Gain foundational knowledge of project management terms, processes, and tools. This associate-level certification is designed for students and entry-level professionals who want to demonstrate their high-level understanding of project execution. Master the basics of the PMBOK Guide and how to support project teams effectively. Build the confidence to pursue more advanced certifications like PMP as your experience grows.

What you'll learn

  • Project Management fundamentals
  • - PMBOK Guide processes
  • - Predictive & Agile methodologies
  • - Business analysis basics
  • - Project communication & documentation

CAPM

Lectures4
Questions239
Duration30 week
Students18,107

$20.00

Full Free Question Bank (239 Questions)

Certified Associate in Project Management (PMI-100) (CAPM) Practice Questions & Verified Answers

Click any option to test your knowledge, or reveal the verified answer and detailed explanation below each question.

Jump to Section:
Question #1Part 1

Once the make-or-buy analysis is completed, which document defines the project delivery method?

AProcurement statement of work (SOW)
BProcurement strategy
CTerms of reference
DChange request
Question #2Part 1

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

AThe project manager should identify and deal with stakeholders only during the execution phase.
BStakeholder satisfaction should be identified immediately and managed as a project objective.
CThe project manager should focus on project objectives and deal with stakeholders as a secondary priority.
DStakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Question #3Part 1

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

AHybrid methodologies
BRisk register updates
COutsourced project resources
DReliance on lessons learned documents
Question #4Part 1

What should a project manager use to determine how much money is needed to complete a project?

AEarned value management (EVM)
BEstimate at completion (EAC)
CEarned value analysis (EVA)
DBudget at completion (BAC)
Question #5Part 1

The project manager is creating the communications management plan. Which group of inputs is required to begin?

AWork performance reports, change requests, and risk register
BWork performance data, project documents, and stakeholder engagement plan
CProject charter, project management plan, and project documents
DWork performance data, stakeholder register, and team management plan
Question #6Part 1

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

Acreate the project management plan.
Bidentify the project objectives.
Creview and update stakeholder engagement.
Dcreate the schedule baseline.
Question #7Part 1

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A8
B18
C36
D40
Question #8Part 1

A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?

AReview stakeholder register and meeting
BData analysis and communication skills
CData gathering and data analysis
DCommunication skills and cultural awareness
Question #9Part 1Select 3

Select three processes that are associated with Project Schedule Management? (Choose three.)

ADefine Activities
BPlan Resource Management
CEstimate Activity Durations
DDevelop Schedule
EAcquire Resources
Question #10Part 1

What are the project management processes associated with project quality management?

APlan Quality Management, Manage Quality, and Control Quality
BPlan Quality Management, Manage Quality, and Cost of Quality
CManage Quality, Customer Satisfaction, and Control Quality
DCustomer Satisfaction, Control Quality, and Continuous Improvement
Question #11Part 1

In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with charges?

AHaving control over the planning and delivery of the products without delegating decisions
BGiving access to information to the team and frequent team checkpoints
CSelecting different team members to take the project manager role during reviews with stakeholders
DAsking the control change board to approve changes before notifying the team
Question #12Part 1

The activity of tailoring is necessary because:

Athe members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide; this is required for all projects.
Beach project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
Cthe members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.
Deach project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide.
Question #13Part 1

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:

ADevelop Schedule
BDefine Activities
CDefine Scope
DCollect Requirements
Question #14Part 1

Which of the following tasks focuses on decomposing work packages?

AAdjust duration estimates
BDefine activities
CComplete rolling wave planning
DDevelop milestone list
Question #15Part 1

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

AInitiating
BPlanning
CExecuting
DMonitoring and Controlling
Question #16Part 1

Given the following information: ✑ Activity A takes one week. ✑ Activity B takes three weeks. ✑ Activity C takes two weeks. ✑ Activity D takes five weeks. ✑ Activity A starts at the same time as Activity B. ✑ Activity C follows Activity B and Activity A. ✑ Activity D follows Activity C. How long will it take to complete the project?

A8 weeks
B9 weeks
C10 weeks
D11 weeks
Question #17Part 1

Which is an example of analogous estimating?

AEstimates are created by individuals or groups with specialized knowledge.
BEstimates are created by using information about resources of previous similar projects.
CEstimates are created by analyzing data.
DEstimates are created at the task level and aggregated upwards.
Question #18Part 1

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

ASuppliers
BCustomers
CGoverning bodies
DProject team
Question #19Part 1

Which document can help a project manager to leverage historical project information?

ALessons learned register
BSchedule baseline
CWork performance data
DDeliverable acceptance forms
Question #20Part 1

Which kind of communication should the project manager use when creating reports for government bodies?

AHierarchical
BExternal
CFormal
DOfficial
Question #21Part 1

Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

AIncreased support and minimized resistance from stakeholders
BIncreased performance of the project team
CMaintenance of stakeholder satisfaction because costs and scope are under control
DUpdated project documents, as requested by stakeholders
Question #22Part 1

How can a project manager evaluate project team development?

AProduce team performance assessments
BHold weekly meetings to engage every member
CComplete a personal skill assessment on each team member
DProvide recognition awards to team members
Question #23Part 1

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element. What are these elements called?

AProject activities
BWork packages
CPlanning packages
DProject deliverables
Question #24Part 1

Which tools and techniques will a project manager use to develop a project charter?

AProject manager experience, expert judgment, scope statement, and meetings
BLessons learned database, interpersonal and team skills, cost baseline, and meetings
CExpert judgment, data gathering, scope statement, schedule baseline, and meetings
DExpert judgment, data gathering, interpersonal and team skills, and meetings
Question #25Part 1

Which key benefit can a project manager obtain by identifying stakeholders?

AIdentify the appropriate focus for engagement of each stakeholder
BAssess the risk exposure for each stakeholder
CMap stakeholder power and influence grid
DIdentify the appropriate channels of communication with all stakeholders
Question #26Part 1

The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?

AAccepted deliverables
BPlanning packages
CVerified deliverables
DWork packages
Question #27Part 1

Which are the most important competencies required for a project manager?

