PRINCE2 Agile Foundation
Practice questions for the PRINCE2 Agile Foundation certification exam.
4.6★★★★★(208 ratings)
17,480 studentsIntermediate- •Familiarity with basic IT concepts
- •Access to relevant platform tools for hands-on practice
- •Interest in pursuing PRINCE2-AGILE-FOUNDATION certification
- •Engineers and architects pursuing professional certification
- •Developers looking to validate their skills
- •IT professionals transitioning to specialized roles
- •Students preparing for certification exams
This course covers everything you need to pass the PRINCE2 Agile Foundation (PRINCE2-AGILE-FOUNDATION) exam. Each part of this course contains real exam questions taken from the actual exam pool, with hint answers to guide your study. Practice with these questions to build confidence and master the topics needed for certification success.
What you'll learn
- Master the core concepts for PRINCE2-AGILE-FOUNDATION certification
- Practice with real exam-style questions
- Understand platform services and architectures covered in PRINCE2-AGILE-FOUNDATION
- Build confidence through timed practice exams
- Learn from detailed hint answers and explanations
- Pass the official PRINCE2-AGILE-FOUNDATION certification exam on your first try
PRINCE2-AGILE-FOUNDATION
Lectures3
Questions174
Duration30 week
Students17,480
$20.00
Full Free Question Bank (174 Questions)
PRINCE2 Agile Foundation (PRINCE2-AGILE-FOUNDATION) Practice Questions & Verified Answers
Click any option to test your knowledge, or reveal the verified answer and detailed explanation below each question.
Jump to Section:
Question #1Part 1
ABusiness Case
BProject Plan
CCommunication Management Strategy
DProject Product Description
✓ Verified Answer: A
Question #2Part 1
What is the definition of a project outcome?
AA measurable improvement that is perceived as an advantage by one or more stakeholders
BThe reason for the project
CThe result of the change derived from using the project's outputs
DThe project's specialist products.
✓ Verified Answer: C
Question #3Part 1
Which is NOT a purpose of a Benefits Review Plan?
ADefine the period over which the cost-benefit analysis will be based
BDescribe how to measure the performance of the project's products in operational use
CDefine the scope, timing and ownership of the benefit reviews required
DDescribe how to measure and confirm any benefits that are to be realised after the project is
✓ Verified Answer: A
Question #4Part 1
Which product documents the information needed to demonstrate continued business justification?
ABusiness Case
BCommunication Management Strategy
CProject Product Description
DQuality Management Strategy
✓ Verified Answer: A
Question #5Part 1
Which is NOT a purpose of a Benefits Review Plan?
ADefine the period over which the cost-benefit analysis will be based
BDescribe how to measure the performance of the project's products in operational use
CDefine the scope, timing and ownership of the benefit reviews required
DDescribe how to measure and confirm any benefits that are to be realised after the project is
✓ Verified Answer: A
Question #6Part 1
What is an off-specification?
AA new requirement
BA quality tolerance
CA type of issue
DA major risk
✓ Verified Answer: C
Question #7Part 1
Which is a type of issue?
AA lesson
BA request for change
CAn Exception Report
DA risk with an estimated high impact
✓ Verified Answer: B
Question #8Part 1
Which is a typical core activity within configuration management?
AQuality assurance
BRisk management
CVerification and audit
DProgress reporting
✓ Verified Answer: B
Question #9Part 1
Which is a typical core activity within configuration management?
AIssue management
BQuality inspection
CIdentification
DPreparation
✓ Verified Answer: C
Question #10Part 1
What needs to be in place to ensure effective issue and change control?
AConfiguration management system
BManage by exception
CQuality planning
DInformation needs for stakeholders
✓ Verified Answer: A
Question #11Part 1
Which should be funded by a change budget?
AIncrease in agreed scope
BInitiation stage
CChange Authority
DHandover activities
✓ Verified Answer: A
Question #12Part 1
Which should be funded from a change budget?
AThe Starting up a Project process
BA fallback plan
CAn agreed change to the scope of a project
DA change to a plan, within allocated tolerances, due to poor estimating
✓ Verified Answer: C
Question #13Part 1
Which is the Issue Register NOT used for?
ACapture external events that are impacting a stage
BRecord information about a deviation in stage tolerance
CCapture any threats or opportunities that might have an impact on a stage
DRecord any problems identified when authorizing a Work Package
✓ Verified Answer: C
Question #14Part 1
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
ACheckpoint Report
BHighlight Report
CIssue Report
DProduct Status Account
✓ Verified Answer: C
Question #15Part 1
Which is the purpose of the Change theme?
ATo prevent change to baselined products
BTo identify, assess and control any potential and approved changes to baselined products
CTo establish mechanisms to monitor and compare actual achievements against those
DTo assess and control uncertainty
✓ Verified Answer: B
Question #16Part 1
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
ACapture
BExamine
CPropose
DDecide
✓ Verified Answer: B
Question #17Part 1
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
ARaise a request for change
BRaise an off-specification
CWrite an Exception Report
DAmend the Work Package
✓ Verified Answer: B
Question #18Part 1
Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage. 2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
AOnly 1 is true
BOnly 2 is true
CBoth 1 and 2 are true
DNeither 1 or 2 are true
✓ Verified Answer: C
Question #19Part 1
What takes place during the Closing a Project process?
