CompTIA Project+
Gain the essential project management skills to lead successful IT projects.
4.8★★★★★(343 ratings)
18,403 studentsIntermediate- •Familiarity with basic IT concepts
- •Access to relevant platform tools for hands-on practice
- •Interest in pursuing PK0-005 certification
- •Junior Project Managers
- •Team Leads
- •Technical Managers
Master the project life cycle, documentation, and communication skills needed to deliver IT projects on time and within budget. This course bridges the gap between technical skills and management excellence.
Validate your ability to manage small-to-medium sized projects effectively in a technical environment. Enhance your career by demonstrating specialized leadership and organizational skills.
What you'll learn
- Project Basics
- Project Constraints
- Communication & Change Management
- Project Tools & Documentation
- Agile vs Waterfall
PK0-005
Lectures4
Questions188
Duration30 week
Students18,403
$20.00
Full Free Question Bank (188 Questions)
CompTIA Project+ (PK0-005) Practice Questions & Verified Answers
Click any option to test your knowledge, or reveal the verified answer and detailed explanation below each question.
Jump to Section:
Question #1Part 1Select 2
ATrain users on the proper use of the system.
BEscalate the issue to the CCB.
CHold sessions to understand user challenges.
DTrack system usage and report user activity.
ELog the issue in the project risk register.
✓ Verified Answer: AC
Question #2Part 1
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
ADaily stand-up
BProject momentum
CPerformance feedback
DMeeting minutes
✓ Verified Answer: C
Question #3Part 1
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
AEvaluating the project
BReleasing the resources
CClosing the contracts
DReconciling the budget
✓ Verified Answer: D
Question #4Part 1
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
AIshikawa diagram
BScatter diagram
CPareto chart
DDecision tree
✓ Verified Answer: C
Question #5Part 1
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
AApply the SDLC process.
BEstablish a program.
CConsult the CCB.
DUse different frameworks.
✓ Verified Answer: B
Question #6Part 1
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
AStatus report
BProject plan
CChange log
DMeeting minutes
✓ Verified Answer: D
Question #7Part 1
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
ASynchronous
BInformal
CAsynchronous
DFormal
✓ Verified Answer: A
Question #8Part 1
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
AUpdate the work breakdown structure.
BReview the backlog.
CSeek baseline approval.
DEstablish the resource pool.
✓ Verified Answer: C
Question #9Part 1
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
ATrigger the contingency plan and communicate with the stakeholders.
BWork with the functional managers to create a work-around.
CSubmit a change request to the change control board.
DTransfer the risk by hiring a new vendor who was successful on a previous project.
ESet up an escalation meeting with the sponsor.
✓ Verified Answer: A
Question #10Part 1
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
AAllocate resources.
BDetermine the project budget.
CDevelop a communication plan.
DEstablish baselines.
✓ Verified Answer: A
Question #11Part 1
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
ARFI
BRACI
CWBS
DSOW
✓ Verified Answer: B
Question #12Part 1
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
ASLA
BTOR
CSOW
DNDA
✓ Verified Answer: C
Question #13Part 1
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
AApproving the change request
BDeveloping a rollback plan
CGathering necessary resources
DDefining requirements
✓ Verified Answer: B
Question #14Part 1
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
AIssue log
BDefect log
CChange log
DTask board
✓ Verified Answer: B
Question #15Part 1
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
AESG
BPHI
CPII
DROIL
✓ Verified Answer: A
Question #16Part 1
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
AMultiauthoring software
BWord processor
CReal-time polling
DConferencing platforms
✓ Verified Answer: A
Question #17Part 1
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
AExternal
BInternal
CMandatory
DDiscretionary
✓ Verified Answer: C
Question #18Part 1
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
AIssue log
BGantt chart
CMilestone chart
DChange control log
✓ Verified Answer: A
Question #19Part 1
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
AProject change management plan
BProject management plan
CProject transition plan
DProject communication plan
✓ Verified Answer: B
Question #20Part 1
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed: Which of the following issues should be addressed FIRST?
AReplace missing peripherals because this process can be easy and less costly.
BAn old operating system issue has the most amount of occurrences.
CDamage to the monitor has the highest percentage.
DAddress each issue as discovered to avoid rework.
✓ Verified Answer: B
Question #21Part 1
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP. Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
AMilestone chart
BWork breakdown structure
CProject charter
DDetailed scope statement
✓ Verified Answer: C
Question #22Part 1
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
AAssemble a new project with existing resources.
BObtain the final report from release management.
CNotify the functional manager that resources are released.
DAllocate resources in a different project.
✓ Verified Answer: B
Question #23Part 1
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
ATime and materials contract
BMaster service agreement
CFixed-price contract
DStatement of work
ECost-plus agreement
✓ Verified Answer: A
Question #24Part 1
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
AAssign action items to attendees.
BDistribute an agenda.
CEmail the minutes from the previous meeting.
DSchedule a convenient time.
✓ Verified Answer: B
Question #25Part 1
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?
AEscalate the finding to the change control board.
