganize a team-building activity to improve team morale
BHave team members work in pairs to learn from each other and develop new skills
CAsk team members to perform a value stream analysis of their activities
DAdd more resources to the team to help with tasks
Question #117Part 2

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope, the team plans to work only on spike user stories for the next three sprints. What should an agile coach do in this situation?

AEnsure that the spikes identify the risks early in the project to increase the chances of success
BEnsure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints
CRecommend that, in the first sprint, user stones with higher priority be executed in addition to the spike
DSupport the decision, because release planning will be improved, and the product backlog can be better groomed after all spikes are executed
Question #118Part 2

How can an agile team working on a new product ensure alignment with external stakeholders?

AAsk the product owner to provide a detailed product specification document
BConduct story-mapping exercises to clarify deliverables and release priorities
CHold a kick-off meeting to assign roles and responsibilities
DWork with the scrum master and stakeholders to ensure agile principles are followed
Question #119Part 2

What can an agile team use to prioritize stories?

APlanning poker technique
BWeighted average calculation
CRisk-value quadrant
DINVEST scale
Question #120Part 2

During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing. What should the scrum master do?

AAsk the tester and developer to discuss it after the meeting, since it is not a part of the daily stand up
BEncourage the discussion to resolve impediments
CAfter the meeting, escalate this issue to the tester's supervisor to ensure that this does not reoccur
DAsk more questions about the testing techniques to obtain clarification on team efforts for quality improvements
Question #121Part 3

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

AInvited end customers to attend the stand ups
BOrganized design review sessions with the customer to obtain sign-off
CHeld regular meetings with the product owner and project team to elicit detailed business requirements
DConducted frequent review meetings with the customer to continually enhance delivery effectiveness
Question #122Part 3

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

AEstablish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis
BEstablish and keep an active risk register based on qualitative risk analysis and expected losses
CHave each development team post the highest risk development items on the information radiator
DAvoid risk by splitting development teams into two locations to ensure knowledge continuity
Question #123Part 3

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth. What should the team do?

AInform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings
BStay focused on the current iteration and let the project manager deal with the regional sales manager's questions
CInvite the regional sales manager to the next iteration review to share the progress
DCreate a risk on the risk register to account for some potentially new requirements from the regional sales manager
Question #124Part 3

What should a team consider when calculating the effort needed to complete a product backlog?

AThe increase in velocity and cost
BA buffer in the sprint to mitigate unexpected risks
CAssigning extra points to each task to allow time for changes
DStories describing infrastructure tasks and analysis tasks
Question #125Part 3

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have assumed a sprint duration of 2 weeks. What can an agile practitioner conclude about team A and team B's estimate?

ATeam B has underestimated scope compared to team A
BTeam A is more confident in delivering velocity than team B
CBoth teams need to indicate their proposed technology before the estimates can be analyzed
DBoth teams have estimated the project to be of same size
Question #126Part 3

Throughout the project, an agile practitioner notices that one team member is becoming an emergent leader. What should an agile practitioner do?

APresent opportunities in order to be supportive and grow that team member's talents
BEncourage the team member to fit in more with the established team norms
CBring this to management's attention so they don't disrupt the team
DAsk team member to respect defined roles on the project to avoid confusion with the team
Question #127Part 3

A product's scope and acceptance criteria have been detailed, and the product is planned for release at the end of the next quarter. What should the project team do next?

AEstimate the project team's capacity
BDetermine how much work can be delivered
CCalculate how much work will fit into the next iteration
DEstimate items in the product backlog
Question #128Part 3

At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity. How should the project team address this issue?

ASuggest pair programming during the retrospective
BAsk the product owner to re-prioritize the user stories at the next retrospective
CRe-estimate the story points with team members at the next iteration planning meeting
DAssign less complex user stories to the inexperienced software engineer at the next iteration planning meeting
Question #129Part 3

How should a project leader manage stakeholder expectations in an agile project?

