This course covers everything you need to pass the CompTIA Project+ (PK0-004) exam. Each part of this course contains real exam questions taken from the actual exam pool, with hint answers to guide your study. Practice with these questions to build confidence and master the topics needed for certification success.

What you'll learn

  • Master the core concepts for PK0-004 certification
  • Practice with real exam-style questions
  • Understand platform services and architectures covered in PK0-004
  • Build confidence through timed practice exams
  • Learn from detailed hint answers and explanations
  • Pass the official PK0-004 certification exam on your first try

PK0-004

Lectures5
Questions291
Duration30 week
Students18,404

$20.00

Full Free Question Bank (291 Questions)

CompTIA Project+ (PK0-004) Practice Questions & Verified Answers

Click any option to test your knowledge, or reveal the verified answer and detailed explanation below each question.

Jump to Section:
Question #1Part 1

A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?

ANetwork diagram
BIshikawa diagram
CWBS
DGantt chart
Question #2Part 1Select 2

Which of the following are characteristics of a project? (Choose two.)

AOngoing
BTemporary
CStart and finish
DAchieving a goal
EConsisting of milestones
Question #3Part 1

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?

ARFO
BRFI
CRFP
DRFQ
Question #4Part 1Select 2

The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

AThe issue log to show why the vendor should be replaced.
BThe team action items to show why the vendor should be replaced.
CThe scope statement to show why the vendor should be replaced.
DA procurement plan to show why the vendor should be replaced.
EA change management plan to have the vendor replaced.
Question #5Part 1

A project manager is creating the WBS. In which of the following phases is the project?

AInitiation
BPlanning
CExecution
DClosing
Question #6Part 1

Which of the following is a characteristics of a matrix organization?

AAuthority lies solely with the project manager.
BAuthority is directed by the project architect.
CAuthority is shared between the project manager and project coordinator.
DAuthority is shared between functional and project managers.
Question #7Part 1

A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

AProject team members
BProject sponsor
CProject manager
DProject scheduler
Question #8Part 1

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?

AProject schedule
BBalanced scorecard
CIssue log
DStatus report
Question #9Part 1Select 2

A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

AStatus report
BOrganizational chart
CRACI matrix
DMeeting minutes
ECommunication plan
Question #10Part 1

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks - A, B, F: 8 weeks - D, E, H: 12 weeks - D, B, F: 7 weeks - Which of the following tasks are on the critical path?

AA, C, G
BA, B, F
CD, E, H
DD, B, F
Question #11Part 1

A project team is comprised of a mix of in-house and virtual team members. When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

AComposing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.
BUsing text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.
CSending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.
DHosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.
Question #12Part 1

A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?

ABacklog
BStandup
CKickoff
DRetrospective
Question #13Part 1

A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps. Which of the following conflict resolution techniques is the project manager using?

AForcing
BNegotiating
CCompromising
DAvoiding
Question #14Part 1

A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?

AImplementation
BApproval
CValidation
DAuditing
Question #15Part 1Select 2

The PMO is responsible for: (Choose two.)

Amanaging the project plan, scope, risk, and budget.
Bcontributing expertise, deliverables, and estimates of costs.
Csetting standards and practices for the organization and providing governance.
Doutlining consequences of non-performance and coordinating between disparate projects.
Eapproving funding, developing the project schedule, and gathering high-level requirements.
Question #16Part 1

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?

AConfidentiality
BCriticality
CFrequency
DCultural differences
Question #17Part 1

Which of the following activities are associated with the closing phase of a project? (Choose two.)

ARisk mitigation
BArchiving of project documents
CTracking of expenditures
DLessons learned
EQuality assurance
Question #18Part 1

Which of the following describes a burn rate?

AThe rate at which project documents are disposed.
BThe rate at which project personnel leave the project.
CThe rate at which the project budget is used.
DThe rate at which the timeline increases.
Question #19Part 1

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?

AEvaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
BEvaluate the risk, fill in the issue log, and communicate it according to the communication plan.
CEvaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
DEvaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Question #20Part 1

One deliverable failed during testing, and this has already happened several times. Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?

ARun chart
BFishbone diagram
CScatter diagram
DGantt chart
Question #21Part 1

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?

ABusiness case
BRequirements document
CProject timeline
DTask plan
Question #22Part 1

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project manager update to document this information?

AA list of realized risks
BA list of decomposed activities
CA sequenced list of project tasks
DA document describing agreed-upon communication methods
Question #23Part 1

The executive sponsor asks a project manager to summarize the following for a project: 1. Final capital expenditures. 2. Anticipated cost of new employee resources to support the solution. 3. Maintenance estimates. Which of the following information should the project manager provide?

ACost baseline
BBurn rate
CCost variance report
DTotal project cost
Question #24Part 1

Which of the following defines a group of projects that work together to achieve a common goal?

AProduct
BPortfolio
CProgram
DProject plan
Question #25Part 1

A company hires an outside vendor to provide 24/7 support. Which of the following documents would determine the contractual obligations?

APO
BSLA
CLOI
DMOU
Question #26Part 1

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?

AThrottling
BCrashing
CResource leveling
DResource smoothing
Question #27Part 1

A project manager is unsure if the quality of a deliverable from a SME meets specifications. Which of the following is the BEST way for the project manager to address the issue?

AConduct a face-to-face or telephone meeting with the team member.
BSend an email outlining the concerns to the team member.
CSend a project team meeting to obtain feedback from everyone.
DPost the issue on the wiki page for input from stakeholders.
Question #28Part 1

Which of the following is a key aspect of the Agile project management methodology?

ATest-driven
BDaily standup meetings
CShort project durations
DDefined list of requirements
Question #29Part 1

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?

AAssess the risk register's new items.
BReview the task start and finish dates.
CObtain additional resources.
DAnalyze the assigned hours.
Question #30Part 1

A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements. Which of the following actions would be BEST for the project manager to take?

AAsk the client to provide additional language resources to the team.
BPurchase a language translation program.
CHire a translator to help the key team member
DAsk the client to provide requirements in the native language of the team.
Question #31Part 1

After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?

AUse milestones identified in the project charter.
BUse data based on past knowledge.
CHold a full team workshop to review the complete WBS.
DCollaborate with other project managers.
Question #32Part 1

A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor. Which of the following terms describe this requirement?