BAdd a risk to the risk register for validation.
CConsult the RACI matrix to identify ownership of the risk.
DHave a meeting with the project sponsor and main stakeholders.
✓ Verified Answer: D
Question #26Part 1
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?
APareto
BRun
CControl
DHistogram
✓ Verified Answer: A
Question #27Part 1Select 3
Which of the following activities would a project manager perform during the closing phase? (Choose three.)
ALessons learned
BRisk analysis
CRemoving resources
DAcquiring resources
EStatement of work sign-off
✓ Verified Answer: ACG
Question #28Part 1
Which of the following is a quality assurance tool?
ADefining project goals
BIdentifying the root cause analysis
CAssessing employee efficiency
DAssessing skill gaps
✓ Verified Answer: B
Question #29Part 1
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
AQuality assurance
BOrganizational branding restrictions
CState privacy acts
DCountry legal regulations
✓ Verified Answer: D
Question #30Part 1
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
ACollate the lessons learned.
BPerform a gap analysis.
CReview existing artifacts.
DConduct a retrospective.
✓ Verified Answer: C
Question #31Part 1
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
ASocial engineering
BPhishing
CSpoofing
DHacking
✓ Verified Answer: B
Question #32Part 1
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
AResponsibility assignment matrix
BAcceptable communication channels
CRisk registry
DStaff directory
✓ Verified Answer: B
Question #33Part 1
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the process?
ABased on the rule of seven, the process is under control.
BThe amount of data is insufficient to determine if quality is low.
CThe process is out of control and should be revised.
DThe goal should be adjusted since most of the data points are close to the lower limit.
✓ Verified Answer: C
Question #34Part 1
After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
AContinuous integration
BRollback plan
CCustomer notification
DAutomated testing
✓ Verified Answer: C
Question #35Part 1
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
ACommunicate with the affected stakeholders.
BInitiate a formal change request to modify the cost.
CAdjust the scope to stay within the cost.
DSet a new cost using a lightweight estimation method.
✓ Verified Answer: A
Question #36Part 1
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
ADocument the request in the change control log.
BCommunicate the change deployment.
CConduct an impact assessment.
DImplement the change.
✓ Verified Answer: B
Question #37Part 1
An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?
AB.
CD.
✓ Verified Answer: A
Question #38Part 1
An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?
AExploit the risk.
BAccept the risk.
CAvoid the risk.
DTransfer the risk.
✓ Verified Answer: A
Question #39Part 1
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
AData warehouse
BSQL database
CMultitier architecture
DContent management system
✓ Verified Answer: C
Question #40Part 1Select 2
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Choose two.)
AReview the detailed plan.
BDevelop a preliminary scope.
CDevelop a transition plan.
DDevelop a project management plan.
EReview the resource pool.
✓ Verified Answer: DF
Question #41Part 1Select 2
A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan. Which of the following should be considered in this evaluation? (Choose two.)
ACompany vision
BGlobal environment
CBrand value
DMission statement
EPortfolio budget
✓ Verified Answer: AD
Question #42Part 1
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
AGantt chart
BMaintenance window schedule
CFunctional requirements
DTest results
✓ Verified Answer: A
Question #43Part 1
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
ADecision board
BWhiteboard
CTask board
DDashboard
✓ Verified Answer: C
Question #44Part 1
A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?
AResource allocation
BCommunication security
CTechnological factors
DCultural differences
✓ Verified Answer: D
Question #45Part 1
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following: Which of the following was the initial cause of the issue?
AInadequate memory
BIncorrect configuration
CLack of infrastructure
DInadequate instructions
✓ Verified Answer: B
Question #46Part 1
Which of the following describes three-tier architecture?
AConceptual, design, and implementation stages
BPresentation, application, and data processing
CNetwork, software, and security
DDevelopment, testing, and production environment
✓ Verified Answer: B
Question #47Part 1
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
AImplement the change.
BApprove the test plan.
CNotify customers.
DDevelop a rollback plan.
✓ Verified Answer: D
Question #48Part 1
Which of the following offers administrators more direct control over operating systems?
AInfrastructure as a service
BSoftware as a service
CFunctions as a service
DPlatform as a service
✓ Verified Answer: A
Question #49Part 1Select 2
Which of the following items must be protected as PII? (Choose two.)
AJob title
BHome address
CWork phone number
DTime zone
EDate of birth
✓ Verified Answer: BE
Question #50Part 1
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
ACreation of a social news forum
BManagement directives to use the new system
CNew user kickoff meeting
DMonthly feedback and training sessions
✓ Verified Answer: D
Question #51Part 1
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis: Based on the chart, which of the following is the current status of the project?
ABehind schedule and over budget
BBehind schedule and under budget
CAhead of schedule and over budget
DAhead of schedule and under budget
✓ Verified Answer: A
Question #52Part 1
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
AStrong projectized organization
BMedium risk
CLack of resources
DMultiple undefined tasks
✓ Verified Answer: D
Question #53Part 1
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains: Purpose - Scope of work - Location of work - Period of performance - Deliverables schedule - Applicable standards - Acceptance criteria - Special requirements - Payment schedule - Which of the following documents did the client provide to the project manager?