AEstablish a common vision and success criteria and involve all the stakeholders in the iteration reviews
BInvite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success
CInvolve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders
DCommunicate issues to all stakeholders via email and only communicate risks to internal stakeholders
Question #130Part 3

A scrum master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum master use to provide these updates?

AShared vision statement and sprint goal
BRelease burnup chart
CVelocity metrics
DIteration burndown chart
Question #131Part 3

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met. If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

AStakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk
BThe team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions
CInterdependent teams should have been engaged using a collaborative approach to identify and leverage the best support
DAn owner should have been identified to obtain timely stakeholder feedback
Question #132Part 3

During a project's last few sprints, an agile practitioner notices an increase in defects. A rootcause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly. What should the agile practitioner do?

AInform the product owner's manager so that corrective action may be taken
BCommunicate this to the product owner, and offer to help facilitate discussion with the team
CEncourage a team member to raise this during the retrospective to ensure that the product owner is aware
DEscalate this issue to the sponsor so that corrective action may be taken
Question #133Part 3

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throught the project?

AInclude security concerns on the agenda for every meeting
BRequest that a security expert be added to the team
CAdd security as a non-functional requirement to the risk register, and review regularly
DEnsure that planning and prioritizing includes consideration of security requirements
Question #134Part 3

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

ALog the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting
BCreate a spike story to determine what needs to be done to use the new interface
CLower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings
DMove the work to the vendor, since they have better knowledge of interface implementation
Question #135Part 3

A project sponsor is upset that an enhancement will be unavailable until next year. What should the product owner do?

AAccept responsibility for the product's delay
BEnsure that the project sponsor's priorities are in the product backlog
CNegotiate with the project sponsor for increased funding
DEmpower the project sponsor to manage the product backlog
Question #136Part 3

An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?

AEscalate the issue to the project sponsor
BRemove stories to increase velocity
CHold a standup to address the issue
DFacilitate a team retrospective
Question #137Part 3

During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the scrum master do?

AEncourage all team members to participate, and have them type their retrospective feedback into the agile lifecycle management tool
BAsk more specific questions during the retrospectives
CSue retrospective techniques, such as silent writing, clustering, and dot voting to field feedback prior to discussion by the team
DAsk team members to email feedback that can be summarized in a spreadsheet for the team
Question #138Part 3

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

ACoach the product owner to update only the acceptance criteria
BInstruct the agile team to fix the user stories during the next retrospective
CFacilitate a user story workshop with the agile team
DInform the product owner's manager that the work items provide insufficient details
Question #139Part 3

Following an upgrade, a software support team is overwhelmed by the number of tickets being submitted by end users. The team's manager is pushing the team to work smart by focusing on activities that deliver the most value in the least amount of time. What should the team do?

AWork longer hours to complete more of the support backlog
BWork support tickets in the order in which they were received
CPlace tickets on hold until the team completes an analysis of the backlog to identify and resolve systematic issues
DAdd members to the support team
Question #140Part 3

What should the agile practitioner know about tracking velocity?

AA team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25
BA team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25
CA team that consistently meets its planned velocity is more efficient that a team that consistently exceeds its planned velocity
DA team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity
Question #141Part 3

During a Kanban team's daily stand-up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to ream effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight. What should the agile coach do?

AWork with the team to determine points at which to celebrate its work
BProvide the team with a break by scheduling a team event
CHave the team increase work in progress (WIP) levels to more quickly complete the flow
DRejuvenate the team by temporarily reducing WIP levels
Question #142Part 3

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

ARequested approval from the project sponsor
BUndertaken a review of all requirements
CConducted an end-of-phase demonstration
DPerformed a retrospective to validate project deliverables
Question #143Part 3

A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team. What should the team do next?

AUse agile estimation techniques to create a shared understanding of when the user stories will be completed
BAgree upon development and testing activities for the user stories
CComplete the user stories, and provide a demo for the product owner and customer
DComplete the user stories, and hold a retrospective to discuss them
Question #144Part 3

An agile team has been in place for five years and the customer is satisfied with the team's performance and deliverables. Now that the product is built and delivered, the customer is considering the future role of the Scrum Master. What should the customer do?