AThe post-project benefits reviews are performed
BOwnership of the project's products is transferred to the customer
CAn End Stage Report is prepared for the final stage
DThe project closure notification is reviewed and approved
✓ Verified Answer: A
Question #20Part 1
Which is an objective of the Closing a Project process?
APrepare the plan for the next stage
BAssess any benefits that have already been realized
CProduce a Benefits Review Plan to identify what benefits are expected
DCheck that all benefits are realized before closing a project
✓ Verified Answer: B
Question #21Part 1
Which is a purpose of the Closing a Project process?
AAuthorize the final stage of the project
BConfirm that all benefits defined in the Business Case have been achieved
CRecognize whether objectives set out in the original Project Initiation Documentation have
DDelegate day-to-day management of the end of the project to the Project Manager
✓ Verified Answer: B
Question #22Part 1
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
AOff-specifications
BFollow-on action recommendations
CIssue Register
DRisk Register
✓ Verified Answer: B
Question #23Part 1
Which is an objective of the 'closing a project' process?
ATo provide corporate management with an interface to the project
BTo ensure the project's delivery will be within set tolerances
CTo seek approval to replace the project or stage plan
DTo assess the benefits that have already been realized
✓ Verified Answer: D
Question #24Part 1
Which is a purpose of the Controlling a Stage process?
AProduce a Team Plan for the work to be assigned to a Team Manager
BSelect and implement actions that will resolve deviations from a plan within tolerance
CObtain approvals for products delivered in a Work Package
DUpdate a Project Plan to incorporate the actuals from a Stage Plan
✓ Verified Answer: B
Question #25Part 1
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
ADirecting a Project
BManaging a Stage Boundary
CControlling a Stage
DStarting up a Project
✓ Verified Answer: B
Question #26Part 1
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
AManaging a Stage Boundary
BManaging Product Delivery
CClosing a Project
DControlling a Stage
✓ Verified Answer: C
Question #27Part 1
Which is a purpose of the Controlling a Stage process?
AAssign work to be done and take corrective action to ensure that the stage remains within
BProvide a fixed reference point at which acceptance for the project product is confirmed
CEnable the Project Board to be provided with sufficient information to authorize the next stage
DEnable the organization to understand the work that needs to be done to deliver the project's
✓ Verified Answer: A
Question #28Part 1
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
ADirecting a Project
BControlling a Stage
CManaging a Stage Boundary
DManaging Product Delivery
✓ Verified Answer: B
Question #29Part 1
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
AProduct Description
BTeam Plan
CWork Package
DStage Plan
✓ Verified Answer: C
Question #30Part 1
Which is a purpose of the 'directing a project' process?
ATo answer the question: Do we have a viable and worthwhile project?
BTo coordinate an area of work delivering the project product's components
CTo delegate day to day management of the project to the project manager
DTo provide a fixed point to confirm acceptance of the project product
✓ Verified Answer: D
Question #31Part 1
Which is an objective of the Directing a Project process?
ACreate and authorize the project mandate
BProvide management control and direction
CControl the day-to-day running of the project
DProvide accurate progress information to the Project Manager
✓ Verified Answer: B
Question #32Part 1
In what process is the authorization to deliver the project's products given?
AStarting up a Project
BInitiating a Project
CManaging a Stage Boundary
DDirecting a Project
✓ Verified Answer: D
Question #33Part 1
Who should act as the communication channel between a project and corporate or programme management?
AProject Board
BProject Assurance
CProject Manager
DProject Support
✓ Verified Answer: A
Question #34Part 1
Which statement about the Directing a Project process is true?
AProvides a mechanism for the Project Board to assure that there is continued business
BCovers the day-to-day activities of the Project Manager
CEnsures there are regular progress meetings
DBegins on completion of the Initiating a Project process
✓ Verified Answer: A
Question #35Part 1
Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project. 2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
AOnly 1 is true
BOnly 2 is true
CBoth 1 and 2 are true
DNeither 1 or 2 are true
✓ Verified Answer: B
Question #36Part 1
Which is NOT a purpose of the Initiating a Project process?
AEnable a Project Board decision about the commitment of resources to a project
BEnable an organization to understand the work that needs to be done to deliver a project's
CEstablish solid foundations for a project
DEnable the Project Board to decide whether it is worthwhile to initiate a project
✓ Verified Answer: D
Question #37Part 1
Which plan provides the Business Case with costs during the Initiating a Project process?
AInitiation Stage Plan
BProject Plan
CStage Plan
DTeam Plan
✓ Verified Answer: B
Question #38Part 1
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
AProject Brief
BProject Initiation Documentation
CProject mandate
DBenefits Review Plan
✓ Verified Answer: C
Question #39Part 1
Which is a purpose of the Initiating a Project process?
ADecide if it is worthwhile to initiate a project
BDecide on the project approach
CEstablish solid foundations for a project
DIdentify the number of Work Packages required
✓ Verified Answer: C
Question #40Part 1
Which is a purpose of the Managing Product Delivery process?
AEnable the Senior Supplier to be provided with sufficient information by the Project Manager
BProvide a controlled link between the Project Manager and the Team Manager(s)
CEnable the Project Board to request updates to the current Team Plan
DEstablish solid foundations for the project
✓ Verified Answer: B
Question #41Part 1
From whom does a Team Manager obtain approval for a completed product?