ARFP
BWBS
CSLA
DSOW
✓ Verified Answer: D
Question #54Part 1
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM’s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
APerform a root cause analysis.
BOrganize a stakeholder meeting.
CEscalate the issue to the CCB.
DContact the PMO for assistance.
✓ Verified Answer: D
Question #55Part 1
A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
AA project manager assigned the wrong resources.
BA project manager did not release the resources.
CA project manager did not remove the system access.
DA project manager did not provide the project sign-off.
✓ Verified Answer: B
Question #56Part 1
Which of the following requires the MOST availability from the business team?
ASDLC
BScrum
CPRINCE2
DWaterfall
✓ Verified Answer: B
Question #57Part 1
Which of the following software programs would be BEST to use to store information related to business transactions?
ARecord management system
BCustomer relationship management
CEnterprise resource planning
DContent management system
✓ Verified Answer: A
Question #58Part 1
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
AWork with the project scheduler to update the project timeline.
BCommunicate to the stakeholders about the updated timeline.
CAsk the development team to fast-track upcoming activities.
DAdd two resources so the critical activities will finish on time.
✓ Verified Answer: A
Question #59Part 1
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
AMemorandum of understanding
BRequest for information
CStatement of work
DNon-disclosure agreement
✓ Verified Answer: C
Question #60Part 1
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
ACreate a list of tasks and share it with the team.
BResend the scope of work to the team.
CReview the Gantt chart weekly with the team.
DHave the project sponsor meet with the team.
✓ Verified Answer: A
Question #61Part 2
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
AMake an impact assessment.
BPrepare a new purchase order.
CSelect a new vendor.
DCreate a risk register.
✓ Verified Answer: A
Question #62Part 2
Which of the following BEST identifies the intent and purpose of a project closeout report?
ATo provide documentation of lessons learned
BTo document variances from the initial project baseline
CTo validate that a project has been successfully completed
DTo release resources and terminate all access rights
✓ Verified Answer: C
Question #63Part 2
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
AROI.
BSOW.
CRFI.
DRFP.
✓ Verified Answer: A
Question #64Part 2Select 2
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)
ARisk report
BDefect log
DIssue log
CBacklog
EChange log
✓ Verified Answer: DE
Question #65Part 2
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
ASOW
BRFI
CRFQ
DWBS
✓ Verified Answer: A
Question #66Part 2
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
ADetermine budget constraints.
BValidate the business case.
CUpdate the project charter.
DCreate a project schedule.
✓ Verified Answer: C
Question #67Part 2
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
AScope creep
BCollecting requirements
CDecision-making
DProject change
✓ Verified Answer: A
Question #68Part 2
Which of the following BEST illustrates how team members with different roles should interact on the team?
ASOW
BWBS
CRACI
DPERT
✓ Verified Answer: C
Question #69Part 2
For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
AResource plan
BOrganizational chart
CProject charter
DRACI chart
✓ Verified Answer: D
Question #70Part 2
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
AKanban board
BPareto chart
CIshikawa diagram
DDecision tree
✓ Verified Answer: C
Question #71Part 2
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
ADashboard
BGantt chart
CWork breakdown structure
DRequirements Traceability Matrix
✓ Verified Answer: A
Question #72Part 2
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
ACritical paths
BResources
CMilestones
DWork breakdown structures
✓ Verified Answer: C
Question #73Part 2
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
ADecline because it is not included in the project scope.
BAssess the impact of the request and create a change request.
CCreate new functional and non-functional requirements for mobile devices.
DRevise the baseline of the project plan by adding the new requirements.
✓ Verified Answer: B
Question #74Part 2
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
AA risk budget
BA risk impact
CA change request
DA contingency plan
✓ Verified Answer: D
Question #75Part 2
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
AProcurement
BCommunication
CQuality assurance
DRisk
✓ Verified Answer: C
Question #76Part 2
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
AEscalate the communication issues.
BImplement a communication platform.
CReview the communication plan.
DTalk with the head of the PMO.
✓ Verified Answer: C
Question #77Part 2
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
AThe ticket system provided access by default without any approval.
BThe project manager did not perform proper project planning.
CThe system is lacking proper access controls.
DSensitive data was incorrectly classified during the audit process.
✓ Verified Answer: C
Question #78Part 2
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens’ complaints. Which of the following solutions would be BEST?
AEnterprise resource planning and end user applications
BElectronic document and record management systems
CCustomer relationship management and databases
DContent management and financial systems
✓ Verified Answer: B
Question #79Part 2
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
AValidate against the scope statement and ask for sign-off.
BRun a control chart to ensure the quality of the deliverables.
CReview the risk register and close up residual risks.
DStart the training and handoff for the operations team.