AOutsourcing
BBusiness acquisition
CBusiness process change
DInternal reorganization
Question #33Part 1

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the following constraints are MOST likely to be affected? (Choose two.)

AQuality because the existing system is now outside the threshold.
BRequirements because this is a change to initial scope.
CCost because replacing the system incurs additional expense.
DSchedule because this was an unscheduled task and will impact the timeline.
EStakeholders because they will need to understand the modification and provide buy-in.
Question #34Part 1

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

ASCRUM retrospective
BKickoff meeting
CBudget baseline
DRisk review
Question #35Part 1

The project manager has noticed a vendor is not performing in accordance with the SLA. Which of the following items should the project manager use to highlight the vendor's areas of poor performance?

ABalanced score card
BWBS
CPost-project evaluation
DPERT
Question #36Part 1

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option. This type of conflict resolution is known as:

Aforcing.
Bavoiding.
Csmoothing.
Dcompromising.
Question #37Part 1

Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

AEAC
BBAC
CCPI
DETC
Question #38Part 1

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?

AThe project manager should identify and document the reasons for the additional resources in a change request.
BThe project manager should hire additional resources temporarily to complete the project.
CThe project manager should terminate the project until additional resources are added to the project.
DThe project manager should ask the project team members to take on more tasks to complete the project on time.
Question #39Part 1

An organization has multiple projects that are taking place simultaneously. Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

APMO
BProject sponsor
CProject coordinator
DHR
Question #40Part 1

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

AIssue log
BRisk management plan
CCommunications plan
DRisk register
EStatus report
Question #41Part 1

A milestone task on the critical path has been completed. Which of the following should the project manager notify?

AOwner of predecessor task
BProject team
CProject sponsor
DProject steering committee
Question #42Part 1

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?

AAlert the project sponsor of the situation.
BContact the customer and request more funding.
CAnnounce the project will end early due to lack of funds.
DAttempt to save money in downstream activities.
Question #43Part 1

Which of the following is the primary purpose of an MOA or an MOU?

AState expectations of all signatory parties to reduce potential misunderstandings.
BFacilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
CEnumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
DProvide transparency to competitors regarding all signatory parties.
Question #44Part 1

Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process. Which of the following conflict resolution techniques has the project manager utilized?

ASmoothing
BForcing
CCompromising
DAvoiding
Question #45Part 1

The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?

AExecution
BKickoff
CClosure
DPlanning
Question #46Part 1

A project manager is working on the project charter. Which of the following phases does this describe?

AInitiation
BPlanning
CExecution
DClosing
Question #47Part 1

A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?

AUpdate the project management plan.
BIssue a change request.
CRevise the project charter.
DEvaluate the impact to the baseline.
Question #48Part 1

Several team members report that meeting objectives are not being met. Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)

ACreate an SOW prior to each meeting and adhere to it.
BCreate a meeting agenda prior to each meeting and adhere to it.
CCreate a lessons learned list prior to each meeting and adhere to it.
DCreate a project charter prior to each meeting and adhere to it.
ECreate an action item list during the meeting and adhere to it.
Question #49Part 1

Which of the following documents should be used to provide high-level reporting to key stakeholders?

ADashboard
BCommunication plan
CStatement of work
DProject charter
Question #50Part 1

A new project charter is being drafted. Which of the following would be the BEST source for the high-level project requirements?

ASponsor
BProject manager
CProject management office
DProject team
Question #51Part 1

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

ASOW
BPO
CSLA
DMOU
Question #52Part 1

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

AEAC
BBAC
CTCPI
DETC
Question #53Part 1

A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?

AWaterfall
BAgile
CPRINCE2
DBottom-up
Question #54Part 1

Which of the following describes risk mitigation?

AThe transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
BThe understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
CThe quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.
DThe weighting or prioritization of the risk against all other identified risks within this project or others associated with it.
Question #55Part 1

Which of the following is a definition of an RFP?

AA document sent to potential vendors to solicit a bid for a project.
BA document sent to potential vendors to request information for skills and experience for a project.
CA document sent to potential vendors to request a commitment for a project.
DA document sent to potential vendors to solicit information that excludes pricing information for a project.
Question #56Part 1

A customer has requested additional features for an active project. Which of the following steps should take place NEXT?

AImplement the requested changes.
BEvaluate the impact of the changes.
CUpdate all project documents.
DSubmit the requested changes to the CCB.
Question #57Part 1

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project's success. Which of the following risk strategies should the project manager adopt?

AExploitation
BAvoidance
CAcceptance
DMitigation
Question #58Part 1

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

ASales clerk
BMarketing representative
CTeam lead
DProduct item
Question #59Part 1

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

A12 days
B14 days
C16 days
D19 days
Question #60Part 1

A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference. Which of the following is MOST likely to be the main challenge the influences this decision?

AGeographical factors
BLanguage barriers
CCultural differences
DTechnology factors
Question #61Part 2

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?

APlace a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.
BRaise a purchase order to purchase the licensing and ask the team member to install it.
CAmend the project scope and raise a project change request to obtain approval of the amendment.
DAmend the project schedule and work breakdown structures to remove the use of the software from the project.
Question #62Part 2

A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)

AThe project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
BThe project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
CThe project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
DThe project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
EThe project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
Question #63Part 2

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?

AGain approval for the changes.
BIdentify the approval authority.
CImplement the changes.
DCreate an emergency change request.
Question #64Part 2

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?

APersonal preferences
BTechnological factors
CLanguage barriers
DCultural differences
Question #65Part 2

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?

AEstablish each WBS work package resource.
BEstablish and set the baseline.
CEstablish and set the quality gates.
DEstablish the tollgates.
Question #66Part 2

Which of the following describes how a project is related to a program?

AA program is a combination of multiple projects.
BA program contains an element of the project.
CA program is a part of a project.
DA program uses half of the project's budget.
Question #67Part 2

Which of the following are examples of organizational change? (Choose two.)

ARelocation
BScope
CBusiness process
DSchedule
ERisk event
Question #68Part 2

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

AProject schedule
BCost plan
CScope statement
DImpact assessment
Question #69Part 2

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?

ACost, schedule, organizational chart, and risks/issues
BRisks/issues, cost, RACI chart, and action items
CSchedule, cost, risks/issues, and milestones
DAction items, organizational chart, schedule, and NDA
Question #70Part 2

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?