ALeadership, bilingualism, experience, and technical knowledge
BPMP certification, experience, technical knowledge, and post-graduate education
CLeadership, strategic and business management, project management knowledge, and technical knowledge
DCommunication skills, project management knowledge, PMP certification, and availability to travel
Question #28Part 1

Which is the correct hierarchy in a project environment, from most to least inclusive?

AProjects, portfolios, then programs
BPortfolios, programs, then projects
CPortfolios, projects, then programs
DProjects, programs, then portfolios
Question #29Part 1

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem. Which technique should the project manager use?

AWithdraw/Avoid
BSmooth/Accommodate
CCompromise/Reconcile
DCollaborate/Problem Solve
Question #30Part 1

Which process determines the correctness of deliverables?

AVerify Deliverables
BValidate Deliverables
CReview Deliverables
DAnalyze Deliverables
Question #31Part 1

Why is tailoring required in a project?

ABecause a one-size-fits-all approach avoids complications and saves time
BBecause every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required
CBecause tailoring allows us to identify the techniques, procedures, and system practices used by those in the project
DProject managers should apply every process in the PMBOK Guide to the project, so tailoring is not required
Question #32Part 1

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

AInternal enterprise environmental factor
BRisk register database
CExternal enterprise environmental factor
DOrganizational process asset
Question #33Part 1

Which of the following documents are created as part of Project Integration Management?

AProject charter and project management plan
BCommunications management plan and scope management plan
CQuality management plan and risk management plan
DProject scope statement and communications management plan
Question #34Part 1

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?

AThree-point estimating
BParametric estimating
CBottom-up estimating
DData analysis
Question #35Part 1

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI's Talent Triangle best relates to this need to improve?

AStrategic and business management skills
BLeadership skills
CTechnical project management
DOrganizational management
Question #36Part 1

Which project documents can determine the budget?

AProcurement documents, contracts, requirements documentation, and basis of estimates
BBasis of estimates, cost estimates, project schedule, and risk register
CBusiness case, project charter, statement of work, and cost estimates
DScope baseline, resource management plan, activity list, and assumption log
Question #37Part 1

When managing costs in an agile environment, what should a project manager consider?

ALightweight estimation methods can be used as changes arise
BAgile environments make cost aggregation more difficult
CAgile environments make projects more costly and uncertain
DDetailed cost calculations benefit from frequent changes
Question #38Part 1

Which statement describes the Monitor Communications process?

AEvaluates the differences between the communications management plan and the reality of communications in a project
BEnsures that the information needs of the project and the stakeholders are met
CEnsures that project information is created, collected, and distributed in a timely and appropriate manner
DDevelops an appropriate and plan for communication of project activities
Question #39Part 1

Which tasks should a project manager accomplish in order to manage project scope correctly?

ADefine, Validate, and Control Scope; Control Schedule; Control Costs and Manage Stakeholder Engagement.
BCollect Requirements, Define Scope, Create WBS, Develop Schedule, and Manage Stakeholder Engagement.
CPlan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS.
DDefine, Validate, and Control Scope; Control Costs; Manage Stakeholder Engagement; and keep budget under control.
Question #40Part 1

In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

AUse a lightweight cost estimation due to the nature of agile projects
BUse a detailed cost estimation for agile projects
CRetrieve a budget from a previous project and create a baseline for this project based on it
DUse a detailed work breakdown structure (WBS) to get cost estimation
Question #41Part 1

Which of the following lists represents the outputs of the Monitor Communications process?

AProject communications, project management plan updates, project documents updates, and organizational process assets updates
BWork performance information, change requests, project management plan updates, and project documents updates
CCommunications management plan, project management plan updates, work performance report, and project documents update
DStakeholder engagement plan, change requests, project management plan updates, and project documents updates
Question #42Part 1

A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

ABottom-up estimating
BThree-point estimating
CAnalogous estimating
DParametric estimating
Question #43Part 1

Which are inputs for the Plan Quality Management process?

AQuality metrics, project documents, and financial performance
BQuality management plan, project documents, and quality metrics
CProject management plan, project documents, and organizational process assets
DProject management plan, quality metrics, and project documents
Question #44Part 1

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

AExpert judgment
BInterpersonal skills
CTeam agreements
DCommunication skills
Question #45Part 1

The project manager has the following information about the estimated duration for an activity: ✑ Most likely [tM] " 15 days ✑ Pessimistic [tP] " 20 days ✑ Optimistic [tO] `" 10 days What is the estimated duration of this activity, according to the triangular distribution technique?

A10 days
B15 days
C12.5 days
D5 days
Question #46Part 1

Which is a major component of an agreement?

AChange request handling
BRisk register templates
CLessons learned register
DProcurement management plan
Question #47Part 1

Which statement is related to the project manager's sphere of influence at the organizational level?

AA project manager interacts with other project managers to detect common interests and impacts their projects.
BA project manager facilitates communication between the suppliers and contractors on the project.
CA project manager considers the current industry trends and evaluates how they can impact or be applied to the project.
DA project manager may inform other professionals about the value of project management.
Question #48Part 1

What process group establishes project scope, refines objectives, and defines the actions necessary to attain project objectives?

AExecuting
BPlanning
CInitiating
DMonitoring and Controlling
Question #49Part 1

Which are examples of processes that may be used once or at predefined points in the project life cycle?

ADevelop Project Charter and Close Project or Phase
BDefine Activities and Acquire Resources
CControl Schedule and Conduct Procurements
DMonitor Communications and Control Costs
Question #50Part 1

After defining activities in project schedule management, which processes should a project manager follow?

ASequence Activities and Estimate Activity Durations
BEstimate Activity Durations and Control Schedule
CDevelop Schedule and Control Schedule
DReview Activities and Develop Schedule
Question #51Part 1

Which of the following tasks is related to the Perform Qualitative Risk Analysis process?

AIdentify the project risks and assign a probability of occurrence
BPerform a sensitivity analysis to determine which risk has the most potential for impacting the project
CAnalyze the effect of identified project risks as numerical data
DPrioritize each protect risk and assign the probability of occurrence and impact for each one
Question #52Part 1

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should the project manager consult?

ARisk management plan
BCommunications management plan
CChange management plan
DStakeholder engagement plan
Question #53Part 1

During what project management process does the project team begin identifying risks?