AProject Manager
BProject Support
CThe authority defined in the Product Description
DSenior Supplier
✓ Verified Answer: C
Question #42Part 1
Which is an objective of the 'managing product delivery' process?
ATo authorize the work package allocated to the team
BTo raise exception reports when tolerance is exceeded
CTo ensure that delivered products match expectations
DTo record any lessons to help later management stages
✓ Verified Answer: C
Question #43Part 1
What process aims to ensure accurate progress information is provided to the Project Manager?
AStarting up a Project
BManaging a Stage Boundary
CManaging Product Delivery
DDirecting a Project
✓ Verified Answer: B
Question #44Part 1
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
AClosing a Project
BManaging a Stage Boundary
CManaging Product Delivery
DDirecting a Project
✓ Verified Answer: C
Question #45Part 1
Which two roles are linked by the Managing Product Delivery process?
ACorporate or programme management and Project Board
BProject Board and Project Manager
CProject Manager and Team Manager
DTeam Manager and external supplier
✓ Verified Answer: A
Question #46Part 1
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
ACreate a separate Project Board to manage the supplier elements of the project
BCreate multiple smaller Project Boards during the process of Starting up a Project, one for
CCreate user and supplier groups
DAppoint corporate quality assurance to perform the Project Assurance role for all members of
✓ Verified Answer: C
Question #47Part 1
When should the Project Board refer to corporate or programme management for a decision?
AThe stage requires resources
BIt is forecast that project level tolerance will be exceeded
CThe Senior Supplier or Senior User needs to be changed
DAny request for change needs to be approved
✓ Verified Answer: B
Question #48Part 1
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
AStage Plan
BCommunication Management Strategy
CFollow-on action recommendations
DQuality Management Strategy
✓ Verified Answer: B
Question #49Part 1
Which is NOT a purpose of the Organization theme?
ADefine a project management team structure
BDefine the level of tolerance for each level of the project management team
CDefine the Project Board's responsibility for directing the project
DDefine which role is accountable for the project's success
✓ Verified Answer: B
Question #50Part 1
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
AThose with a financial interest in the project
BThose who will manage the project on a day-to-day basis
CThose who will specify the desired outputs of the project
DThose who will create the project's outputs
✓ Verified Answer: B
Question #51Part 1
Which does the Executive need to ensure is in place before the project is initiated?
AAll Work Packages are authorized
BAn understanding of how the project will contribute to corporate objectives
CThe Project Plan has been approved
DThe Project Initiation Documentation is complete
✓ Verified Answer: B
Question #52Part 1
What product is used to maintain a record of those who have an interest in the project and their information requirements?
AProject Plan
BCommunication Management Strategy
CProject Brief
DProject Product Description
✓ Verified Answer: B
Question #53Part 1
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
Aquality
Bsupplier
Crisk
Dproduct
✓ Verified Answer: B
Question #54Part 1
How many roles make up the Project Board?
AOne
BTwo
CThree
DFour
✓ Verified Answer: D
Question #55Part 1
Which of the following statements about stakeholders are true? 1. Someone who thinks they will be affected by a project is a stakeholder on that project. 2. Stakeholders may be internal or external to the corporate organization.
AOnly 1 is true
BOnly 2 is true
CBoth 1 and 2 are true
DNeither 1 or 2 are true
✓ Verified Answer: D
Question #56Part 1
Which is one of the six aspects of project performance that needs to be managed?
AProgress
BChange
CRisk
DSecurity
✓ Verified Answer: C
Question #57Part 1
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
ABenefits
BQuality
CRisk
DScope
✓ Verified Answer: D
Question #58Part 1
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
Aa corporate
Ba temporary
Can external
Da technical
✓ Verified Answer: D
Question #59Part 1
Which is NOT one of the PRINCE2 integrated elements?
ATailoring PRINCE2 to the project environment
BThe processes
CThe products
DThe themes
✓ Verified Answer: C
Question #60Part 1
Which is a benefit of using PRINCE2?
AIs a method specifically designed for technical projects
BProvides for the efficient and economic use of management time
CIncludes many of the proven planning techniques, such as critical path analysis
DCan be used to manage both projects and programmes
✓ Verified Answer: B
Question #61Part 2
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
ASpecify the desired result
BProvide the resources and skills to deliver the desired result
CPay for the project
DSpecify the benefits of the project
✓ Verified Answer: B
Question #62Part 2
Which does NOT reflect the PRINCE2 principle of continued business justification?
AThere must be a justifiable reason for starting a project
BThe business justification drives decision making
CIf a project is no longer forecast to deliver a financial benefit, it should be stopped.
DIf a project can no longer be justified, it should be stopped
✓ Verified Answer: B
Question #63Part 2
Which characteristic distinguishes a project from regular business operations?
AProduces benefits
BIntroduces business change
CManages stakeholders
DIncurs cost
✓ Verified Answer: B
Question #64Part 2
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
AChange
BCross-functional
CUnique
DRisk
✓ Verified Answer: B
Question #65Part 2
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
AManage by stages
BManage by exception
CContinued business justification
DLearn from experience
✓ Verified Answer: B
Question #66Part 2
Which role is responsible for creating Checkpoint Reports?