AExpand the Scrum Master's role to other projects, while allowing them to support the current project
BRelease the Scrum Master, since the team is adequately skilled with agile practices
CExpand the product owner's role to serve as the Scrum Master, while providing additional product knowledge
DIncrease the functional manager's role to act as the Scrum Master, while providing additional information about functional areas
Question #145Part 3

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

ASuggest the product owner start by focusing on the next 2 sprints instead of 10
BSpend the first few sprints to develop detailed schedules and budgets
CInvite the product owner to the retrospective to explain the team's approach to schedule and budget
DExplain that detailed project schedules and budgets are not artefacts in agile projects
Question #146Part 3

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action. What should the team do?

ACollaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed
BAsk the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase the capacity
CFocus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans
DReestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations
Question #147Part 3

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

AAdvise the product owner that the story will have to wait until the next sprint
BWork extra hours to complete the story and satisfy the customer's requirements
CBreak down the story into smaller increments and negotiate other stories on the sprint backlog
DIncrease the length of the sprint to accommodate the story
Question #148Part 3

A senior team member feels underutilized. What should the agile practitioner do?

ATransfer the senior member to another team that will more fully utilize their skill set
BConduct a performance evaluation to determine whether or not this member is a team player
CEncourage the project team to involve the senior member in more project activities
DAsk the functional manager to determine the best course of action
Question #149Part 3

A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup. What should the Scrum Master do?

AAsk the product owner how upper management's comments can be redirected
BDirect the developer team to ignore the phone calls and emails
CAsk the product owner to enter the requests into the product backlog as high priority
DPersonally respond to upper management's phone calls and emails
Question #150Part 3

What estimation technique is an agile team using when collectively estimating the relative size of its stories using story points?

AParametric
BOne-to-one comparison
CAffinity
DPlanning poker
Question #151Part 3

The product owner wants to build security firewalls into the product. How can the team members support this?

AAdd new security features to the backlog and prioritize
BExecute a spike to research security features for the project
CAsk questions to determine where and how the product owner wants to use product
DAsk questions to determine if the product owner can define the desired level of security
Question #152Part 3

An agile practitioner becomes a Scrum Master on an established Scrum team. After introductions, what should the agile practitioner do?

ACoach team members to improve functional specialties and increase overall velocity
BIdentify where team processes misalign with accepted Scrum practices
CFacilitate the identification of problems or issues and help the team resolve them
DReview the backlog to ensure that it is prioritized, refined, and properly tasked
Question #153Part 3

A key stakeholder cannot attend the project vision statement development workshop. The stakeholder has emailed their requirements to the agile team lead, and believes that the vision statement is not critical. How should the agile team lead respond?

AEmphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project
BPersonally meet with the stakeholder to understand their requirements, and then share the vision with the team
CWork with the team to create a vision from the stakeholder's supplied requirements
DExplain to the team that creating a vision is not critical in agile projects, as requirements may change over time
Question #154Part 3

During a daily stand up meeting, a developer expresses concerns that the selected technology limits the number of concurrent users. What should the agile team do?

AAsk the team to conduct research to find a viable solution
BSelect a better technology for team implementation
CObtain customer input on their technology requirements
DConsult the product owner about their non-functional requirements
Question #155Part 3

A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only for generic user's perspective. This may lead the team to miss stories for non-generic users. What agile tools can help the team address these issues?

AInformation radiators and wireframes
BInformation radiators and story maps
CProcess flows and personas
DPersonas and extreme characters
Question #156Part 3

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

AThe iteration is in jeopardy
BThe team has removed scope
CThe iteration is ahead of schedule
DThe team's velocity is constant
Question #157Part 3

The amount of information captured in the project's defects is varying within the development team. Team members are becoming frustrated with the defect quality inconsistencies and the frequent clarification required. What should be done to address the issue?