ADuring the planning phase, the project manager should have recognized the relationship between the vendor's and project team's tasks and adjusted the schedule for the project team to begin activities two months later.
BThe project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
CDuring the project team's regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
DDuring the project team's regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.
Question #71Part 2

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator use?

ARisk register
BIssue log
CCommunication plan
DStatus report
Question #72Part 2

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST likely to have on the project?

AThe deliverables and quality will remain the same, but the cost will increase.
BThe deliverables and quality will remain the same, but the cost will decrease.
CThe deliverables and cost will remain the same, but the quality will increase.
DThe cost and quality will remain the same, but the deliverables will increase.
Question #73Part 2

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?

AUpdate the scope management plan.
BModify the project baselines.
CImplement change control management.
DInform the stakeholders of the issue.
Question #74Part 2

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date. To alter the pace of the project, which of the following should the project manager do FIRST?

AGive approval for the change requested by the project sponsor.
BDeny the request from the project sponsor.
CDocument the change request from the project sponsor.
DAsk the project sponsor to change the request.
Question #75Part 2

Which of the following is a schedule that illustrates the duration of an activity?

AProcess diagram
BIshikawa diagram
CGantt chart
DPareto chart
Question #76Part 2

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:

Afollow the change process flow and notify the legal department after the change is implemented.
Bextend a formal invitation to the legal department representative to join the CCB.
Chold a separate meeting with the legal department representative and ask for approval.
Dnotify the legal department representative in the event of an upcoming audit.
Question #77Part 2

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change. Which of the following is the MOST likely reason?

AEstablished communication plan
BScope creep
CResource constraints
DIterative approach
Question #78Part 2

In which of the following organizational structures would a project manager have the MOST authority?

AProjectized
BStrong matrix
CBalanced matrix
DFunctional
Question #79Part 2

A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility. Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

AEmail
BSocial media
CText messaging
DFace-to-face
Question #80Part 2

A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule. The project manager is concerned that the requests will lead to:

Aquality control issues.
Badditional risks.
Cscope creep.
Dtime constraints.
Question #81Part 2

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager?

AProject charter
BProject management plan
CProject statement of work
DProject schedule
Question #82Part 2

A project manager has noticed poor attendance as status meetings. Which of the following strategies should the project manager use to improve attendance? (Choose two.)

AProvide an agenda before the status meeting.
BAdhere to an agenda and scheduled time.
CAdd non-project-related items to the agenda.
DAdd and discuss new agenda items throughout the meeting.
EDiscard the action items at the conclusion of the meeting.
Question #83Part 2

Which of the following events would MOST likely trigger communications to the largest audience for a given organization?

ABusiness continuity response
BQuality audit
CReplacement of a subcontractor
DCompletion of a task
Question #84Part 2

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

AThe project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
BThe scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
CThe scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
DThe scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Question #85Part 2

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project manager using?

ACompromising
BSmoothing
CWithdrawing
DAccepting
Question #86Part 2

An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:

Aan RFP.
Ban NDA.
Can SLA.
Dan MOU.
Question #87Part 2

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

AProject manager and project scheduler
BProject coordinator and project sponsor
CProject champion and project scheduler
DProject stakeholders and project team
Question #88Part 2

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?

ASubmit a new change request.
BInitiate the regression plan.
CAdd remediation to the schedule.
DAccept the new power output.
Question #89Part 2

A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take?

ATell the senior manager the estimation is not available yet.
BUse the budget from a similar project to generate estimates.
CAsk a SME for an opinion and propose an estimate.
DGather the team to immediately generate estimates.
Question #90Part 2

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.)

AScope management plan
BConfiguration management plan
CNetwork diagram
DProject schedule
EProject plan
Question #91Part 2

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

AQuality
BRegulations
CSchedule
Dproject team
Question #92Part 2

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?

AReduce the scope
BIncrease the budget
CDecrease staff
DUpdate the WBS
Question #93Part 2

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

ATransfer
BAccept
CAvoid
DMitigate
Question #94Part 2

A company is hired to perform some of another organization's work. Which of the following types of organizational change is described?

AOutsourcing
BBusiness process change
CShared resources
DSplit
Question #95Part 2

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

AAdditional resources
BA gate review
CA risk register update
DA performance audit
Question #96Part 2

A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

ACost performance parameter
BProject schedule
CKPI
DCorrective action plan
EWBS
Question #97Part 2

A project has activities on the critical path that must be completed before other activities can start. Task A is dependent on Task C before Task D can be completed. Task A requires task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?

AB, A, D
BC, B, D, A
CD, A, C
DB, C, A, D
Question #98Part 2

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB. Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

A12 days
B16 days
C17 days
D22 days
Question #99Part 2

Which of the following job roles is primarily tasked with communicating the project timeline changes?

AProject scheduler
BProject manager
CProject sponsor
DProject coordinator
Question #100Part 2Select 2

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early. Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

ACost
BPredecessors
CLag
DDurations
EResource loading
Question #101Part 2

A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

AWait until the change requests are approved by the CCB.
BApprove the changes because the additional functionality is required to complete the process.
CSpeak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
DSchedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
Question #102Part 2

The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?

ASchedule a conference call for the team meeting and invite the chairperson.
BArrange an impromptu team meeting with the chairperson.
CEmail the chairperson the meeting minutes from the scheduled meeting
DInvite the chairperson to the next project team meeting
Question #103Part 2

Which of the following are characteristics of a project? (Choose two.)

AA project is a temporary endeavor.
BA project provides a unique product, service, or result.
CA project is an ongoing endeavor.
DA project involves scheduled maintenance.
EA project includes life-cycle cost management.
Question #104Part 2

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

ATransfer
BShare
CMitigate
DAvoid
Question #105Part 2

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

ASCRUM retrospective meeting
BSprint planning meeting
CDaily standup meeting
DReview meeting
Question #106Part 2

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

APersonal preference
BIntra-organizational differences
CCulture
DTime zone
Question #107Part 2

A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?

ARisk register
BPost-mortem analysis
CIssue log
DProcurement report
Question #108Part 2

A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:

AResource leveling
BStaff Augmentation
CWork relocation
DOutsourcing
Question #109Part 2

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

AMOU
BMOA
CSOW
DSLA
Question #110Part 2

Which of the following roles has approval authority for project funding?