✓ Verified Answer: A
Question #80Part 2
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
ASmoke testing
BRegression testing
CUnit testing
DUser acceptance testing
✓ Verified Answer: B
Question #81Part 2
A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
ASecure folder
BReal-time, multiauthoring editing software
CDigital whiteboard
DWiki knowledge base
✓ Verified Answer: D
Question #82Part 2
During online, collaborative meeting sessions, a project team is consistently in consensus, which is causing a creativity roadblock. Which of the following can the facilitator do to minimize this issue?
AEnable chat.
BDistribute surveys.
CMeet face to face.
DUse a whiteboard.
✓ Verified Answer: D
Question #83Part 2
During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?
AWaterfall method
BSimulation method
CPrecedence diagramming method
DCritical path method
✓ Verified Answer: C
Question #84Part 2
During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?
ATime-tracking log
BIssue log
CStatement of work
DRisk register
✓ Verified Answer: B
Question #85Part 2
A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?
AReview the progress reports.
BPerform a gap analysis.
CCoordinate a phase-gate review.
DSet up touch points with the team.
✓ Verified Answer: C
Question #86Part 2
Which of the following can be used to determine whether a sample product is within an acceptable range?
AScatter diagram
BVelocity chart
CControl chart
DFishbone diagram
✓ Verified Answer: C
Question #87Part 2
A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity. Which of the following actions should the PM take?
AContinue to monitor the system performance.
BResize the resource utilization to reflect current needs.
CReinforce adoption over time.
DRaise an item in the issue log.
✓ Verified Answer: B
Question #88Part 2
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
AData plan
BContingency plan
CRollback plan
DRecovery plan
✓ Verified Answer: B
Question #89Part 2
A PM has gathered stakeholders from across various functions in the organization. The team has never worked together before. Which of the following should the PM do to ensure standards are understood?
AConduct team training.
BPresent the scope statement.
CEstablish meeting schedules.
DDevelop a communication plan.
✓ Verified Answer: A
Question #90Part 2
A PM in a matrix organizational structure has team members who do not have adequate time to dedicate to project activities. Which of the following should the PM do to improve the team members' availability?
ARequire overtime for assignments.
BConduct training on time management.
CNegotiate with functional managers.
DRecruit additional team members.
✓ Verified Answer: C
Question #91Part 2
A meeting agenda included the following items: • Review the goals of the project. • Review the progress of the project. • Discuss if the project is ready to move forward. Which of the following BEST describes this type of meeting?
AStand-up
BMonthly status
CGap analysis
DGate review
✓ Verified Answer: D
Question #92Part 2
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
APerforming
BAdjourning
CForming
DNorming
✓ Verified Answer: D
Question #93Part 2
Which of the following is the BEST example of a breach of physical security?
ASystem user IDs being used by multiple individuals
BPrinters that do not request user authentication
CDevelopers having full access to both development and production environments
DProject documentation that is only kept on a removable device
✓ Verified Answer: D
Question #94Part 2
Which of the following is a typical characteristic of Scrum?
ALarge teams
BLow-risk scope
CSelf-organized team
DWell-defined scope
✓ Verified Answer: C
Question #95Part 2
In the kickoff meeting, a project manager announced the project will use a tool to store documents, artifacts, and any other data relevant to the project. The tool will perform version control, maintain retention data, and archive destruction or historical information. Which of the following is being described?
ARecord management system
BProject dashboard
CBacklog
DWiki knowledge base
✓ Verified Answer: A
Question #96Part 2
Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?
AWBS
BRACI
CRFP
DPERT
✓ Verified Answer: A
Question #97Part 2
After a meeting, a team member recaps all of the topics that worked well, worked relatively well, and did not work at all. The expectation is for upcoming project work to make better progress and achieve targets. Which of the following combinations of tactics is being used?
AStand-up meeting, action items
BWorkshop meeting, timeboxing
CStatus meeting, follow-ups
DPresentation meeting, meeting notes
✓ Verified Answer: C
Question #98Part 2
In the middle of a five-year project, a vendor asked the buyer to revisit the rate card associated with the development team. According to the vendor, the development team's experience and technical skills have increased since the project started. Which of the following documents should the buyer review FIRST?
AMOU
BSOW
CRFP
DRFI
✓ Verified Answer: B
Question #99Part 2
A project plan included budgeted funding to set up only a specified number of workstations. A department manager asked a project manager to set up additional workstations just in case the workstations are needed in the future. Which of the following should the project manager do?
AAsk the sponsor for additional funding to accommodate the request.
BEscalate the request to the senior management team.
CAdvise that a change request would need to be approved.
DInstruct the project team to set up the additional workstations.
✓ Verified Answer: C
Question #100Part 2
During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?
ACreate a change request for the change advisory board.
BWork with the business analyst to document the new epic.
CReject the change to prevent scope creep.
DUpdate the risk register and the work in the mitigation plan.
✓ Verified Answer: B
Question #101Part 2
Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?
ANegotiate to get more of the team member's available time.
BAssign the team member to work overtime to finish the task.
CSpeed up completion of the task by assisting the team member.
DHave the project manager complete the task.