ASenior Supplier
BTeam Manager
CChange Authority
DProject Support
✓ Verified Answer: B
Question #67Part 2
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Aproject cost tolerance
Bstage cost tolerance
CWork Package cost tolerance
Dproduct cost tolerance
✓ Verified Answer: C
Question #68Part 2
Which is a true statement about time-driven controls?
ATime-driven controls are used for monitoring the progress of Work Packages and
BTime-driven controls take place when specific events happen
CTime-driven controls are produced at the end of a stage
DAn Exception Report is a time-driven control
✓ Verified Answer: A
Question #69Part 2
Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board. 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
AOnly 1 is true
BOnly 2 is true
CBoth 1 and 2 are true
DNeither 1 or 2 are true
✓ Verified Answer: C
Question #70Part 2
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
AProgress
BChange
COrganization
DQuality
✓ Verified Answer: A
Question #71Part 2
Which is a FALSE statement about technical stages?
ACan overlap with other technical stages
BTypified by the use a particular set of specialist skills
CInclude the Managing a Stage Boundary process activities
DCan span more than one management stage
✓ Verified Answer: B
Question #72Part 2
How should the Team Manager report that tolerances are forecast to be exceeded?
ACreate an Exception Report
BCreate a Highlight Report
CRaise an issue
DGrant a concession
✓ Verified Answer: A
Question #73Part 2
Which statement about stages is true?
AManagement stages should be of the same duration
BThe use of technical stages is mandatory
CThe use of management stages is mandatory
DManagement stages are driven by specialist teams
✓ Verified Answer: A
Question #74Part 2
What product defines the reporting requirements between the Project Manager and Team Manager?
AProject Brief
BProduct Description
CTeam Plan
DWork Package
✓ Verified Answer: D
Question #75Part 2
Whose approval is needed to replace a Stage Plan with an Exception Plan?
ACorporate or programme management
BProject Board
CProject Manager
DTeam Manager
✓ Verified Answer: B
Question #76Part 2
Which is a difference between management and technical stages?
AManagement stages require planning and technical stages do not
BTechnical stages can overlap and management stages cannot
CManagement stages deliver products and technical stages do not
DTechnical stages require resources and management stages do not
✓ Verified Answer: B
Question #77Part 2
Which is a purpose of a Lessons Log?
ANote any lessons that are raised in Checkpoint Reports
BRecord that corrective action is being taken
CEscalate lessons to the Project Board
DRaise improvements with Project Assurance
✓ Verified Answer: C
Question #78Part 2
Which is a true statement about PRINCE2 event-driven controls?
AEvent-driven controls take place at predefined periodic intervals
BEvent-driven controls are produced at the frequency defined in a Work Package
CEvent-driven controls are used for decision making
DCheckpoint Reports are event-driven controls
✓ Verified Answer: C
Question #79Part 2
Which is a purpose of an End Project Report?
AIdentify individuals or groups that need to be told that the project is coming to an end
BReview how well the project performed against the Project Initiation Documentation used to
CIdentify individuals or groups that are responsible for measuring the expected benefits after
DEnsure that key project information is archived and made secure
✓ Verified Answer: B
Question #80Part 2
How many management stages should a PRINCE2 project consist of?
AStart up stage, initiation stage and at least one other management stage to cover the
BStart up stage, at least one other management stage to cover the remainder of the project
CInitiation stage and at least one other management stage to cover the remainder of the
DStart up stage, initiation stage and a closing stage
✓ Verified Answer: A
Question #81Part 2
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
AConfiguration Item Record
BQuality Register
CHighlight Report
DCheckpoint Report
✓ Verified Answer: D
Question #82Part 2
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
AOnly corporate or programme management
BOnly the Project Board
COnly the Project Manager
DAll levels of management
✓ Verified Answer: D
Question #83Part 2
Which is one of the three levels of plan in PRINCE2?
ABenefits Review Plan
BProgramme Plan
CTeam Plan
DProject Brief
✓ Verified Answer: C
Question #84Part 2
Which theme estimates the cost of delivering the project?
ABusiness Case
BChange
CPlans
DProgress
✓ Verified Answer: C
Question #85Part 2
Which is a task of product-based planning?
AIdentify activities and dependencies
BWrite the Project Product Description
CPrepare the Work Packages
DProduce Product Status Accounts
✓ Verified Answer: B
Question #86Part 2
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
AManagement strategies
BPlan
CStakeholder interests
DTime-driven controls
✓ Verified Answer: B
Question #87Part 2
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
Adefine a coding system to provide a unique identifier for the products within
Bsummarize the results of the quality activities performed on
Cprovide a framework to design, develop and maintain
Ddefine the project benefits to be achieved by each of
✓ Verified Answer: C
Question #88Part 2
What is the first task of product-based planning?
AProduce the Initiation Stage Plan
BWrite the Project Product Description
CIdentify dependencies
DCreate the product breakdown structure
✓ Verified Answer: C
Question #89Part 2
How many tasks does the product-based planning technique describe?
AOne
BTwo
CThree
DFour
✓ Verified Answer: A
Question #90Part 2
What is shown in a product breakdown structure?
AManagement stages, major products and control points
BIn which order the products should be created
CThe major products that are to be developed in a plan
DThe resources that are required to develop the products
✓ Verified Answer: C
Question #91Part 2
Which statement applies to Stage Plans?