AInitiating
BPlanning
CExecuting
DMonitoring and Controlling
Question #54Part 1

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

AMonitor and Control Project Work
BDirect and Manage Project Work
CClose Project or Phase
DPerform Integrated Change Control
Question #55Part 1

Which format can a network diagram take?

AFlow chart
BControl chart
CAffinity diagram
DCause-and-effect diagram
Question #56Part 1

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

AStakeholder engagement plan and organizational process assets
BProject schedule and stakeholder register
CQuality management plan and risk register
DBasis of estimates and scope baseline
Question #57Part 1

According to the PMI Talent Triangle, leadership skills relate to the ability to:

Aunderstand the high-level overview of the organization
Btailor traditional and agile tools for the project
Cwork with stakeholders to develop an appropriate project delivery
Dguide, motivate, and direct a team to reach project goals
Question #58Part 1

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

APost project artifacts in a transparent fashion and engage stakeholders on a regular basis.
BMake surveys among the stakeholders and meet with the team once a month.
CCreate a social network and post news there.
DCreate personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.
Question #59Part 1

A project manager is assigned to a strategic project. Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project. Which entities will the project manager attempt to influence?

AThe project and the organization
BThe organization and the industry
CThe subject matter experts and the project
DThe change control board and the organization
Question #60Part 1

Which statement summarizes the role of the change control board?

AThe change control board is responsible for presenting the change for approval
BThe change control board will analyze the change impact in terms of cost and schedule
CThe change control board is responsible for managing the change management and configuration management systems
DThe change control board is responsible for reviewing and approving changes to the project
Question #61Part 2

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex. Which strategies should the project manager take into account for risk management in this environment?

AOccasionally identify, evaluate, and classify risks
BReview requirements and cross-functional project teams
CInclude contingency reserves and update the project management plan frequently
DFrequently review incremental work products and update the requirements for proper prioritization
Question #62Part 2

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

AProject charter, business documents, and project management plan
BAgreements, scope baseline, and project management plan
CProject charter, business case, and project management plan
DWork performance data, enterprise environmental factors, and project management plan
Question #63Part 2

How should a project manager plan communications for a project which has uncertain requirements?

AInclude stakeholders in project meetings and reviews, use frequent checkpoints, and co-locate team members only.
BInvite customers to sprint planning and retrospective meetings, update the team quickly and on a daily basis, and use official communication channels.
CAdopt social networking to engage stakeholders, issue frequent and short messages, and use informal communication channels.
DAdopt a strong change control board process, establish focal points for main subjects, and promote formal and transparent communication.
Question #64Part 2

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

AProject scope statement and accepted deliverables
BScope baseline and project documents update
CAccepted deliverables and enterprise environmental factors
DScope baseline and work performance information
Question #65Part 2

Which statement about identification and engagement of stakeholders during a project is correct?

AProject stakeholders should be identified and engaged in every phase of the project to influence the success of the project directly.
BProject stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
CProject stakeholders should be identified when the project charter is being completed and engaged during requirements gathering.
DProject stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process
Question #66Part 2

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

ADefining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
BThe detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
CAn iterative scheduling and on-demand, pull-based scheduling will be required.
DTo address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
Question #67Part 2

Which task will a project manager undertake while conducting Project Resource Management?

AIdentify the different aspects of the team to manage and control physical resources efficiently
BProcure equipment, materials, facilities, and infrastructure for the project
CTrain the team members in project skill sets
DDefine the roles and responsibilities of each team member
Question #68Part 2

Which is an example of an internal enterprise environmental factor?

AMarket share brand recognition
BFactory location
CLocal government regulation
DIndustry research
Question #69Part 2

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because it is a foreign location. Which type of life cycle would the project manager use in this case?

APredictive life cycle
BWaterfall life cycle
CHybrid life cycle
DProduct life cycle
Question #70Part 2

What are the two most common contract types used in a project?

ACost plus award fee (CPAF) contract and fixed price contract
BFixed price contract and cost-reimbursable contract
CCost-reimbursable contract and time and material (T&M) contract
DTime and material (T&M) contract and cost plus award fee (CPAF) contract
Question #71Part 2

If you established a contingency reserve including time, money, and resources, how are you handling risk?

AAccepting
BTransferring
CAvoiding
DMitigating
Question #72Part 2

Which are required to create the schedule management plan?

AScope baseline, work breakdown structure (WBS), estimated costs, and milestone list
BResource management plan, organizational process assets, activity list, and business case
CEnterprise environmental factors, organizational process assets, project charter, and project management plan
DActivity list, project statement of work, project charter, and communications management plan
Question #73Part 2

Which factors should be considered for cross-cultural communication?

ABackground, personality, and communications management plan
BPersonality, background, and escalation process
CSponsor relationship, personality, and background
DCurrent emotional state, personality, and background
Question #74Part 2

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

AWork performance information
BBidder conferences
CComplexity of procurement
DProcurement management plan
Question #75Part 2

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

AThe risk management plan and the assumption log
BCosts estimates and cost forecasts
CThe risk management plan and the basis of estimates
DThe assumption log and the project charter
Question #76Part 2

What is one of the main purposes of the project charter?

AFormal authorization of the existence of the project
BFormal acceptance of the project management plan
CFormal approval of the detailed project budget
DFormal definition of stakeholder roles and responsibilities
Question #77Part 2

Tailoring considerations for project scope management may include:

Arequirements management, stability of requirements, development approach, and validation and control.
BWBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.
Cbusiness needs, product descriptions, project restrictions, and project management plan.
Dissues defining and controlling what is included in the project, verified deliverables, and quality reports.
Question #78Part 2

Which of the following is a category of organizational process assets?

AGovernment standards
BOrganizational culture
CEmployee capabilities
DOrganizational knowledge bases
Question #79Part 2

To which knowledge area does the Collect Requirements process belong?

AQuality Management
BScope Management
CCost Management
DIntegration Management
Question #80Part 2

Which of the following can a project manager use to represent defined team member roles in a group of tasks?