✓ Verified Answer: A
Question #102Part 2
A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?
ADashboard
BStatus report
CGantt chart
DEmail
✓ Verified Answer: A
Question #103Part 2
A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?
ATrust that the project requirements fully document the necessary compliances.
BMeet with the end users to learn more about the compliance requirements.
CResearch the compliance requirements related to the project to understand the implications.
DMake the QA specialist responsible for ensuring that the compliance requirements are met.
✓ Verified Answer: C
Question #104Part 2
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
ACompromising
BForcing
CSmoothing
DCollaborating
✓ Verified Answer: C
Question #105Part 2
A project manager is assigned to a large, complex project that is very new to the organization. Because of huge expenditures, the project cannot be cancelled after it starts. Which of the following is most important for the project manager to do FIRST?
ACarefully select the vendor.
BIdentify and evaluate risks.
CEstablish change management procedures.
DEvaluate the resource pool.
✓ Verified Answer: B
Question #106Part 2
As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?
AValidate the change implementation.
BImplement the change.
CConduct an impact assessment.
DCommunicate the change deployment.
✓ Verified Answer: B
Question #107Part 2
A project manager is discussing with team members sensitive project information that should not be disclosed outside of the office. Which of the following BEST describes this type of information?
AIntellectual property
BMarketing
CTrade secret
DTop secret
✓ Verified Answer: C
Question #108Part 2
Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?
ASchedule variance
BCost variance
CWork breakdown structure
DKey performance indicators
✓ Verified Answer: D
Question #109Part 2
A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
AProposed solution design
BPreliminary scope statement
CResponsibility assignment matrix
DInitial budget baseline
✓ Verified Answer: B
Question #110Part 2
A project has been initiated to provide insurance forms for a company. A constraint for this project is that the insurance commission in each state where the company underwrites has to approve each form. Which of the following compliance considerations BEST describes this scenario?
ARegulatory impacts
BEnvironmental impacts
COrganizational impacts
DSensitive data types
✓ Verified Answer: A
Question #111Part 2
During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?
ADiscuss the requests with the sponsor.
BPrepare and send the information.
CAssign this task to the project team.
DReview the communication plan.
✓ Verified Answer: D
Question #112Part 2
A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?
AUpdate the risk register
BDocument the finding in the change log.
CCreate a record in the issue log
DDetail a proposed solution.
✓ Verified Answer: C
Question #113Part 2
A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?
ACall the development lead to discuss the fixes for the bug.
BInclude the bug issue as part of the status update for stakeholders.
CIssue a change request.
DAdd the bug issue to the project's risk register.
✓ Verified Answer: C
Question #114Part 2
Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?
AProgram manager
BEnd user
CSteering committee
DProject sponsor
✓ Verified Answer: B
Question #115Part 2
Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?
APRINCE2
BWaterfall
CScrum
DSLDC
✓ Verified Answer: C
Question #116Part 2
A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?
AEstablish a minimally viable product.
BPrepare new knowledge base documentation.
CUpdate the project baseline and schedule.
DPeriodically review vendor performance.
✓ Verified Answer: B
Question #117Part 2
Which of the following methods frequently delivers new code in an automatic way for development projects?
AAutomated testing
BCI/CD process
CValidation checks
DDeploy sprint
✓ Verified Answer: B
Question #118Part 2
When trying to calculate the expected monetary value for using a particular vendor, which of the following charts would be BEST to use?
ADecision tree
BFishbone
CHistogram
DPareto
✓ Verified Answer: A
Question #119Part 2
Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?
AStart-to-finish
BStart-to-start
CFinish-to-start
DFinish-to-finish
✓ Verified Answer: B
Question #120Part 2
Which of the following is a consideration when determining a project's ESG factors?
AProject management methodology
BIT infrastructure security
CProper accounting practices
DCorporate values compliance
✓ Verified Answer: D
Question #121Part 3
In an agenda for a kickoff meeting, some time is set aside to complete a document that identifies each member of the project, the members' roles and responsibilities for tasks, the milestones, and the key decisions. In which of the following should this data be documented?
ATOR
BWBS
CRAM
DSOW
✓ Verified Answer: C
Question #122Part 3
During a project sprint, an analyst explains multiple situations the team encountered after the previous day's sessions. The analyst then lists the tasks that need to be completed before the end of the day. Which of the following meeting types is the team utilizing?
AStand-up meeting
BWorkshop meeting
CKick-off meeting
DPresentation meeting
✓ Verified Answer: A
Question #123Part 3
A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the following tools should the project manager update NEXT?
ADefect log
BStakeholder register
CIssue log
DRisk register
✓ Verified Answer: D
Question #124Part 3
Which of the following IT elements allows developers to leverage existing code to integrate with other software systems?
ASaaS
BAPI
CDatabases
DEnd user applications
✓ Verified Answer: B
Question #125Part 3
A stakeholder notices a typo in the project management plan, specifically the word manager was spelled “manger”. Which of the following is the decision maker who can authorize the change so the correction can be made?