AAlways have the same duration as the Project Plan
BAre produced at the same time as the Project Initiation Documentation
CAssist the Project Manager in the day-to-day running and control of the project
DProvide a baseline against which the Project Board monitor overall progress
✓ Verified Answer: C
Question #92Part 2
Which is a recommended quality review team role?
AProject Manager
BAssurance
CProject Support
DAdministrator
✓ Verified Answer: D
Question #93Part 2
Which is a recommended quality review team role?
AProject Manager
BAssurance
CChair
DProducer
✓ Verified Answer: D
Question #94Part 2
Which is a purpose of a Project Product Description?
ARecords the costs and timescales for delivery of the project's final product
BShows the dependencies between the project's products to aid planning
CProvides a list of all the products to be delivered by the project
DDefines what the project must deliver in order to gain acceptance
✓ Verified Answer: C
Question #95Part 2
Which of the following statements about quality assurance and Project Assurance is true?
AProject Assurance is the responsibility of the corporate organization; quality assurance is the
BProject Assurance is independent of the Project; quality assurance is only independent of the
CProject Assurance may be delegated within a project; quality assurance must be undertaken
DProject Assurance ensures compliance to standards within the project environment; quality
✓ Verified Answer: C
Question #96Part 2
Who carries out audits that are independent of the project?
AQuality assurance
BProject Assurance
CProject Support
DProject Manager
✓ Verified Answer: D
Question #97Part 2
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
Aa solution should be designed for
Ban issue should be created for
Cthe agreed actions should be recorded for
Dthe chair will approve the solution to
✓ Verified Answer: A
Question #98Part 2
Which statement about the quality review technique is FALSE?
AIt enables a check to be made on a product's fitness for purpose
BIt defines the quality responsibilities of the project team
CIt supports the management of future changes by providing a baseline for a product
DIt is used to gain wider acceptance of a product by involving key interested parties
✓ Verified Answer: B
Question #99Part 2
Which is part of quality control?
AUndertake quality reviews
BWrite Product Descriptions
CProvide assurance that the project is being conducted properly
DDocument the customer's quality expectations
✓ Verified Answer: A
Question #100Part 2
Which is part of quality control?
ADocument the project's acceptance criteria in the Project Product Description
BDefine the quality responsibilities of those involved in the production of the products
CProduce quality records to show that the planned quality activities have been carried out
DMaintain the corporate organization's quality management system
✓ Verified Answer: C
Question #101Part 2
Which of the following statements about customer's quality expectations and acceptance criteria are true? 1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders. 2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
AOnly 1 is true
BOnly 2 is true
CBoth 1 and 2 are true
DNeither 1 or 2 are true
✓ Verified Answer: D
Question #102Part 2
Why is it crucial that the Project Product Description clearly defines acceptance methods?
AEnables Project Assurance to authorize quality activities
BDefines how all project products will be reviewed and approved
CDefines how it will be proven that the completed project product meets the customer's
DProvides confirmation that all project products have met their quality criteria
✓ Verified Answer: D
Question #103Part 2
Which is a purpose of the Quality theme?
AEstablish how the project will ensure that all products created meet their requirements
BEstablish quality assurance to maintain the quality management system
CIdentify all the products of the project to ensure the scope has been adequately defined
DDetermine the communication needs of the organization's quality assurance function
✓ Verified Answer: A
Question #104Part 2
Which statement defines a risk?
AA certain event occurring in the future that will have a negative impact on the project's
BAn event that has already occurred that the Project Manager must deal with immediately
CAn uncertain event, or set of events that, should it or they occur, will have an effect on the
DAn uncertain event, or set of events that, should it or they occur, will be automatically
✓ Verified Answer: A
Question #105Part 2
Which risk response type is appropriate to respond to an opportunity?
AAccept
BFallback
CExploit
DTransfer
✓ Verified Answer: C
Question #106Part 2
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
AAvoid
BReduce
CShare
DTransfer
✓ Verified Answer: C
Question #107Part 2
Which is NOT considered when defining risk tolerance?
AA Project Board's attitude towards risk taking
BThe allocated risk budget
CAn organization's risk appetite
DThe amount of risk a Project Board considers acceptable
✓ Verified Answer: C
Question #108Part 2
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
AProject Assurance
BProject Support
Cthe risk actionee
Dthe risk owner
✓ Verified Answer: C
Question #109Part 2
Which is a purpose of the Risk theme?
AEstablish a method for the implementation of continuous improvement during the project
BIdentify, assess and control problems that have occurred
CProvide the Project Board with a time-driven control to capture all project risks
DEstablish a cost-effective procedure to identify, assess and control risks
✓ Verified Answer: D
Question #110Part 2
Which document should record the agreed amount of risk budget for a project?
AProject Brief
BProject Plan
CRisk Management Strategy
DRisk Register
✓ Verified Answer: B
Question #111Part 2
Which statement describes the 'Implement' step within the recommended risk management procedure?
ATake planned action to respond to a risk
BImplement the responsibilities for risks defined in the Risk Management Strategy
CAssess the proximity of a risk
DIdentify the level of risks that can be tolerated by the project
✓ Verified Answer: C
Question #112Part 2
Which is a purpose of the Risk theme?