AWork breakdown structure (WBS)
BResponsibility assignment matrix (RAM)
COrganizational breakdown structure (OBS)
DResource breakdown structure (RBS)
Question #81Part 2

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

AMonitor project stakeholder relationships using engaging strategies and plans
BSend all project documents to stakeholders each time they are modified
CSchedule monthly meetings with the stakeholders, including team members
DEngage only with the project sponsors
Question #82Part 2

Which are the competing constraints that a project manager should address when tailoring a project?

ACost, scope, schedule
BSponsorship, risk, quality
CSchedule, sponsorship, scope
DResources, quality, communication
Question #83Part 2

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

AProject Integration Management
BProject Communications Management
CProject Quality Management
DProject Risk Management
Question #84Part 2

For what protect management process is work performance information an output?

AImplement Risk Responses
BPlan Stakeholder Engagement
CMonitor Stakeholder Engagement
DPlan Quality Management
Question #85Part 2

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

AInitiating Process Group
BPlanning Process Group
CExecuting Process Group
DMonitoring and Controlling Process Group
Question #86Part 2

Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long- range strategic objectives that contribute to the bottom line?

APlanning and risk management skills
BCommunication and time management skills
CBusiness intelligence and leadership skills
DStrategic and business management skills
Question #87Part 2

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

ASensitivity analysis
BMonte Carlo analysis
CExpected monetary value analysis
DDecision tree analysis
Question #88Part 2

The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?

ATeam values, team agreements, and conflict resolution process
BConflict resolution process, communication guidelines, and meeting schedules
CTeam roles and responsibilities, team management, and training plan
DResource requirements, resource assignments, and team performance assessments
Question #89Part 2

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the importance of creating the project management office?

AIt will give the project manager independence to make decisions without other departmental input.
BIt integrates organizational data and information to ensure that strategic objectives are fulfilled.
CThe project management office can execute administrative tasks.
DThe project management office can coordinate projects.
Question #90Part 2

In order to detect quality issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches for Project Quality Management?

AThe frequency of the quality and review steps
BThe number of deliverables
CThe duration of each of the quality and review steps
DThe tools used in the quality and review steps
Question #91Part 2

An important project stakeholder has low risk tolerance. Which type of communication should a project manager use to provide this stakeholder with a difficult update?

AInformal conversation
BFace-to-face meeting
CShort email update
DWritten report
Question #92Part 2

Which tools and techniques should a project manager use to monitor risks?

AExpert judgment, data analysis, and interpersonal and team skills
BData analysis, audits, and meetings
CExpert judgment, audits, and decision making
DMeetings, data gathering, and expert judgment
Question #93Part 2

What internal enterprise environmental factor (EEF) can impact a project?

ACultural influences
BPhysical environmental elements
CCommercial databases
DInfrastructure
Question #94Part 2

A protect manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?

ATime and material (T&M)
BCost plus fixed fee (CPFF)
CFixed price
DCost plus award fee (CPAF)
Question #95Part 2

Which is a list of organizational systems that may have an impact on a project?

AInternal policies, company procedures, and organizational resources
BCompany culture, purchasing system, and project management information system
COrganizational structure, governance framework, and management elements
DOrganizational process assets, enterprise environmental factors, and corporate knowledge
Question #96Part 2

Which set of activities should a project manager use as part of the Develop Team process?

ATraining and establishing ground rules
BNetworking activities and estimating team resources
CConflict management activities and tracking team performance
DRecruit new team members and training
Question #97Part 2

Which set of competencies should a project manager have?

ALeadership, strategic and business management, and technical project management
BExpertise in the industry, leadership and business management, and bilingual skills
CTechnical project management, expertise in every rote, and PMP certification
DExpertise in every detail on project activities, PMP certification, and leadership
Question #98Part 2Select 2

Select two key benefits of the Control Procurements process. (Choose two.)

AEnables the development of make-or-buy decisions
BEnsures that contract performance meets the terms of the legal agreement
CGuarantees that legal agreements influence vendor selection
DAssures that legal agreements guide contract closings
EHelps determine whether a certain type of contract should be used
Question #99Part 2

A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

AThe project manager should identify and deal with stakeholders only during the execution phase.
BStakeholder satisfaction should be identified immediately and managed as a project objective.
CThe project manager should focus on project objectives and deal with stakeholders as a secondary priority.
DStakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Question #100Part 2

Which of the following set of elements is part of an effective communications management plan?

AEscalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information
BPhone book directory, stakeholder communication requirements, project charter, glossary of common terminology
COrganizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology
DGlossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan
Question #101Part 2

Which is the order of steps in the Procurement Management process?

AIdentifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements.
BIdentifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements.
CControlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors.
DObtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements.
Question #102Part 2

What process is included in Project Integration Management?

AMonitor and Control Project Work
BControl Scope
CControl Schedule
DDevelop Team
Question #103Part 2

What are the inputs of the Estimate Costs process?

AProject management plan, work performance data, enterprise environmental factors, and organizational process assets
BProject management plan, project documents, enterprise environmental factors, and organizational process assets
CCost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
DProject management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Question #104Part 2

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

AMatrix - strong
BMatrix - balanced
CVirtual
DFunctional
Question #105Part 2

The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?

AProject charter and stakeholder engagement plan
BRisk management plan and stakeholder engagement plan
CCommunications management plan and stakeholder engagement plan
DProject charter and communications management plan
Question #106Part 2

In which Project Cost Management process is work performance data included?

APlan Cost Management
BEstimate Costs
CDetermine Budget
DControl Costs
Question #107Part 2

In a project using agile methodology, who may perform the quality control activities?

AA group of quality experts at specific times during the project
BThe project manager only
CAll team members throughout the project life cycle
DSelected stakeholders at specific times during the project
Question #108Part 2

What does earned value (EV) measure?

ABudgeted work that has been completed
BTotal costs incurred while accomplishing work
CBudget associated with planned work
DCost efficiency of budgeted resources
Question #109Part 2

How can a project manager represent a contingency reserve in the schedule?

AAdditional weeks of work to account for unknown-unknowns risks
BTask duration estimates of the best case scenarios
CAdditional duration estimates in response to identified risks that have been accepted
DMilestones representing the completion of deliverables
Question #110Part 2

Which action should the project manager take after the team finishes executing the scope?