APM
BCCB
CSponsor
DBusiness analyst
✓ Verified Answer: A
Question #126Part 3
A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM MOST likely perform?
ACall the previous PM for advice on risks and issues.
BAsk the project sponsor to provide previous final project report results.
CComplete the project charter using the other PM's subject matter expertise.
DUse existing artifacts and accommodate based on the current project success criteria.
✓ Verified Answer: D
Question #127Part 3
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take NEXT?
AAssign more resources to complete similar stories in the future.
BBreak the stories into workable items that can be completed within one sprint.
CExtend the sprint duration when required with the approval of the product owner.
DRelease the current progress into production and carry over the rest of the code for the next sprint.
✓ Verified Answer: B
Question #128Part 3
During the planning phase, a project manager held a meeting to discuss meeting days, meeting times, meeting frequency, and tools to use. Which of the following will the project manager use to document this data?
AProject communication plan
BProject charter
CProject management plan
DProject plan
✓ Verified Answer: A
Question #129Part 3
During the course of a project, an unexpected event occurs that could ultimately benefit the company. Which of the following is the company employing if the company decides to take advantage of this opportunity?
AExploit
BEnhance
CAccept
DMitigate
✓ Verified Answer: A
Question #130Part 3
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
AMitigate
BTransfer
CAccept
DShare
✓ Verified Answer: A
Question #131Part 3
Testing has been completed, and the new system is loaded in production and ready to be activated. Which of the following needs approval from the project sponsor?
AProject charter
BDeployment plan
CBusiness case
DRelease schedule
✓ Verified Answer: D
Question #132Part 3
A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation?
ARACI
BSOW
CEscalation path
DCommunication plan
✓ Verified Answer: A
Question #133Part 3
During the kickoff meeting, a stakeholder raises a concern that an assigned responsibility is outside of the stakeholder's domain. Which of the following would MOST likely be the reason?
AThe communication plan is outdated.
BThe project manager did not assess the stakeholders.
CThe project manager did not update the risk register.
DThe statement of work does not reflect the impacted stakeholders.
✓ Verified Answer: B
Question #134Part 3
The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?
AHost a risk workshop with all stakeholders to complete an initial risk assessment.
BWork with the interns to develop a work breakdown structure and project schedule.
CConduct a skills assessment to determine the strengths and weaknesses of the staff.
DAssign the resources to project tasks and encourage them to begin work immediately.
✓ Verified Answer: C
Question #135Part 3
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members. Which of the following would be the BEST tool for the project manager to use?
AMeeting chat
BEmail
CReal-time survey
DWhiteboard
✓ Verified Answer: C
Question #136Part 3
While defining technical requirements, the development team requested a tiered architecture setup. Which of the following types of environments BEST describes this architecture?
ASecurity environment
BNetwork environment
CRelease environment
DStage environment
✓ Verified Answer: B
Question #137Part 3
A project manager reviews a new project charter and notices that the project objective is similar to a project that was done in the past. Which of the following actions should the project manager take?
AReview the existing artifacts and customize accordingly.
BUtilize the existing artifacts to manage the project.
CAsk the previous project manager for advice.
DNotify the sponsor that this project duplicates a prior project.
✓ Verified Answer: A
Question #138Part 3
Which of the following is a web template that is used to create websites?
AERP
BCRM
CEDRMS
DCMS
✓ Verified Answer: D
Question #139Part 3
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
ASmoke test
BStress test
CPenetration test
DRegression test
✓ Verified Answer: A
Question #140Part 3
A project manager is performing planning tasks for a complex project at a small company. Which of the following items would be of GREATEST importance during planning?
ADefining the project objectives, scope, and success criteria
BAssessing the resources available for operational support after project implementation
CProviding updates and status reports to the project owner and stakeholders
DDeveloping a records management plan and reviewing existing project artifacts
✓ Verified Answer: A
Question #141Part 3
To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which of following techniques is the project manager utilizing?
AProcess modeling
BBrainstorming
CInterview
DFocus group
✓ Verified Answer: C
Question #142Part 3
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?
ATelephone
BVideoconference
CFace-to-face
DEmail
✓ Verified Answer: D
Question #143Part 3
Several stakeholders have declined the invitation for the kickoff of a major digital transformation project. Which of the following actions should the project manager take NEXT?
AEscalate directly to the project sponsor.
BPush the kickoff meeting out by one week.
CProceed with the kickoff as planned.
DIdentify replacements for project stakeholders.
✓ Verified Answer: A
Question #144Part 3
A development team, which is working on a software project, demonstrates software functionality to project stakeholders a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?
AProject status report
BRequirements Traceability Matrix
CDefect log
DSigned project charter
EWork breakdown structure
✓ Verified Answer: B
Question #145Part 3Select 2
A PM is working on a strategy to store records. Which of the following elements must be included in this plan? (Choose two.)
AData management
BIssue management
CWork breakdown structure
DDocument management
ECommunication management
✓ Verified Answer: AD
Question #146Part 3
Which of the following should be considered FIRST when determining the privacy management for project data?