AEstablish a procedure to ensure every change is agreed by the relevant authority before it
BEstablish a cost-effective procedure to identify, assess and control uncertainty
CEstablish mechanisms to control any unacceptable deviations from plan
DEstablish mechanisms to manage risks at the corporate or programme level of an
✓ Verified Answer: A
Question #113Part 2
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
Achange budget
Bproject budget
Cproject's cost tolerance
Dproject's risk tolerance
✓ Verified Answer: B
Question #114Part 2
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
ARisk category
BRisk description
CRisk response
DRisk status
✓ Verified Answer: B
Question #115Part 2
Which describes a risk effect?
AThe uncertainty expressed as a negative or favourable occurrence
BThe issue which is affecting the project and has resulted in a risk
CThe impact(s) on the project objectives should the threat or opportunity occur
DThe change in the status of a risk in response to actions taken to control it
✓ Verified Answer: D
Question #116Part 2
Which describes risk probability?
ALevel of risks which the project can tolerate before escalating to the Project Board
BProbable effect on the project delivering its objectives
CTimeframe within which the risk may occur
DA measure of the likelihood of the risk occurring
✓ Verified Answer: A
Question #117Part 2
Which is a purpose of a Risk Register?
ACapture risks that may occur during the project
BRecord how risk management activities will be undertaken on the project
CRecord the risk tolerance for the project
DCapture issues which are impacting on the delivery of the project objectives
✓ Verified Answer: C
Question #118Part 2
Which role is responsible for ensuring the project is justified in terms of cost?
AProject manager
BExecutive
CSenior user
DSenior supplier
✓ Verified Answer: B
Question #119Part 2
What is described as an organization's unique attitude towards risk taking
ARisk appetite
BRisk management
CRisk evaluation
DRisk tolerance
✓ Verified Answer: B
Question #120Part 2
Which is a purpose of the Risk Register?
ADescribe the risk management techniques and standards to be applied to the project
BAct as a central record of information relating to the identified risks for the project
CAct as a repository for informal issues
DList the responsibilities for achieving an effective risk management procedure
✓ Verified Answer: D
Question #121Part 3
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
AControlling a Stage
BClosing a Project
CDirecting a Project
DManaging a Stage Boundary
✓ Verified Answer: D
Question #122Part 3
Which is a purpose of the Managing a Stage Boundary process?
AProvide the Project Board with sufficient information for approving the next stage
BApprove the next Stage Plan
CReview and close any risks and issues identified during the previous stage
DControl the link between the Project Manager and the Team Manager(s)
✓ Verified Answer: A
Question #123Part 3
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
AEnd Stage Report
BTeam Plan
CWork Package
DProject Plan
✓ Verified Answer: C
Question #124Part 3
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
ATeam Plan
BStage Plan
CBenefits Review Plan
DProject Plan
✓ Verified Answer: D
Question #125Part 3
Which activity takes place within the Managing a Stage Boundary process?
AProduce Highlight Reports
BTake corrective action within the limits of a stage's tolerance
CProduce an Exception Plan
DAuthorize a Stage Plan for the next stage
✓ Verified Answer: C
Question #126Part 3
Which is a purpose of a Project Brief?
AEnable the assembly of the project mandate
BDescribe the reporting requirements of the various layers of management involved with the
CDescribe how changes to products will be controlled
DProvide a solid basis for the initiation of the project
✓ Verified Answer: B
Question #127Part 3
Which is an objective of the Starting up a Project process?
AIdentify who will be responsible for creating the Project Plan
BAgree how the project will be monitored and controlled after initiation
CAuthorize the Project Manager to proceed with the initiation stage
DAgree how issues and changes will be identified, assessed and controlled
✓ Verified Answer: A
Question #128Part 3
Which is created during the Starting up a Project process?
AProject mandate
BProject management team role descriptions
CCommunication Management Strategy
DQuality Register
✓ Verified Answer: B
Question #129Part 3
Which should be provided by corporate or programme management before the Starting up a Project process commences?
AA Project Brief
BSufficient information to identify the prospective Executive
CThe Project Initiation Documentation
DAuthority to initiate a project
✓ Verified Answer: D
Question #130Part 3
How is the tailoring approach defined for a project?
AThe project board approves the approach
BThe project board documents the approach
CProject assurance approves the approach
DProject assurance documents the approach
✓ Verified Answer: A
Question #131Part 3
Which is a purpose of the change theme?
ATo prevent change to baselined products
BTo identify, assess and control any potential and approved changes to baselined products
CTo establish mechanisms to monitor and compare actual achievements against those
DTo assess and control uncertainty
✓ Verified Answer: D
Question #132Part 3
Why is a project brief produced?
ATo act as a trigger for the 'starting up a project' process
BTo record the how the project will communicate with its stakeholders
CTo provide a full and firm foundation for the initiation of a project
DTo be used by the project board as a basis for reviewing the progress of a project
✓ Verified Answer: A
Question #133Part 3
Which is a key decision made during the 'directing a project' process?
ASelect and appoint the project executive
BApprove the project manager role description
CConfirm that the benefits management approach addresses all expected benefits
DApprove the proposed project mandate
✓ Verified Answer: C
Question #134Part 3
What action is taken as part of the 'controlling a stage' process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products
A1 and 2
B2 and 3
C3 and 4
D1 and 4
✓ Verified Answer: B
Question #135Part 3
Why can PRINCE2 be applied to any type of project?