AVerify the deliverables to ensure that they are correct and meet the customer's satisfaction.
BAccept all the deliverables and deliver them to the customer for final acceptance.
CConduct a joint session with the customer, change the deliverables, and then request approval.
DCheck that all change requests were implemented and release deliverables to the customer.
Question #111Part 2

Which are the main objectives of Project Risk Management?

AIncrease the probability of positive risks and decrease the probability of negative risks.
BAvoid all kind of risks.
CIncrease the probability of positive risks and eliminate all negative risks.
DIdentify positive and negative risks.
Question #112Part 2

What is the difference between verified and accepted deliverables?

AAccepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.
BAccepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.
CAccepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.
DAccepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process
Question #113Part 2

What statement describes the function or responsibility of a project manager?

AWorks with the sponsor to address internal political and strategic issues that may impact the team
BSeeks ways to develop relationships that assist the team in achieving organizational goals and objectives
CEnsures that the project's business operations are efficient
DProvides management oversight tor a project's functional or business units
Question #114Part 2

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

AA diagram in which resource optimization has been applied.
BA diagram in which the critical path method has been applied.
CA diagram in which a predefined series of activities has been organized.
DA diagram which shows a combination of resource and time optimization.
Question #115Part 2

The features and functions that characterize a result product, or service can refer to:

Aproject scope
Bproduct scope
Cservice scope
Dproduct breakdown structure
Question #116Part 2

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables. Which process is the project manager executing?

AManage Quality
BPlan Quality Management
CControl Quality
DPlan Scope Management
Question #117Part 2

In an agile and adaptive project, which scope management entity involves stakeholder engagement?

ACollect Requirements
BCreate work breakdown structure (WBS)
CPlan Scope Management
DScope Baseline
Question #118Part 2

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

ABrainstorming. Monte Carlo simulation, analogous estimation
BThree-point estimation, resources leveling, iteration burndown chart
CMilestone charts, parametric estimation, schedule baseline
DParametric estimation, three-point estimation, meetings
Question #119Part 2

A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win situation?

ACollaborate/Problem Solve
BCompromise/Reconcile
CSmooth/ Accommodate
DWithdraw/Avoid
Question #120Part 2

What should a project manager do to prepare a risk management plan in a project with a lot of technical uncertainty?

AGet expert judgment
BCount on personal experience
CAsk project sponsors
DDelay the project until technical uncertainty is clarified
Question #121Part 3

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?

ADefining the scope of the project
BBuilding a collaborative environment
CCreating a detailed project management plan
DDirecting the delivery of the project
Question #122Part 3

Which statement describes the relationship between Manage Quality process and Control Quality process?

AManage Quality is all about following planned processes and procedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.
BControl Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.
CManage Quality and Control Quality are the same.
DManage Quality is part of Quality Management and Control Quality is a subset of the Stakeholder Management Process group.
Question #123Part 3

A stakeholder is reading project documents given by the project manager. The stakeholder is curious about the difference between a verified deliverable and an accepted deliverable. Which of the following definitions can the project manager use to explain the difference?

AAn accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.
BAn accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.
CAn accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process.
DAn accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.
Question #124Part 3

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

AA self-organizing approach to increase team focus and maximize collaboration
BA virtual team to minimize feeling of isolation and gaps on sharing knowledge
CA distributed team to improve tracking progress, productivity, and performance
DA norming approach that requires team members to adjust their behavior and work together
Question #125Part 3

How is the Project Scope Management process different in agile and adaptive projects than in traditional projects?

ALess time spent on defining scope early on
BMore time spent on defining scope early on
CLess time spent on scope management process
DProject scope management is the same in all projects
Question #126Part 3

What is the purpose of the project management process groups?

ATo define a new project
BTo track and monitor processes easily
CTo logically group processes to achieve specific project objectives
DTo link specific process inputs and outputs
Question #127Part 3

After an internal deliverable review session with the team, the project manager identifies some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and time for the required rework. How would the project manager define these extra costs?

AAppraisal costs
BManagement reserves
CCost of nonconformance
DCost of conformance
Question #128Part 3

During which process of Project Cost Management does a project manager produce the cost baseline?

AEstimate Costs
BControl Schedule
CDetermine Budget
DDevelop Project Charter
Question #129Part 3

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

AAcquire Resources
BControl Resources
CManage Team
DDevelop Team
Question #130Part 3

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

AInvolvement is needed only during project initiation
BMinimal involvement of stakeholders is sufficient
CThey should be continuously engaged
DThey should be involved only during phase or deliverable reviews
Question #131Part 3

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

APush communication
BPull communication
CInteractive communication
DStakeholder communication
Question #132Part 3

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?

AOrganizational process assets
BChange management plan
CCommunications management plan
DResource management plan
Question #133Part 3

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

ATechnical project management skills
BTime management skills
CStrategic and business management skills
DLeadership skills
Question #134Part 3

What tool should a project manager use to efficiently manage project resources?

AList of project resources
BResource breakdown structure
CResources detailed in the project scope
DResource requirements
Question #135Part 3

Which process is engaged when a project team member makes a change to project budget with the project manager's approval?

AManage Cost Plan
BEstimate Costs
CDetermine Budget
DControl Costs
Question #136Part 3

What is the best tool to calculate the critical path on a project?

ACritical chain method
BGraphical evaluation and review technique (GERT) diagram
CGantt chart
DProject network diagram
Question #137Part 3

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?

AOperations management
BProject management
CProgram management
DPortfolio management
Question #138Part 3

What is the discipline that focuses on the interdependencies between projects to determine the optimal approach for managing them?

AProject Management
BProgram Management
CPortfolio Management
DOperations Management
Question #139Part 3

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

ALife cycle approaches
BResource availability
CProject dimensions
DTechnology support
Question #140Part 3

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

AInteractive
BPush
CVerbal
DOral
Question #141Part 3

Creating the project scope statement is part of which process?

AManage Scope
BCollect Requirements
CDefine Scope
DValidate Scope
Question #142Part 3

What organizational asset can influence the Plan Risk Management process?