AChampion
BChief Financial Officer (CFO)
CProject Management Office (PMO)
DSponsor
Question #111Part 2

Which of the following is an example of a project?

APurchasing pedometers from local retail stores for employees
BImplementing a health awareness program at an organization
CConducting semi-annual blood drives at an organization
DPresenting a scripted workshop at an organization's three locations
Question #112Part 2

A project is about to begin the execution phase. The SOW and project plan have been approved, and the project team has been formed. Which of the following types of meetings should happen NEXT?

AUpdate
BScheduling
CKickoff
DReview
Question #113Part 2

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?

AIssue log and process diagram
BResource analysis and Gantt chart
CStakeholder analysis and communication plan
DScatter chart and scope analysis
Question #114Part 2

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

AZero
BOne
CTwo
DThree
Question #115Part 2

A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?

ARF1
BRFP
CRFQ
DChange request
ERequest for bid
Question #116Part 2

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?

AReview the PERT chart and evaluate if the task is a critical dependency.
BReview the PERT chart and evaluate if the task is a discretionary dependency.
CReview the PERT chart and evaluate if the task is a real dependency.
DReview the PERT chart and evaluate if the task is an external dependency.
Question #117Part 2

A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?

ALanguage barriers
BTime zones
CCultural differences
DPersonal preferences
Question #118Part 2Select 2

Which of the following vendor documents specifically address quality? (Choose two.)

ALOI
BSLA
CWarranty
DPO
ENDA
Question #119Part 2

A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the work packages for the WBS?

ABrainstorming
BAnalogous
CBottom-up
DForward pass
Question #120Part 2Select 2

Which of the following documents need to be updated as events occur during a project? (Choose two.)

AChange request
BRisk register
CMeeting minutes
DIssue log
EStatus report
Question #121Part 3

During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

AChange request
BRisk mitigation
CChange control
DScope creep
Question #122Part 3

A project manager is assigned to an ongoing project. Which of the following is the FIRST document the project manager should review?

AProject schedule
BAction items
CProject charter
DCommunication plan
Question #123Part 3

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

AAdd durations.
BAdd the start and finish dates
CAdd tasks.
DAdd resources.
Question #124Part 3

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members' managers Which of the following types of organizational structures did the new project manager MOST likely join?

ABalanced matrix
BStrong matrix
CFunctional
DProjectized
Question #125Part 3

Which of the following shows projected project expenditures?

AWork breakdown structure
BCash flow schedule
CCash burn rate
DBudget milestone
Question #126Part 3

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)

AUsing the WBS will help prevent work from slipping or being forgotten.
BTheWBS will be required on very large projects.
CTheWBS will be required if the project manager has the time available to complete it.
DTheWBS will aid in determining which resources are required for the project.
EThe WBS is the best way to determine risks of the project.
Question #127Part 3

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

AIssue log
BAction items
CDashboard information
DCommunication plan
Question #128Part 3

Which of the following elements should be included on a responsibility assignment matrix?

AResponsible, accountable, consulted, informed
BResource, accountable, signoff, input
CResponsible, accurate, confidential, informed
DResource, accountable, consulted, informed
Question #129Part 3

The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?

AProject charter
BProject schedule
CMeeting agenda
DResponsibility assignment matrix
ERisk register
Question #130Part 3

Which of the following charts is a graphical representation of the causes of a specific event?

AHistogram
BScatter
CFishbone
DGantt
Question #131Part 3

While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

Aquality plan.
Bproject management plan.
Crisk register.
Dprocess diagram.
Question #132Part 3

A project is in the initiation phase. Which of the following tasks will take place during this phase?

ADevelop a WBS.
BDefine the project requirements.
CCreate a project charter.
DAcquire the project resources.
Question #133Part 3

A team member has completed an assigned task. Which of the following roles should be notified FIRST?

AProject sponsor
BKey stakeholders
CProject manager
DProject team
Question #134Part 3

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

ASLA
BSOW
CChange request
DRFP
Question #135Part 3

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

ASubmit a change request.
BEvaluate the impact of the change.
CGet approval from the CCB.
DCommunicate the change to stakeholders.
Question #136Part 3

Using Scrum, which of the following are discussed in a daily standup meeting?

AWhat was done yesterday, what is planned for today, and what roadblocks need to be removed
BWhat was done yesterday, what is planned for the week, and what issues were resolved
CWhat was done yesterday, what is planned for today, and what deliverables were completed
DWhat was done yesterday, what is planned for this week, and what items from the backlog are priority
Question #137Part 3

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. Which of the following calculations accurately shows the critical path?

A20 days
B39 days
C49 days
D52 days
Question #138Part 3

׀ new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?

AIdentify and document the risk.
BEvaluate the impact and justification.
CImplement the change.
DUpdate the documents and plans.
Question #139Part 3

A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?

AVendors
BKey stakeholders
CResources
DProject team
EBusiness analysts
Question #140Part 3

Which of the following inherently affects quality standards?

ASLA
BMOA
CMOU
DWBS
Question #141Part 3

At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?

AProject charter, organization chart, scope statement, and issue log
BDashboard information, action items, project schedule, and status report
CProject management plan, scope statement, communication plan, and meeting agendas
DProject schedule, project management plan, communication plan, and issue log
Question #142Part 3

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

AFast-track the tasks.
BUtilize positive float.
CCrash the schedule.
DRemove the critical path
Question #143Part 3

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

Ainternal project team.
Bkey stakeholders.
Caffected team members.
Dfull project team.
Question #144Part 3

An industry leader may be joining the project team and can potentially provide additional expertise. Which of the following strategies should the project manager employ?

AExploitation
BAcceptance
CValidation
DTransfer
Question #145Part 3

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

AReduced quality
BReduced scope
CReduced risk
DReduced timeline
Question #146Part 3

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?

AAhead of schedule and over budget
BBehind schedule and under budget
CAhead of schedule and under budget
DBehind schedule and over budget
Question #147Part 3

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

ATime
BSchedule
CScope
DCost
Question #148Part 3

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

AResource loading
BResource leveling
CPrioritizing tasks
DAllocating resources
Question #149Part 3

Which of the following would indicate a project manager is working in a matrix-based organization?