AEvaluating the current privacy protection program
BUnderstanding applicable privacy regulations
CMaintaining awareness of industry best practices
DImplementing security role-based controls
✓ Verified Answer: B
Question #147Part 3Select 2
An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the MOST important prerequisites? (Choose two.)
ARollback plans
BProject management plan
CDeployment plan
DAsset management plan
ECommunication plan
✓ Verified Answer: AC
Question #148Part 3
Following the approval of a change by the CCB, which of the following should a project manager consider NEXT when deploying a new networking device into an existing production environment?
AMaintenance window
BRisk assessment
COperational security
DValidation check
✓ Verified Answer: A
Question #149Part 3
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
AUse a software tool during the meeting that can create a transcript of what is discussed.
BHave a standing agenda that is vague enough so that it can be used again.
CDelegate the roles and responsibilities to improve meeting management.
DReprimand project team members for not completing assigned action items.
✓ Verified Answer: C
Question #150Part 3
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
ARational Unified Process
BWaterfall
CAgile
DDevOps
✓ Verified Answer: C
Question #151Part 3
Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?
AThe project manager did not release the resources.
BThe project is in the verification testing phase.
CThe project manager did not complete the project closure phase.
DThe project manager did not remove access.
✓ Verified Answer: C
Question #152Part 3
Project team members have questions regarding their responsibilities during the latest sprint. Which of the following personnel would MOST likely be able to assist?
AProduct owner
BTeam leader
CProduct manager
DScrum master
✓ Verified Answer: D
Question #153Part 3
During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update NEXT?
ASchedule
BStatus report
CIssue log
DTask board
✓ Verified Answer: C
Question #154Part 3
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the MOST important for the team to take into consideration?
ATime to be fixed
BImpact to project
CIssue category
DResource availability
✓ Verified Answer: D
Question #155Part 3
Which of the following pieces of data are examples of PII?
AMedical record and test result values
BIP address and email address
CName and year of birth
DX-ray and blood type
✓ Verified Answer: C
Question #156Part 3
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
AAvoid
BTransfer
CAccept
DShare
✓ Verified Answer: B
Question #157Part 3
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
AAvoiding
BSmoothing
CForcing
DCompromising
✓ Verified Answer: A
Question #158Part 3
A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?
AProject scope
BQuality plan
CContract obligations
DWork breakdown structure
✓ Verified Answer: A
Question #159Part 3
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
AStart-to-finish
BFinish-to-finish
CFinish-to-start
DStart-to-start
✓ Verified Answer: C
Question #160Part 3
Which of the following would be considered operational security?
AMobile device compliance
BBackground screening
CMultifactor authentication
DFacility access
✓ Verified Answer: B
Question #161Part 3
A popular application that has been used by clients everywhere is prohibited in one particular jurisdiction because of security concerns. Which of the following should a project manager do?
AConduct an analysis to find a comparable application that is allowed in the particular jurisdiction.
BContinue implementing the existing application because it is proven to be secure elsewhere.
CBuild a new application in house that is comparable to the existing application.
DCancel the project and begin project closeout activities.
✓ Verified Answer: A
Question #162Part 3
Given the following velocity chart: Which of the following updates on the project status should the Scrum master provide to the senior management team?
AThe project utilized all of its available reserve.
BThe project has scope creep.
CThe project deviated from the critical path.
DThe project is trending ahead of schedule.
✓ Verified Answer: D
Question #163Part 3
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
Athe preferred sponsor's communication channel.
Bthe preferred project manager's communication channel.
Cthe preferred reported communication channel.
Demail communication as the preferred communication channel.
✓ Verified Answer: C
Question #164Part 3
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do NEXT to comply with the new legislation?
AUse only full-time employees even if the project is delayed.
BHire all team members to avoid any delay in the project.
CClose the contract and pay the contractors cash for the remainder of the project.
DLook for an overseas vendor to finalize the project work.
✓ Verified Answer: A
Question #165Part 3
A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following BEST describes this technique?
ADemonstration
BWorkshop
CBrainstorming
DFocus group
✓ Verified Answer: D
Question #166Part 3
While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?
AInstruct the team members to set their speakers to maximum volume and mute their microphones.
BRequire everyone to turn on their cameras and use the same background filter.
CEncourage the use of the chat and use plain language when speaking.
DAllow one person to speak at a time after receiving acknowledgment from the facilitator.
✓ Verified Answer: C
Question #167Part 3
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member MOST likely consulting?
APareto chart
BMilestone chart
CBurndown chart
DGantt chart
✓ Verified Answer: C
Question #168Part 3
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the BEST chart to use?
AMilestone
BGantt
CBurndown
DPERT
✓ Verified Answer: A
Question #169Part 3Select 2
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Choose two.)
APurchase the materials.
BAssign the resources.
CAccept delays in the work.
DApprove the deliverables.
EMonitor the performance.
✓ Verified Answer: DE
Question #170Part 3
A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do NEXT?
ARequest a change control ticket.
BReview the schedule plan.
CRefine the project documentation.