ACorporate policies and procedures for social media, ethics, and security
BOrganizational risk policy
CStakeholder register templates and instructions
DOrganizational communication requirements
Question #143Part 3

A project manager called for a team meeting to estimate the project effort. During the session, the team went on to identify all the deliverables and analyzed the related work. Each of the analyzed deliverables were estimated. Which estimation method did the team use?

ARolling wave planning
BExpert judgment
CDecomposition
DData analysis
Question #144Part 3

Due to new market conditions a five-year project requires a full revision of project objectives. Which components of the stakeholder engagement plan need to be updated?

AScope and impact of change to stakeholders
BProject scope and stakeholder goals
CEngagement level of key stakeholders
DStakeholder expectations for the project
Question #145Part 3

The project team is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

ACo-location
BLife-cycle
CDiversity
DManagement
Question #146Part 3

A project manager is identifying the risks of a project. Which technique should the project manager use?

ARepresentations of uncertainty
BPrompt lists
CAudits
DRisk categorization
Question #147Part 3

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

AMonitor Communications
BPlan Communications Management
CManage Communications
DManage Stakeholder Engagement
Question #148Part 3

What is a tailoring consideration in Project Integration Management?

AValidation and control
BBenefits
CTechnology support
DPhysical location
Question #149Part 3

What important leadership quality/qualities should project manager possess?

ASkills and behaviors related to specific domains of project management
BSkills and behaviors needed to guide a team and help an organization reach its goals
CIndustry expertise that helps to better deliver business outcomes
DIndustry and organizational expertise that enhances performance
Question #150Part 3

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

AApproved change requests
BVerified deliverables
CLessons learned
DWork performance data
Question #151Part 3

Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

ALeadership management
BTechnical project management
CStrategic management
DBusiness management
Question #152Part 3

Which of these is true of project integration management?

AProject Integration Management is mandatory and more effective in larger projects
BProject Integration Management and expert judgment are mutually exclusive
CProject Integration Management is the responsibility of the project manager
DProject Integration Management excludes the triple constraints if cost performance index (CPI) equals zero
Question #153Part 3

Why is tailoring in a project necessary?

ARequirements keep changing
BAn artifact must be produced
CA tool or technique is required
DEach project is unique
Question #154Part 3

An organization structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

AProject Management Information System
BProject Management System
CProject Management Office
DProject Management Knowledge Area
Question #155Part 3

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract is this?

ATime and material (T&M)
BFixed price incentive fee (FPIF)
CCost plus fixed fee (CPFF)
DCost plus award fee (CPAF)
Question #156Part 3

A project manager is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?

AMonitor Stakeholder Engagement
BMonitor Communications
CManage Communications
DManage Stakeholder Engagement
Question #157Part 3

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

AVerified deliverables
BValidated deliverables
CAccepted deliverables
DCompleted change requests
Question #158Part 3

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

AFinish-to-Finish (FF)
BStart-to-Finish (SF)
CFinish-to-Start (FS)
DStart-to-Start (SS)
Question #159Part 3

Which of the following is used as an input to prepare a cost management plan?

AExpert judgment
BLessons learned
CCost estimates
DProject management plan
Question #160Part 3

In which organizational structure would the project manager have most authority?

AMatrix-weak
BMatrix-balanced
CMatrix-strong
DOrganic or simple
Question #161Part 3

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

ADevelop Schedule
BControl Schedule
CEstimate Activity Durations
DDefine Activities
Question #162Part 3

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

AWhat-if scenario analysis
BSimulation
CAlternatives analysis
DReserve analysis
Question #163Part 3

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

AEarly requirements gathering
BFeedback analysis
CProgressive elaboration
DRequirements documentation
Question #164Part 3

Which of the following describes the similarities of the process groups and project life cycle?

AThe life cycle involves three project management process groups
BBoth provide a basic framework to manage the project
CEach project must have a life cycle and all processes in the five process groups
DThe project life cycle is managed by executing the processes within the five process groups
Question #165Part 3

What can the project manager find among the factors that could lead a project to be tailored?

ACompany culture
BReturn on investment
CEarned Value
DSchedule Performance Index
Question #166Part 3

Which of the following are components of the technical project management skill?

AAbility to explain business aspects of the project, business strategy, goals and objectives, and business value
BAbility to deal with people, to be collaborative, and to apply persuasion and negotiation
CAbility to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy
DAbility to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors
Question #167Part 3

What is a tailoring consideration for the application of Project Risk Management processes?

AProject complexity
BProcurement criteria
CCommunication technology
DKnowledge management
Question #168Part 3

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

AInformal
BUnofficial
CFormal
DHierarchical
Question #169Part 3

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

AWithdraw/avoid
BSmooth/accommodate
CCollaborate/problem solve
DCompromise/reconcile
Question #170Part 3

What is the project manager's responsibility in Project Integration Management?

AEnsuring that requirements-related work is clarified in the project management plan
BInvesting sufficient effort in acquiring, managing, motivating, and empowering the project team
CCombining the results in all other knowledge areas and overseeing the project as a whole
DDeveloping a strategy to ensure effective stakeholder communication
Question #171Part 3

What is the role of project management in terms of organizational strategy?

AProject management aligns initiatives, prioritizes work, and provides resources
BProject management provides the strategic vision for an organization to achieve its goals
CProject management enables the achievement of organizational goals and objectives
DProject management harmonizes components and controls interdependencies to realize specific benefits
Question #172Part 3

Perform Quantitative Risk Analysis focuses on:

Acompiling a list of known risks and preparing responses to them
Bassessing the probability of occurrence and impact for every risk in the risk register
Cevaluating the contingency and management reserves required for the project
Danalyzing numerically the impact of individual risks on the overall project's time and cost objectives
Question #173Part 3

Which is the tool or technique that is used to obtain the list of activities from the work packages?

AData analysis
BLeads and lags
CPrecedence diagramming method
DDecomposition
Question #174Part 3

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

AProject level
BOrganizational level
CIndustry level
DInfluential level
Question #175Part 3

Stakeholder identification and engagement should begin during what phrase of the project?