AThe project manager has full authority over resources and the project.
BThe project manager has no authority over the project resources and limited-to-no authority over the project.
CResources align to the project, report to the project manager, and have no functional home at the end of the project.
DResources report to business area functional managers and return to the functional area at the end of the project.
Question #150Part 3

Two team members approach a project manager with different ideas for completing a task. After listening to the team members' ideas, the project manager does not choose either one and requires both members to finish the task as originally planned. Which of the following conflict resolution techniques is the project manager applying?

AAvoiding
BSmoothing
CForcing
DCompromising
Question #151Part 3

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

Adurations.
Btasks.
Ccritical path.
Dresources.
Question #152Part 3

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

APareto chart
BFishbone diagram
CProcess diagram
DRun chart
Question #153Part 3

A project has a ׀’׀׀¡ of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?

AAdd the required work to complete the project behind $892,500.
BEvaluate the impact and justify adding new work to the project.
CObtain approval from the CCB.
DRequest a budget increase of $170,000.
Question #154Part 3

A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?

AInitiation
BPlanning
CMonitor and control
DClosing
Question #155Part 3

A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?

AThe company received a C&D.
BA higher-priority project needed the expertise.
CThe new member did not sign an NDA.
DAn SLA prevented new team members.
Question #156Part 3

In which of the following categories does a business process change fit?

AProject change
BOrganizational change
CGeneral change
DDepartmental change
Question #157Part 3

A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the MOST likely reason for the failed inspection?

AThere were insufficient resources assigned to the task.
BThe prior document version was not reviewed.
CVersion control processes were not applied.
DThe CCB was not contacted.
Question #158Part 3

A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?

AThe reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
BThe reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
CThe reduced timeline will decrease risk, resulting in an increased contingency reserve.
DThe reduced budget will cause the project manager to reject the change order.
Question #159Part 3

Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?

AOne-on-one meetings
BProject wiki
CText messages
DSocial media
Question #160Part 3

A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 - PV = 80 - EV = 120 - Based on this information, the CPI reflects which of the following about the project?

AIt is under budget.
BIt is over budget.
CIt is ahead of schedule.
DIt is behind schedule.
Question #161Part 3

In a project with a ׀’׀׀¡ of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

AThe project is under budget and ahead of schedule.
BThe project is over budget and ahead of schedule.
CThe project is under budget and behind schedule.
DThe project is over budget and behind schedule.
Question #162Part 3

The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit. Which of the following actions should the project manager take?

AInitiate change control.
BFollow communications plan.
CManage project quality.
DPrepare a performance report.
Question #163Part 3

A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?

ATechnical design, schedule, and budget
BBusiness process impacts and resourcing
CNew software and hardware requirements
DSchedule, budget, and quality
Question #164Part 3

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

ACost performance index
BRisk mitigation
CSchedule variance
DCost variance
Question #165Part 3

The design activity of a project has the following cost attributes: PV = 100,000 - EV = 20,000 - AC = 90,000 - Based on this scenario, calculate the schedule variance.

Aגˆ’80,000
Bגˆ’70,000
C10,000
D120,000
Question #166Part 3

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should the project manager do to ensure stakeholder expectations are met?

AEnsure that Ann is involved during the testing phase of the project so she can call out functional gaps.
BOrganize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
CEscalate the issue to the project steering committee that Ann is criticizing the project quality.
DOrganize a requirements workshop to capture any gaps.
Question #167Part 3

Which of the following techniques modifies the schedule based upon resource constraints?

ACritical Chain Method
BCritical Path Method
CArrow Diagramming Method
DPrecedence Diagramming Method
Question #168Part 3

Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:

AManaging change
BFast tracking
CRolling wave planning
DCrashing
Question #169Part 3

The project's network map has a loop with multiple project outcomes. This is the result of which of the following scheduling tools?

AEstablishing project schedule baselines
BCritical Path Analysis
CCritical Chain Method
DGraphical evaluation and review technique
Question #170Part 3

Which of the following tools would a project manager use to determine the root cause of an issue?

APareto Chart
BIshikawa Diagram
CHistogram
DMonte Carlo Analysis
Question #171Part 3

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

ACritical Path Method
BArrow Diagramming Method
CCritical Chain Method
DPrecedence Diagramming Method
Question #172Part 3

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

ACritical Path Method
BCritical Chain Method
CArrow Diagramming Method
DGantt Chart Method
Question #173Part 3

Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?

AExpansion
BRightsizing
CMerger
DOnboarding
Question #174Part 3

A project manager is not required to participate in performance appraisal meetings with team members. The project manager is working within which of the following organizational structures?

AProjectized
BBalanced matrix
CFunctional
DStrong matrix
Question #175Part 3

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. Which of the following represents the cost variance for both project completions?

Aגˆ’$4.8K and גˆ’$7K
Bגˆ’$4.9K and $7K
C$4.8K and גˆ’$7K
D$4.8K and $7K
Question #176Part 3

A daily standup Scrum meeting is BEST accomplished in a:

Atelephone conference.
Bgroup email.
Cface-to-face meeting.
Dvideo conference.
Question #177Part 3

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

AProject communication plan
BProject status report
CProject management plan
DProject backlog
Question #178Part 3

When an action is taken on a risk, which of the following is being done and which document needs to be updated?

AMitigating risk, and the risk register should be updated
BAccepting risk, and the risk review document should be updated
CAvoiding risk, and the risk review document should be updated
DExploiting risk, and the risk register should be updated.
Question #179Part 3

A project schedule lists a resource as 50% because it likely:

Ais a shared resource.
Bdepict a resource shortage.
Csignifies overallocation of a resource.
Dnotes underallocation of a resource.
Question #180Part 3

A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?

ATeam Building
BTeam Selection
CResource loading
DResource leveling
Question #181Part 4

The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?

APersonal preferences and message content
BLevel of message/report detail and confidentiality constraints
CTime zones and language barriers
DTechnological and criticality factors
Question #182Part 4

A project team is defining detailed risks. Which of the following project phases is taking place?

AInitiation
BMonitor and control
CExecution
DPlanning
Question #183Part 4

Which of the following statements are correct regarding project management? (Choose two.)