ABecause it provides the project manager with procedures for managing project risks and
BBecause it allows each member of the project management team to fully understand their
CBecause it separates the management of the project from the specialist work needed to
DBecause it provides the project manager with a planning procedure to plan the project more
✓ Verified Answer: C
Question #136Part 3
Which is a purpose of a quality register?
ATo record the quality management approach for a product
BTo issue a unique reference number for each product
CTo detail the number and type of quality activities to be conducted
DTo identify corrective actions that are required after an audit by quality assurance
✓ Verified Answer: C
Question #137Part 3
Which describes a characteristic of a project?
AIt maintains business as usual profitability
BIt provides a quality service to customers
CIt involves a team with different skills
DIt enables established and proven best practices
✓ Verified Answer: C
Question #138Part 3
What is the project manager role responsible for?
AApproving the completion of each management stage
BEnsuring that the project produces the required products
CDefining the project-level tolerances
DVerifying that the project gives value for money
✓ Verified Answer: B
Question #139Part 3
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
AProgress
BChange
COrganization
DQuality
✓ Verified Answer: A
Question #140Part 3
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
AProject mandate
BInitiation stage plan
CProject initiation documentation
DProject brief
✓ Verified Answer: A
Question #141Part 3
Which is a minimum requirement for applying the quality theme?
ATo use lessons to inform quality planning
BTo use the prescribed approach to quality management
CTo use external quality standards for quality control
DTo use user stories to inform the project product description
✓ Verified Answer: A
Question #142Part 3
Which process is used to define how baselines will be established and controlled?
AControlling a stage
BDirecting a project
CInitiating a project
DStarting up a project
✓ Verified Answer: C
Question #143Part 3
Which risk response is applied on a pain/gain basis?
AShare
BAccept
CExploit
DEnhance
✓ Verified Answer: A
Question #144Part 3
To meet the minimum requirements for applying the progress theme, what must be considered?
AHow lessons will be learned
BHow time-driven reports will be produced
CWhich management products will be baselined
DWho is responsible for reporting on progress
✓ Verified Answer: A
Question #145Part 3
Which is a purpose of the 'initiating a project' process?
ATo decide if it is worthwhile to initiate a project
BTo decide on the project approach
CTo establish solid foundations for a project
DTo identify the number of work packages required
✓ Verified Answer: A
Question #146Part 3
Which is a step in the recommended approach to 'defining and analyzing the products'?
APreparing estimates
BDesigning a plan
CWriting a project product description
DIdentifying activities and dependencies
✓ Verified Answer: C
Question #147Part 3
How does the use of product descriptions support the 'focus on products' principle?
ABy documenting the scope tolerance for the project
BBy documenting the quality expected by the customer
CBy documenting the costs for the product
DBy documenting the delivery date for the product
✓ Verified Answer: D
Question #148Part 3
Which describes a risk event?
AThe area of uncertainty in terms of the threat or opportunity
BThe derivation or sources of a potential risk to the project
CThe achievement of a milestone on the project plan
DThe sequence of events and actions that will be put in place if a risk occurs
✓ Verified Answer: A
Question #149Part 3
Which is a minimum requirement for applying the plans theme?
AThe project must have at least two management stages
BThe team managers in the project must prepare team plans
CScope tolerance must be prioritized using MoSCoW
DThe project plan must be presented as a Gantt chart
✓ Verified Answer: A
Question #150Part 3
Which is a minimum requirement for applying the quality theme?
ATo define the project's approach to quality assurance
BTo appoint external reviewers for quality reviews
CTo define quality criteria in product descriptions
DTo provide administrative support for quality controls
✓ Verified Answer: C
Question #151Part 3
Which level of management sets the project level tolerances?
AProject board
BTeam manager
CCorporate, programme management or the customer
DProject manager
✓ Verified Answer: C
Question #152Part 3
If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?
AAppointing the project board and producing the project brief
BPlanning the initiation stage and appointing the project manager
CProducing the additional role descriptions and validating the project product description
DVerifying the project approach and capturing previous lessons
✓ Verified Answer: A
Question #153Part 3
Which is part of quality control?
AUndertaking quality reviews
BWriting product descriptions
CProviding assurance that the project is being conducted properly
DDocumenting the customer's quality expectations
✓ Verified Answer: A
Question #154Part 3
According to the 'continued business justification' principle, what must project benefits be aligned to?
ARegular deliveries throughout the project
BThe business objectives
CThe direction of the project board
DThe technology available
✓ Verified Answer: A
Question #155Part 3
Which is a purpose of the 'closing a project' process?
ATo provide the project board with information to judge the success of a stage
BTo confirm the project has nothing more to deliver
CTo establish mechanisms to judge whether the project is still viable
DTo establish mechanisms for forecasting project objectives
✓ Verified Answer: D
Question #156Part 3
Which role represents the stakeholders who will operate the project's products after the project is complete?
AExecutive
BSenior user
CSenior supplier
DProject manager
✓ Verified Answer: B
Question #157Part 3
Which is a minimum requirement for applying the organization theme?
AEach member of the project management team must have a written role description
BThe roles of the project management team must be combined, wherever possible
CThe project manager must be appointed from the supplier organization
DThe frequency of communication to the project's stakeholders must be documented
✓ Verified Answer: D
Question #158Part 3
Which statement about time-driven controls is CORRECT?