AAfter the project management plan is completed
BAfter the stakeholder engagement plan is completed
CAs soon as the project charter has been approved
DAfter the communications management plan is completed
Question #176Part 3

What communication methods would a project manager use for overall effective project communication?

AInteractive communication, push communication, interpersonal communication
BInteractive communication, push communication, pull communication
CPush communication, pull communication, interpersonal communication
DPull communication, interactive communication, interpersonal communication
Question #177Part 3

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

ACreate Work Breakdown Structure (WBS)
BCreate Scope Baseline
CCollect Requirements
DDefine Scope
Question #178Part 3

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

AInformal communication
BInternal communication
CFormal communication
DHorizontal communication
Question #179Part 3

Which type of project life cycle uses an iteration plan?

AAgile
BPredictive
CWaterfall
DProduct
Question #180Part 3

Which two processes should be used to influence costs in the early stages of a project?

AEstimate Costs and Determine Budget
BPlan Cost Management and Estimate Activity Durations
CControl Quality and Control Costs
DPlan Stakeholder Engagement and Plan Communications Management
Question #181Part 4

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

APlan Quality Management
BControl Quality
CRisk Management
DPlan Scope Management
Question #182Part 4

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

AThe organization
BThe project
CThe industry
DThe product
Question #183Part 4

What process is included in Project Schedule Management?

AEstimate Activity Durations
BCreate Work Breakdown Structure (WBS)
CDirect and Manage Project Work
DEstimate Activity Resources
Question #184Part 4

What does expert judgement provide as an input to the resource management plan?

AGeographic distribution of facilities and resources
BPhysical resource management policies and procedures
CEstimated lead times based on lessons learned
DTemplates for the resource management plan
Question #185Part 4

Which tasks should a project manager perform in order to manage the project schedule effectively?

APlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Develop Schedule
BPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
CPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities, Develop Schedule
DDefine Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities, Develop Schedule
Question #186Part 4

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

ATake control of all decisions and product planning
BBuild a team that can respond to changes within a collaborative, decision-making environment
CPromote a team with a narrow specialization within a hierarchical environment
DDelegate project decisions to the product owner and sponsor
Question #187Part 4

Which of the following is an example of an internal factor that influences the outcome of the project?

ALegal restrictions
BFinancial considerations
CCommercial database
DGeographic distribution of facilities
Question #188Part 4

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

APrompt lists and data analysis
BReports and representations of uncertainty
CData analysis and risk audits
DInterpersonal and team skills and project management information system
Question #189Part 4

Which term refers to the work performed to deliver results with specified features and functions?

AProject scope
BProduct scope
CChange request
DAcceptance criteria
Question #190Part 4

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

ADiversity background
BStakeholder's relationships
CTechnical expertise
DKnowledge management
Question #191Part 4

The primary purpose of the stakeholder register is to:

ARecord stakeholder issues on the project
BMaintain lessons learned earlier in the project
CMaintain a list of all project stakeholders
DDocument change requests and their status
Question #192Part 4

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

ALeast cost
BQualifications only
CSole source
DFixed budget
Question #193Part 4

Project reporting is a tool that is most closely associated with which process?

ACommunicate Plan
BManage Communications
CReport Performance
DControl Communications
Question #194Part 4

A project reports an earned value (EV) of US$45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

A0.88
B1.12
C0.58
D1.58
Question #195Part 4

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

APower interest grid
BStakeholder cube
CSalience model
DDirections of influence
Question #196Part 4

A project manager is performing a specific process and has a list of accepted deliverables. One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables. Which process is being referred to?

AControl Quality
BValidate Scope
CValidate Quality
DControl Scope
Question #197Part 4

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

AList of identified risks, potential risk owners, list of potential risk response
BList of identified risks, list of causes, list of risk categories
CShort risk titles, list of potential risk owners, list of impacts on objectives
DList of activities affected, list of potential risk responses, list of causes
Question #198Part 4

What is a tool or technique used in the Control Quality process?

AAttribute sampling
BParametric estimating
CStatistical sampling
DExpert judgment
Question #199Part 4

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

APlan Resource Management
BEstimate Activity Resources
CEstimate Costs
DAcquire Resources
Question #200Part 4

A project manager held a meeting and listed all the team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

AFocus groups
BInterviews
CBrainstorming
DDelphi technique
Question #201Part 4

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

AHold a face-to-face meeting with the project manager and warn them
BPoint the director to a link where they can take a look at the reports
CInvite stakeholders to attend monthly progress review meetings
DAsk the project manager to update the monthly status report distribution list
Question #202Part 4

What is the difference between quality metrics and quality measurements?

AQuality metrics are product attributes and the measurement is the result of the Monitor and Control Project process
BQuality metrics are the result of the Monitor and Control Project process and the measurements are product attributes
CQuality metrics and measurements are the same concept
DQuality metrics is the general objective and the measurements are the specific objectives
Question #203Part 4

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

ALook at the quality metrics
BValidate the scope
CReview the quality checklist
DConduct a quality audit
Question #204Part 4

What are the objectives of initiation processes?

AInitiation processes are performed in order to develop the project charter and identify stakeholders.
BInitiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
CInitiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
DInitiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.
Question #205Part 4

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?

AUS$-30,000
BUS$120,000
CUS$370,000
DUS$400,000
Question #206Part 4

In agile projects while performing scope management, what is the definition of requirements?

AMetrics
BSprint
CCharter
DBacklog
Question #207Part 4

Which of the following sets are inputs to the Collect Requirements process?

AProject charter and requirements documentation
BProject charter and business documents
CProject charter and stakeholder requirements
DBusiness documents and requirements traceability matrix
Question #208Part 4

During the execution phase of a project a defect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

AChange request
BRisk response
CRisk management plan
DLessons learned
Question #209Part 4

A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

ACollective decision making
BMulticriteria decision analysis
CMind mapping
DAffinity diagram
Question #210Part 4

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

ARisk, resource, and communications management plans
BScope, quality, and resource management plans
CProcurement, integration, and risk management plans
DCommunications, schedule, and cost management plans
Question #211Part 4

Which contract type is least desirable to a vendor?