DRevise the communication plan.
✓ Verified Answer: D
Question #171Part 3
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
ASoftware as a service
BInfrastructure as a service
CData as a service
DPlatform as a service
✓ Verified Answer: B
Question #172Part 3
Which of the following tools is BEST to use for storing lessons learned?
AWhiteboard
BWiki knowledge base
CContent management system
DWorkflow platform
✓ Verified Answer: B
Question #173Part 3
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do NEXT?
AObtain details from the owner of the project.
BUpdate the critical path for the project.
CApply contingency reserves.
DReestimate epic user stories.
✓ Verified Answer: A
Question #174Part 3
Given the following network diagram: Which of the following is the critical path?
AA-C-G-K-M
BA-B-D-I-L-M
CA-B-E-J-L-M
DA-B-F-L-M
✓ Verified Answer: B
Question #175Part 3
A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?
AEscalate to vendor management.
BConsult the request for proposal.
CReview the meeting cadence.
DReinforce the rules of engagement.
✓ Verified Answer: D
Question #176Part 3
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take NEXT?
AInform the CCB to stop communication.
BEstablish a RACI matrix.
CEscalate the communication issues.
DRevise the communication plan.
✓ Verified Answer: D
Question #177Part 3
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
AIaaS
BXaaS
CPaaS
DSaaS
✓ Verified Answer: D
Question #178Part 3
A team member identifies a critical issue in production. Which of the following should the project manager apply?
ACompliance check
BRelease plan
CRollback plan
DValidation check
✓ Verified Answer: C
Question #179Part 3
A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following BEST describes what the team is developing?
AThe project closeout report
BA handover to operations
CPhase-gate review documentation
DA transition plan
✓ Verified Answer: D
Question #180Part 3
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do NEXT?
ABuy a replacement for the faulty equipment.
BGet the maintenance team to resolve the issue.
CEscalate the issue to the project sponsor.
DRate the severity of the impact the issue has on the project.
✓ Verified Answer: D
Question #181Part 4
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform FIRST?
ADefine the WBS.
BDevelop a RAM.
CManage the vendors.
DAssess the resource pool.
✓ Verified Answer: B
Question #182Part 4
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do FIRST?
AEscalate the change to the CCB.
BReview the requested change.
CDocument the change recommendations.
DValidate the implementation of the requested change.
✓ Verified Answer: C
Question #183Part 4
Which of the following statements BEST describes a content management system?
AA system to manage electronic signatures and document workflow
BA system to manage database integration and provide messaging services
CA system to manage shared data on the web, allowing multiple contributors to create, edit, and publish
DA system to manage documents archival, such as emails, spreadsheets, and support tickets
✓ Verified Answer: C
Question #184Part 4
Which of the following statements BEST describes zero-based budgeting?
AStart with the budget from the last project and add any new expenses.
BStart with allocating expenses based on the importance of the project.
CStart the project with a fixed amount decided by the management team.
DStart with no financial plan and justify each new expense.
✓ Verified Answer: D
Question #185Part 4
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps. Which of the following actions should the project manager take?
ANotify customers the downtime will take longer than expected.
BAdd new team members to help speed up validation.
CBegin executing the rollback plan.
DRecord the issue and proceed with the implementation.
✓ Verified Answer: C
Question #186Part 4Select 2
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Choose two.)
ACreating a backlog
BManaging the quality of deliverables
CUpdating the issue log
DPerforming a risk assessment
EValidating the deliverables
✓ Verified Answer: EF
Question #187Part 4
During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?
AAwareness of the local environment
BAwareness of the brand value
CAwareness of the resource constraints
DAwareness of the company's mission
✓ Verified Answer: A
Question #188Part 4
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
AInitiation
BClosing
CExecution
DPlanning
✓ Verified Answer: D
More COMPTIA Certification Practice Exams
Explore related COMPTIA exam dumps and free practice question banks.
220-1001204 Questions
CompTIA A+ Certification Exam: Core 1
220-1002235 Questions
CompTIA A+ Certification Exam: Core 2
220-1101279 Questions
CompTIA A+ Certification Exam: Core 1
220-1102335 Questions
CompTIA A+ Certification Exam: Core 2
220-120191 Questions
CompTIA A+ Certification Exam: Core 1
220-120287 Questions
CompTIA A+ Certification Exam: Core 2
220-90165 Questions
CompTIA A+ (220-901)
220-9027 Questions
CompTIA A+ (220-902)
CA1-0056 Questions
CompTIA SecurityX
CAS-0026 Questions
CompTIA Advanced Security Practitioner (CASP)
CAS-003189 Questions
CompTIA Advanced Security Practitioner (CASP) CAS-003
CAS-00465 Questions
CompTIA Advanced Security Practitioner (CASP+) CAS-004
📢 Unlock Full Access to Success!
"The content displayed here is a promotional preview and contains only 50% of the actual exam database. To access the complete set of updated questions, please upgrade to the Full Version."
👉 Click the button and follow the instructions to secure your full access immediately!