AStop the current iteration to discuss defect quality issues and explore solutions
BDiscuss and explore solutions in the next planning meeting and take corrective actions as required
CGenerate insights at the next retrospective and adjust processes as decided by the team
DAssign corrective actions to the backlog for the team to identify the mandatory defect information
Question #158Part 3

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with feature. The team conducted a retrospective and reviewed the user stories related it. What should the agile team do next?

AEnsure that the product owner reviews the acceptance criteria for delivered user stories
BAugment the quality assurance and continuous integration processes for delivery
CApproach the relevant developers and testers regarding quality issues, in upcoming iterations
DAsk the product owner to define the entire scope of delivery two to three iterations in advance
Question #159Part 3

A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?

AWork with the customers to build the product backlog and identify their initial requirements
BMeet with the stakeholders and enterprise architects to understand the project's vision
CPlan and execute a sprint 0 to establish the project's foundational needs
DCreate a backlog, and execute a sprint 1 to quickly deliver value to the customers
Question #160Part 3

A development team, new to scrum, questions the need to collect metrics on team performance. While team members understand velocity and burn down, they feel that once velocity becomes settled it is needless to keep track. What should the agile coach tell the team?

AContinuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate
BThe trends will show how the team performs against other scrum teams in the organization
CTracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working
DTracking velocity will document and communicate team health to the stakeholders
Question #161Part 3

A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company. What should the agile coach ensure that developers do?

AEstablish pair programming partners, and regularly perform peer reviews
BPerform demos at the end of each iteration
CSend coding to the quality assurance (QA) team upon completion
DDemonstrate each feature to the client as soon as coding is complete
Question #162Part 3

During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal. What practice is the agile facilitator implementing?

ABuilding openness and transparency on the project's health and status
BFacilitating conflict resolution among executive team members
CUsing active stakeholder involvement to build features in an increment and iterative approach
DSeeking continuous feedback from executive team members
Question #163Part 3

What can a team use to prioritize stories?

AMoSCoW method
BPlanning poker technique
CWeighted average calculation
DINVEST scale
Question #164Part 3

Business stakeholders of an agile project frequently skip the review meetings. What should the agile practitioner do?

AAsk the product owner to inform all stakeholders about the project's progress
BSend meeting notes to all stakeholders after each review meeting
CInclude the results of the review meetings in the information radiators
DConvince the stakeholders of the benefits of attending the review meetings
Question #165Part 3

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings. What should the product owner do to resolve this?

AAsk the development team to address the issue since it is in their domain
BReview the project's risk matrix, and follow the steps outlined in the risk mitigation plan
CMeet with the team and stakeholders to address rework and rewrite stories as needed
DCancel the current sprint, and meet with stakeholders to reassess the project's validity
Question #166Part 3

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories. What should be proposed to the team?

AHave other team developers attend training to learn database skills
BMonitor the retrospectives of two additional sprints before taking action
CPlan fewer stories for the sprint to reduce the database engineer's workload
DAsk the scrum master to work the product owner to remove backlog stories that have database dependency
Question #167Part 3

An agile project has three more iterations before the release. There is lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports. What should the project leader do?

AEncourage the team to self-organize and determine how to best complete their existing work and this spike
BEncourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal
CDirect the team to defer the spike until the next release and add the action on the backlog for prioritization
DDirect the team to work on the spike immediately given the importance of reporting functionality to complete the iteration
Question #168Part 3

While attending a conference, an agile practitioner learns of a new user interface (UI) framework that could benefit the team. What should the agile practitioner do next?

AIdentify a team member to do a proof of concept using this framework
BEmail the team directing them to immediately begin using this new framework
CObtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it
DDiscuss this option at the next retrospective

📢 Unlock Full Access to Success!

"The content displayed here is a promotional preview and contains only 50% of the actual exam database. To access the complete set of updated questions, please upgrade to the Full Version."

👉 Click the button and follow the instructions to secure your full access immediately!