AA project can be part of an organization's program management.
BAn organization's portfolio will include programs.
CA program has a defined start and finish.
DAn organization's portfolio is a temporary and unique endeavor.
EA project portfolio will be managed under program management.
Question #184Part 4

A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

ARequirements traceability matrix
BGantt chart
CSWOT analysis
DProject charter
Question #185Part 4

Which of the following documents is typically signed by the vendor and includes a reference for how customers' internal information will be protected?

AMOU
BNDA
CSOW
DSLA
Question #186Part 4

A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?

AGo over the meetings objectives and agenda.
BBrief the team on which tasks have fallen behind schedule and where the project has slack.
CRefer to the risk register to map the risks to issues and mitigation strategies.
DReview the issue log with the project team and identify potential risks.
EReview an Ishikawa diagram with the project team to determine possible causes and effects.
Question #187Part 4

A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?

ACrashing the schedule
BPrioritizing tasks
CDetermining milestones
DDeveloping sprints
Question #188Part 4

A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?

ADraft a C&D letter and send it to vendor.
BReview the MOU with the vendor.
CAsk the legal departments to draft a non-complete agreement for the vendor to sign.
DMeet with the finance department to prevent the vendor from sending invoices.
Question #189Part 4

During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

Athere is unfamiliarity with the project structure.
Bthere is a lack of trust among team members.
Cthere are minimal team decisions.
Dthere is no engagement of the team by the project manager.
Question #190Part 4

A project manager procures additional resources from a local company. Which of the following-describes this event?

AReorganizing
BOnboarding
COffshoring
DOutsourcing
Question #191Part 4

In which of the following situations is a project manager MOST likely to use a process diagram?

AWhen describing a new business idea for the team to review
BWhen describing a new business workflow for the team to implement
CWhen describing a new business project for the team to implement
DWhen describing a new business acquisition for the team to review
Question #192Part 4

A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?

AKickoff meeting
BOne-on-one meetings
CVoice conferencing
DInstant messaging
Question #193Part 4

A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?

ASchedule
BMilestone
CGate
DTask
Question #194Part 4

A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

AEmail
BDistribution of printed media
CFace-to-face
DVideo conferencing
Question #195Part 4

During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?

AAsk the team member to move to a different test environment.
BAsk the team member to refrain from testing the scenarios.
CRevisit the risk management plan and provide corrective actions.
DRevisit the contingency plan and provide corrective actions.
Question #196Part 4

A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?

ADetermine the expected duration of the rework and complete a charge request to modify the project baselines.
BNotify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
CDetermine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
DUpdate the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.
Question #197Part 4

A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?

AResponsibility matrix
BResource allocation plan
CProject charter
DStatement of work
Question #198Part 4Select 2

Which of the following are mutually binding project documents? (Choose two.)

AQuotation
BLetter of intent
CProposal
DEvaluation
EWarranty
Question #199Part 4

A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?

ADefine the communications plan.
BRecord the missed tasks on the issue log.
CProvide meeting minutes after each call.
DComplete a fishbone diagram.
Question #200Part 4

A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?

AIncident response
BQuality control
CResource changes
DBusiness continuity response
Question #201Part 4

A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?

AProcess diagram
BChange control plan
CBalanced scorecard
DSWOT matrix
Question #202Part 4

An active project has a CPI of 0.92. Which of the following can be determined?

AThe project is currently over budget.
BThe project has a budget surplus.
CThe project is ahead of schedule.
DThe project is behind schedule.
Question #203Part 4

A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations. The project team must ensure completion of the:

Abusiness continuity plan.
Bincident response plan.
Cdisaster recovery plan.
Drisk management plan.
Equality management plan.
Question #204Part 4

While developing a project schedule, the project manager is attempting to sequence the following tasks: Which of the following is the correct sequence for the above tasks?

AF, C, A, E, B, D
BF, E, C, B, A, D
CF, A, B, C, E, D
DD, B, E, F, C, A
Question #205Part 4

Which of the following represents additional unauthorized requirements from the client?

AScope creep
BChanging scope baseline
CChange request
DGold plating
Question #206Part 4

A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?

AIssue log
BStatus report
CRisk register
DSOW
Question #207Part 4

Before a team can start on a sprint, they will need to:

Acreate a set of iterations to work on and prioritize.
Bgenerate an icebox of work items to review.
Creview the backlog of work items to prioritize.
Dtake client requirements and draft them into a task list.
Question #208Part 4

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?

ARevise the project plan.
BUpdate the issue log.
CRequest additional funding.
DIssue a change request.
Question #209Part 4

Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?

AEncrypted email
BFace-to-face communication with a translator
CSocial media communication through a secure connection
DVoice conferencing
Question #210Part 4

Which of the following defines the minimum level of engagement of a stakeholder?

APassive
BInvested
CContributing
DInterested
Question #211Part 4

At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?

ATeam contract
BCorrective action plan
CUser acceptance policy
DMOU
ESLA
Question #212Part 4

A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?

ABusiness process change
BBusiness merger
CInternal reorganization
DInterorganizational change
Question #213Part 4

A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?

AIncident response plan
BRegression plan
CProgress plan
DBusiness continuity plan
Question #214Part 4

Which of the following information does the project risk register typically contain?

AType of risk, identified risk, risk response, impact of risk, severity of risk
BType of risk, project task, risk response, impact of risk, severity of risk
CType of risk, identified risk, risk response, project schedule risk, severity of risk
DType of risk, identified risk, risk response, impact of risk, risk avoidance
Question #215Part 4

A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?

AIndividually call all project team members.
BSend an email to all project team members.
CSchedule a conference call.
DSchedule a face-to-face meeting.
Question #216Part 4

Which of the following documents ensures two parties do not share contractually binding information?

AC&D letter
BRFI
CNDA
DMOU
Question #217Part 4

Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks: Which of the following tasks are on the critical path?

AA, D, C, G
BA, B, H, G
CA, D, E, F
DA, B, C, G
Question #218Part 4

Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?

ASLA
BProject charter
CRisk register
DRFP
Question #219Part 4

A project manager is overseeing a multinational project, and team leaders from numerous countries indicate the team members have low morale. Which of the following is the MOST likely reason the project manager would be unaware of the team member's decreased morale?

AThe project manager did not pay attention to visual cues.
BThe project manager did not perform active listening.
CThe project manager did not prioritize team member concerns.
DThe project manager did not visit the project's international office locations.
Question #220Part 4

A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?