ATime-driven controls are used for monitoring the progress of work packages and
BTime-driven controls take place when specific events happen
CTime-driven controls are produced at the end of a stage
DAn exception report is a time-driven control
✓ Verified Answer: D
Question #159Part 3
How does the project plan help to support the 'manage by stages' principle?
ABy identifying the customer's quality expectations
BBy defining products to ensure they are fit for purpose
CBy identifying the major control points and milestones
DBy estimating the timescales and costs of the project
✓ Verified Answer: C
Question #160Part 3
Which is a factor when deciding the duration of a management stage?
AThe work packages to be delivered
BThe level of risk in the project
CThe cost of the stage
DThe number of products to be produced in the project
✓ Verified Answer: B
Question #161Part 3
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
AThe senior user's responsibilities for realizing benefits
BStatements of actual versus forecast benefits at reviews
CThe management actions needed to ensure benefits are realized
DNo specific documents related to benefits are necessary
✓ Verified Answer: C
Question #162Part 3
According to PRINCE2, why might there be more than one business case for a project?
AThere may be more than one management stage in the project
BThe project may be in a commercial environment with a number of suppliers
CThere may be more than one work package being delivered in the project
DThe project may be in a programme environment
✓ Verified Answer: B
Question #163Part 3
Why is the 'initiating a project' process used?
ATo decide which project approach is suitable for the project
BTo fully understand how the project objectives will be achieved before committing significant
CTo produce the required work packages
DTo enable corporate or programme management to give authorization to deliver a project
✓ Verified Answer: D
Question #164Part 3
Which are purposes of the quality theme? 1. To implement continuous improvement during the project 2. To establish how the project will ensure that products created will be acceptable to key stakeholders 3. To ensure that the project is desirable and achievable 4. To identify, assess and control uncertainty
A1 and 2
B2 and 3
C3 and 4
D1 and 4
✓ Verified Answer: A
Question #165Part 3
What is performed as part of the recommended risk management procedure?
AA budget to investigate issues is allocated
BRisk management practices are reviewed to ensure that they are performed effectively
CInformation about risks to the projects is sent to project stakeholders
DConflicts between the project and the programme board are resolved
✓ Verified Answer: C
Question #166Part 3
Within which integrated element does PRINCE2 set minimum requirements?
AThemes
BProcesses
CPrinciples
DProject environment
✓ Verified Answer: B
Question #167Part 3
Which is a purpose of the 'controlling a stage' process?
ATo produce a team plan for the work to be assigned to a team manager
BTo select and implement actions that will resolve deviations from a plan within tolerance
CTo obtain approvals for products delivered in a work package
DTo update a project plan to incorporate the actuals from a stage plan
✓ Verified Answer: B
Question #168Part 3
Which role is responsible for the quality of the specialist products delivered in the project?
AExecutive
BSenior user
CSenior supplier
DProject assurance
✓ Verified Answer: C
Question #169Part 3
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
AA description of the risk management procedure
BAn explanation of the company's risk appetite
CThe names of the assigned actionees for each risk
DEstimations of the likelihood and impact of risks
✓ Verified Answer: A
Question #170Part 3
Identify the missing word in the following sentence. The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
Aactivities
Bprocesses
Cproducts
Dquality
✓ Verified Answer: B
Question #171Part 3
Which is a minimum requirement for applying the change theme?
ATo establish a change budget to fund changes in scope
BTo appoint the project manager as part of the change authority
CTo define the project's approach to baselining products
DTo record every issue that is raised in the issue register
✓ Verified Answer: C
Question #172Part 3
What should the 'managing product delivery' process ensure? 1. That the planned products meet their quality criteria 2. That the stage plan is kept up to date 3. That the project board is provided with progress information 4. That the planned products are delivered within tolerance
A1 and 2
B2 and 3
C3 and 4
D1 and 4
✓ Verified Answer: D
Question #173Part 3
According to the 'tailor to suit the project' principle, what is the basis for effective project management?
AThat the appropriate number and type of meetings are held
BThat the project is divided into an appropriate number of stages
CThat the appropriate information is provided to make decisions
DThat the project method relates to the project's environment
✓ Verified Answer: C
Question #174Part 3
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
AContinued business justification
BDefined roles and responsibilities
CManage by exception
DManage by stages
✓ Verified Answer: C
More PRINCE Certification Practice Exams
Explore related PRINCE exam dumps and free practice question banks.
PRINCE2-7-PRACTITIONER65 Questions
PRINCE2 7 Practitioner
PRINCE2-AGILE-PRACTITIONER35 Questions
PRINCE2 Agile Practitioner
PRINCE2-FOUNDATION65 Questions
PRINCE2 Foundation
PRINCE2-PRACTITIONER65 Questions
PRINCE2 Practitioner Edition 7
PRINCE2-PRACTITIONER-EDITION-665 Questions
PRINCE2 Practitioner Edition 6
PRINCE2-RE-REGISTRATION65 Questions
PRINCE2 Re-Registration
📢 Unlock Full Access to Success!
"The content displayed here is a promotional preview and contains only 50% of the actual exam database. To access the complete set of updated questions, please upgrade to the Full Version."
👉 Click the button and follow the instructions to secure your full access immediately!