AFixed price with economic price adjustment (FPEPA)
BFirm fixed price (FFP)
CCost plus fixed fee (CPFF)
DCost plus award fee (CPAF)
Question #212Part 4

A project manager is addressing risks and potential concerns related to stakeholder management, and is clarifying and resolving previously identified issues. In which process is the project manager engaged?

AIdentify Stakeholders
BPlan Stakeholder Engagement
CManage Stakeholder Engagement
DMonitor Stakeholder Engagement
Question #213Part 4

Deciding the phases of project life cycle would be considered a part of which of these knowledge areas?

AProject Schedule Management
BProject Scope Management
CProject Resource Management
DProject Integration Management
Question #214Part 4

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

AText-oriented format
BResource management plan
COrganization chart
DResponsibility assignment matrix (RAM)
Question #215Part 4

What charts and figures should project managers use during the Perform Quantitative Risk Analysis process?

ATornado diagrams and influence diagrams
BDetectability bubble charts and probability and impact matrix
CHierarchical charts and burndown charts
DFlow charts and responsible, accountable, consult, and inform (RACI) charts
Question #216Part 4

Recognition and rewards are tools and techniques of which process?

ADevelop Team
BManage Team
CControl Resources
DPlan Resource Management
Question #217Part 4

What are the key tools for managing project knowledge?

AExpert judgment and data gathering
BNetworking and storytelling
CData analysis and decision making
DPrototypes and product analysis
Question #218Part 4

Make-or-buy analysis is a tool and technique of which process?

AConduct Procurements
BPlan Procurement Management
CAnalyze Procurements
DControl Procurements
Question #219Part 4

Which of the following are outputs of the Define Scope process in Project Scope Management?

ARequirements documentation and requirements traceability matrix
BScope management plan and requirements management plan
CProject scope statement and project documents updates
DScope baseline and project documents updates
Question #220Part 4

What does an S-curve from a Monte Carlo analysis show?

ACumulative probability distribution representing probability of achieving a particular outcome
BIndividual project risks or uncertainties that have the most potential impact on outcome
CBest alternative out of the possible solutions, incorporating associated risks and opportunities
DDiagram for all project uncertainties and their influence over a period of time
Question #221Part 4

Project managers play a key role in performing integration on a project. What are the three different levels of integration?

AProcess, cognitive, and context
BComplexity, understand, and change
CInteract, insight, and leadership
DCommunication, knowledge, and value
Question #222Part 4

Which of the following is an example of tacit knowledge?

ARisk register
BProject requirements
CExpert judgment
DMake-or-buy analysis
Question #223Part 4

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

AVideo conferencing
BAudio conferencing
CShared portal
DEmail/chat
Question #224Part 4

When should Project Risk Management be conducted?

AProject Planning
BMonitoring and Controlling
CQuality Planning
DThroughout the project lifecycle
Question #225Part 4

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

AIt represents how and when the project will deliver the products, services, and results defined in the project scope
BIt creates a formal record of the project and shows the organizational commitment to the project
CIt describes how the scope will be defined, developed, monitored, controlled, and validated
DIt provides the needs of a stakeholders or stakeholder group
Question #226Part 4

Which of the following are processes associated with Project Cost Management?

ADevelop Costs, Estimate Costs, Determine Budget, Control Costs
BDevelop Budget, Determine Budget, Determine Risks, Control Costs
CPlan Cost Management, Estimate Costs, Determine Budget, Control Costs
DPlan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
Question #227Part 4

A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs). What type of procurement document is the RFP?

ABid document
BStatement of work (SOW)
CSource selection criteria
DIndependent cost estimate
Question #228Part 4

What is a key benefit of using virtual project teams?

AEnsures appropriate behavior, security, and the protection of proprietary information
BReduces the risk of conflict due to interpersonal communications and other interactions
CAssures that all team members have a clear and common understanding of the project
DReduces project cost by use of modern technologies allowing seamless team collaboration
Question #229Part 4

Which behavior relates to team leadership?

ACentering on systems and structure
BProviding guidance using the power of relationships
CAccepting the status quo
DFocusing on operational issues and problem solving
Question #230Part 4

For a 10-day project, activity B's duration is three days, and activity C's duration is two days. What is the duration of activity A if activities B and C are performed in parallel?

A3 days
B5 days
C7 days
D10 days
Question #231Part 4

What is the purpose of the Manage Quality process?

ATo translate the quality management plan into executable quality activities.
BTo monitor and record the results of executed quality management activities.
CTo determine if project activities comply with organizational and project policies.
DTo identify project deliverables and quality requirements and/or standards.
Question #232Part 4

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders?

APrioritization
BDirections of influence
CSalience model
DPower/influence grid
Question #233Part 4

What process in Project Risk Management prioritizes project risks?

APerform Qualitative Risk Analysis
BPerform Quantitative Risk Analysis
CPlan Risk Responses
DImplement Risk Responses
Question #234Part 4

What process is performed periodically throughout the project as needed?

APlan Risk Management
BPlan Communications Management
CPlan Resource Management
DPlan Cost Management
Question #235Part 4

A project team is closing out a phase and updating the organizational knowledge base. What organizational process asset (OPA) will the team update?

ATraceability matrices
BLessons learned
CChange control procedures
DResource availability
Question #236Part 4

What does the creation of a project management plan accomplish?

ADefines the basis of all project work and how it will be performed
BAcknowledges the existence of a project, and defines its high-level information
CAuthorizes the project manager to apply organizational resources to project activities
DProvides the project manager with organizational standards, policies, processes, and procedures
Question #237Part 4

When planning communications management, what input identifies key stakeholders?

AWork performance information
BProject schedule
CProject charter
DWork performance reports
Question #238Part 4

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

AThe receiver decodes the message.
BThe receiver responds to the message with feedback
CThe receiver transmits the message.
DThe receiver acknowledges their receipt of the message.
Question #239Part 4

A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project, of what should the project manager be aware?

ADemands on the same resources
BRequirements that impact the scope
CUncertainty of emerging issues
DProject charter

📢 Unlock Full Access to Success!

"The content displayed here is a promotional preview and contains only 50% of the actual exam database. To access the complete set of updated questions, please upgrade to the Full Version."

👉 Click the button and follow the instructions to secure your full access immediately!