ADeny the CEO's request.
BImplement the project change.
CSubmit the request to the CCB.
DAsk the CEO to follow the communications plan.
Question #221Part 4

Which of the following is a characteristic of a project?

AIt solves a business problem.
BIt created a unique service.
CIt has a definite beginning and end.
DIt adheres to a formal framework.
Question #222Part 4

A project manager has been experiencing resistance from a group of stakeholders. With which of the following should the project manager consult to reduce friction going forward?

AProject scheduler
BProject coordinator
CProject sponsor
DProject management office
Question #223Part 4

Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement?

ASmoothing
BCollaborating
CCompromising
DAvoiding
Question #224Part 4

During the planning phase of a construction project, the project team discovers the site is the nesting area of rare birds, and construction could disrupt the birds' patterns. Lobbyists would like the team to move the project down the road. Which of the following constraint and influencer types are involved in this scenario?

AEnvironmental; resources
BEnvironmental; stakeholders
CDeliverables; resources
DDeliverables; stakeholders
Question #225Part 4

Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)

AFishbone diagram
BRACI matrix
CMonte Carlo
DProcess flowchart
EExpert judgment
Question #226Part 4

A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.)

AMail the purchase order and follow up with a phone call.
BFax the purchase order and follow up with a phone call.
CDrive to the vendor if local and provide a signed purchase order.
DScan and send the purchase order and follow up with a phone call.
ERequest a courier from the vendor to pick up the purchase order.
Question #227Part 4

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue?

ARisks were not identified.
BRisks were not mitigated.
CRisks were not exploited.
DRisks were not communicated.
Question #228Part 4

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented: ✑ Project description ✑ Draft project timeline and schedule ✑ Rough milestones ✑ Draft project budget ✑ Draft resources required High-level risk review - Which of the following sections should be included in this document?

ABusiness information
BFull risk assessment results
CDraft work breakdown structure
DFull resource requirements
Question #229Part 4

A PM is reviewing bids from vendors and has a question. Which of the following documents should the PM use to obtain a response?

AProject schedule
BRFP
CQuotation
DRFI
Question #230Part 4

A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:

Ashared resource contention
Bintraproject resource contention
Cinterproject resource contention
Ddedicated resource contention
Question #231Part 4

A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?

ASocial media
BEmail
CInstant messaging
DTeam meeting
Question #232Part 4

An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work. Which of the following types of procurement should be used?

ARequest for information
BRequest for quote
CRequest for bid
DRequest for proposal
Question #233Part 4

Which of the following captures unforeseen activities throughout the project that need attention and resolution?

AGantt chart
BAction items
CProject schedule
DMeeting minutes
Question #234Part 4

Which of the following project phases would MOST likely include creating a transition plan?

AClosing
BInitiation
CExecution
DPlanning
Question #235Part 4

The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company. The sale of this division is an example of which of the following?

AOutsourcing
BRelocation
CBusiness process change
DBusiness merger
Question #236Part 4

Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status. Which of the following types of reports should the project sponsor use to quickly summarize the status report data?

APie chart
BRun chart
CProject schedule
DDashboard information
Question #237Part 4

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint described in this scenario is:

Acost
Benvironmental
Cscope
Dscheduling
Question #238Part 4

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it. Which of the following steps of the control was missed?

ACommunicate the change
BQuality check
CImplementation
DEvaluate impact and justification
Question #239Part 4

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)

APlanned value
BSchedule variance
CAcceptable variance
DCost variance
EEarned value
Question #240Part 4

The project manager needs to motivate the team; however, there is an insufficient budget for awards. Which of the following motivating agents is the MOST appropriate option the project manager can utilize?

AReduce the workload
BReplace resources
CExtend the timeline
DProvide additional responsibility
Question #241Part 5

A project manager needs status on the project timeline. Which of the following team members should provide an update?

AProduct owner
BBusiness analyst
CScheduler
DSponsor
Question #242Part 5

Under an Agile methodology, standup meetings occur:

Adaily
Btwice daily
Cweekly
Dad hoc
Question #243Part 5

A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

Aproject management plan
Bscope statements and issue log
Cproject dashboard and status report
Daction items and meeting minutes
Question #244Part 5

A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter: ✑ Project title description ✑ Preassigned resources ✑ Budget ✑ WBS ✑ Measurable project objectives Which of the following components should be a part of the project management plan instead of the project charter?

AProject title and description
BPreassigned resources
CBudget
DWBS
EMeasurable project objectives
Question #245Part 5

Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?

AEmail and instant messaging to project team members and the project team members and the project sponsor
BText messages to and voice conferences with all stakeholders and project team members
CVideo conferences with key stakeholders and the project champion
DInstant messaging to the project coordinator and project scheduler
Question #246Part 5

A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:

Achange management
BA milestone
Ca tollgate
Dan incident response
Question #247Part 5

A new corporate policy was approved that will positively affect the project. Which of the following should the project manager do FIRST?

ASchedule the change
BReview the communication plan
CUpdate the issue log
DUpdate the risk register
Question #248Part 5

Given the following sprint: Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?

AGantt chart
BPareto chart
CScatter chart
DBurndown chart
Question #249Part 5

Based on the table below: Which of the following is the critical path if Task B has extended to ten days?

A21 days
B23 days
C24 days
D26 days
Question #250Part 5

Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?

ARFP
BRFQ
CRFI
DSOW
Question #251Part 5

A diagram or chart is required to illustrate data differences given the following: 1. The diagram or chart must track at least two variables to determine the relationship between independent variables and include a regression or trend line. 2. The diagram or chart should include cause and effect analysis and investigate historical information. Which of the following should be used given these requirements?

APareto Chart
BIshikawa Diagram
CHistogram
DProbability distribution
ERun chart
Question #252Part 5Select 2

Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members. Which of the following steps should the PM take to make the meetings more productive? (Choose two.)

AFacilitate the meetings by adhering to the agenda.
BEncourage interaction among team members during the meetings.
CEnsure meetings minutes are accurately recorded.
DAdjust the number of meetings.
EChange the number of action items.
Question #253Part 5

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a project?

ARepetitive
BOngoing
CIterative
DTemporary
Question #254Part 5

Given the information in the table below, which of the following is the total project cost?

A$40,000
B$70,000
C$95,000
D$120,000
Question #255Part 5

The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutually agreed-upon deliverables. Which of the following conflict resolution techniques did the teams use?

ACompromising
BSmoothing
CConfronting
DForcing
Question #256Part 5

One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines. Which of the following roles has the responsibility of resolving the issue?

ACCB
BPMO
CProject sponsor
DProject scheduler
Question #257Part 5

During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?

AThe quality of the deliverable decreased due to the rising material cost.
BThe PM did not follow the project communication plan.
CQuality assurance actions were not adjusted for the vendor change.
DThe change was not documented and approved.
Question #258Part 5

A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue. Which of the following documents should the project manager consult?

AIssue log
BRACI chart
CRisk management plan
DOrganizational chart
Question #259Part 5

The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the project manager should take?

AUpdate the documentation.
BImplement the change.
CClose the project.
DEvaluate the impact.
Question #260Part 5

A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)

ABusiness continuity response
BResource changes
CDisaster recovery response
DRisk response
EGate review
Question #261Part 5

A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer (CEO) directs that all meetings be conducted via video conference to save costs and expedite communication. This scenario is an example of:

Aoutsourcing.
Bcorporate acquisition.
Cinternal reorganization.
Dprocess change.
Erelocation.
Question #262Part 5

A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?

ACrash the schedule.
BNotify the project team.
CInitiate a change request.
DAccept the risk.
Question #263Part 5

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

ARisk identification
BGate review
CResource allocation
DResource leveling
Question #264Part 5

During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:

Arisk identification
Brisk prioritization
Crisk qualification
Drisk quantification
Question #265Part 5

A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?

ANorming
BPerforming
CForming
DStorming
Question #266Part 5

Which of the following job roles is MOST responsible for providing input on the project requirements, steering the project, providing expertise, and having vested interest in the project?

AProject scheduler
BProject stakeholder
CProject team
DProject coordinator
Question #267Part 5

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

AAnalyze the critical path and update the WBS with the new feature
BAdd the new feature and reprioritize the product backlog
CAdd the new feature to the next sprint and move the old feature to the following sprint
DConduct a retrospective with the team to discuss the change and introduce the feature
Question #268Part 5

A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?

AFunctional
BProjectized
CStrong matrix
DFlat
Question #269Part 5

The following tasks are required to complete an IT project that is behind schedule: Which of the following is the critical path?

A3, 2, 4
B4, 2, 3
C3, 2, 1, 4
D4, 1, 2, 3
Question #270Part 5

A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm. The PMO declines to assign a project manager and refers to another department within the company. Which of the following is MOST likely the reason for this?

AThere are not enough project managers available for additional work
BThe work does not align with the strategic objectives of the organization
CThis is ongoing work the vendor has been hired to perform
DThe third party has a reputation for expertise in this area
Question #271Part 5

Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)

ASteer the project
BProvide governance
CJustify the business case
DProcure hardware
EIdentify key performance indicators
Question #272Part 5

Which of the following is the MOST important component against which the project manager can analyze project performance?

ABurn rate
BProject baselines
CKPIs
DBudget
Question #273Part 5

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?

ARequirements
BLessons learned
CBudget
DEnvironment
Question #274Part 5

While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints. Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?

ASend the stakeholders a survey about the project constraints to complete anonymously
BWatch and determine which constraint is most important
CCompare the constraints two at a time and have the stakeholders vote on importance
DLook at historical information regarding the flexibility preferences of key stakeholders
Question #275Part 5

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?

AStakeholders
BScrum master
CProject sponsor
DProject team
Question #276Part 5

A team member has reported Task 3 will be completed ahead of schedule. Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

A8 days
B10 days
C11 days
D12 days
Question #277Part 5

A PM is asked to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information?

AStatus report
BMeeting minutes
CDashboard
DEmail
Question #278Part 5

Which of the following should be included in an effective SOW?

ALessons learned
BProcurement process
CCorrective action plan
DProject objectives
Question #279Part 5

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

AUpdate the project charter to include the functional manager as a key stakeholder
BPublish the project schedule to the functional manager
CReview the communications plan to ensure proper involvement
DAdd the incident to the issue log and seek resolution
EEnsure the functional manager is on the status report distribution list
Question #280Part 5

The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?

AWiki page
BIntranet
CExtranet
DInternet
EKnowledge base
Question #281Part 5Select 2

Which of the following documents are considered mutually binding? (Choose two.)

ANDA
BPO
CRFP
DWBS
EKPI
Question #282Part 5

According to the communication management plan, the project scheduler is required to post weekly status reports on the project's intranet site. From the stakeholders' point of view, accessing the weekly report is an example of:

Ainterorganizational preferences
Bpersonal preferences
Cthe interactive method
Dthe pull method
Question #283Part 5

The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?

AExecution to monitor and control
BInitiation to planning
CInitiation to monitor and control
DPlanning to execution
Question #284Part 5

During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

AIncident response
BProject plan
CRisk register
DBusiness continuity plan
Question #285Part 5

A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?

AIdentifying the risk
BObtaining approval from the CCB
CEvaluating the impact of the risk
DCommunicating to stakeholders
Question #286Part 5

Which of the following should a project manager consider as part of a make or buy analysis?

AOrganization type
BKPIs
CProject charter
DTrade secrets
Question #287Part 5

A project manager is assigned a project that is part of the company's strategic objectives. Of which of the following is the project a part?

AProject management office
BPortfolio
CProgram
DMission statement
Question #288Part 5

In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:

Aa dedicated resource pool
Ban allocated resource pool
Ca shared resource pool
Da benched resource pool
Question #289Part 5

A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:

Abusiness change response
Bchange management response
Cbusiness continuity response
Drisk management response
Question #290Part 5

A PM has a complex project that requires coordination among numerous stakeholders. Which of the following is the MOST appropriate type of meeting for the stakeholders to hold?

AVirtual
BImpromptu
COne-on-one
DIn-person
Question #291Part 5Select 2

The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)

AScope creep
BDeliverables
CBusiness requirements
DProject schedule
EGate review

📢 Unlock Full Access to Success!

"The content displayed here is a promotional preview and contains only 50% of the actual exam database. To access the complete set of updated questions, please upgrade to the Full Version."

👉 Click the button and follow the instructions to secure your full access immediately!